Municipality Barangay Project Title Appropriation Source of Fund Contractor Status Remarks Actions
Municipality Barangay Project Title Appropriation Source of Fund Contractor Status Remarks Actions
KabayanPacsoImprovement of Mankeo FMR600,000.00SB #2, CY 2016QPJ General Engineering Const. & SupplyCompleted
KabayanBashoyReconstruction of Mt. Pulag Elementary School Building (3 Classroom)3,000,000.00Trust Fund LDRRMF 2016Jamil Sean ConstructionCompleted
KabayanLusodImprovement of Proper Lusod-Landing FMR1,000,000.00SB #1, CY 2017Jamil Sean ConstructionTemporarily suspended1) 1 suspension 2) Suspended since May 9, 2018 up to present (awaiting for CNC) 3) Update as of July 2019
KabayanBashoyImprovement of Abukot - Nandupit FMR500,000.0020% PDF CY 2017Vanvin Construction and SupplyCompleted
KabayanBallayConstruction of Flood Control at Kubo-Ballay250,000.0020% PDF 2018YKL-LHAT General ConstructionCompleted
KabayanPacsoRepair of Asokong Pacso Elementary School900,000.00SEF 2018Four Brothers ConstructionCompleted
KabayanBallayImprovement of Indaoac - Tinaleb - Barangay Road1,500,000.0020% PDF CY 2019Jamil Sean ConstructionCompleted
KabayanEddetConstruction of Retaining Wall & Widening of Sharp Curve500,000.00SB #1 CY 2019Vanvin Construction and supplyCompleted
KabayanGusaranConstruction of Flood Control with Spillway at Basil, Asokong6,000,000.0020% PDF 2019Jamil Sean ConstructionCompleted
KabayanPacsoRoad opening - Pacso500,000.00SB #1 CY 2019Jamil Sean constructionCompleted
KabayanPoblacionConstruction of Abapang Cotcot Access Road800,000.0020% PDF CY 2019Jamil Sean ConstructionCompleted
KabayanAdaoayImprovement of Lt. Alisandro Marquez Barangay Center500,000.00SB #1, CY 2019Vanvin Construction and SupplyCompleted
KabayanGusaranImprovement of Bakbakan - Akikian Farm to Market Road1,000,000.00SB #3 CY 2019 & 20% PDF CY 2019Vanvin Construction and SupplyCompleted1.) Revised target date of completion is: March 17, 2020; 2.) Actual date of completion is: March 17, 2020;
KabayanPacsoCompletion of Barangay Hall Extension500,000.00General Fund Vanvin Construction and SupplyCompletedActual date of completion: February 27, 2020.
KabayanBallayImprovement along Akikian-Lindawan (Besocol) FMR1,000,000.00SB #03 CY 2019Jamil Sean ConstructionCompleted1.) Suspended on March 17, 2020 due to community quarantine; 2.) Date resumed: September 4, 2020; 3.) Actual date of completion: October 12, 2020.
KabayanBatanRehabilitation of Lower Batan Farm to Market Road2,000,000.00LDRRMF Trust FundQPJ General Engineering Construction and SupplyCompletedActual date of completion: September 23, 2020.
KabayanGusaranConstruction of Flood Control at Gusaran3,000,000.00SB #3, 2019Vanvin Construction and SupplyCompleted
KabayanKabayan BarrioConstruction of Elbag to Kinapol Footbridge1,000,000.00SB #3 CY 2019Botjack ConstructionCompletedOriginal target date of completion: November 20, 2020
KabayanTawanganImprovement of Aw-awa to Ankatit Farm to Market Road1,500,000.00SB #3 CY 2019 & 20% PDFJamil Sean ConstructionCompleted
KabayanTawanganImprovement of Nanhabitan - Kapalan Farm to Market Road1,500,000.0020% PDF CY 2019Jamil Sean ConstructionCompleted
KabayanPacsoCompletion of One-Storey Building for Asokong Pacso Elementary School800,000.00SEF CY 2019Botjack ConstructionCompleted
KabayanAdaoayConcreting of Pavement along Upper Adaoay Farm to Market RoadSEF CY 2019CompletedDate completed: April 14, 2021
KabayanTawanganConstruction of Waterworks500,000.0020% PDF CY 2019Chrishua Construction ServicesCompletedActual date of completion: May 7, 2021
KabayanPacsoConstruction of Dampeg - Mankew Farm to Market Road2,000,000.00General Fund 2020CompletedDate completed: April 20, 2021
KabayanKabayan BarrioConstruction of Waterworks System from Pikaw Spring Farm to Tumol1,000,000.0020% PDF CY 2020CompletedDate completed: March 27, 2021
KabayanBallayConstruction of Sidewalk with Railings along Tinaleb Elementary School600,000.00SEF CY 2020CompletedDate completed: March 25, 2021
KabayanPoblacionRehabilitation of Six (6) Sources of Potable Water and PipelinesLDRRMF - Trust FundCompletedDate completed: April 26, 2021
KabayanDuacanConstruction of CICL and VAWC Refugee Center1,000,000.00General Fund CY 2020CompletedDate of completion: May 18, 2021
KabayanEddetReconstruction of Datuan Footbridge2,000,000.00General Fund CY 2020Completed2021
KabayanEddetConstruction of Eddet Barangay Hall Comfort Rooms375,000.00General Fund CY 2015 SB No. 5 CY 2015akiki builders/ ruben aguinseCompletedCompleted and usable with liquidated damages
KabayanAdaoayConstruction of Cattle Barn/Shed at Adaoay500,000.0020% PDF CY 2015solonio construction/ritchie solonioCompletedCompleted and usable with underrun
KabayanBallayImprovement along Bagto - Bacanganga FMR1,000,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanGusaranConstruction of Shed, Barangay Ground1,500,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanGusaranConstruction of Culture and Arts Building at Kamora National High School (Phase 2)1,000,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanBallayImprovement of Tongotong FMR1,500,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Dinamili - Bolagabog Takitak FMR1,070,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBashoya) Construction (Extension/Continutation) of FMR along Palansa - Pinanshay b)Widening and Construction of FMR access along Palansa - Pinanshay 450,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanBallayImprovement along Besocol FMR500,000.0020% PDF CY 2016Akiki BuildersCompleted
KabayanBallayTirepathing of Upper Dumipayas100,000.0020% PDF CY 2016Akiki BuildersCompletedproject contract cluster "D" a)tirepathing of upper dumipayas ballay, kabayan b)const. of tirepath along kubo-tinaleb fmr ballay,kabayan both located @ ballay, kabayan, benguet
KabayanBallayConstruction of Tirepath along Kubo - Tinaleb FMR100,000.0020% PDF CY 2016Akiki BuildersCompleted contract cluster "D" a)tirepathing of upper dumipayas ballay, kabayan b)const. of tirepath along kubo-tinaleb fmr ballay,kabayan both located @ ballay, kabayan, benguet
KabayanLusodImprovement of Baay - Ballay - Lusod FMR (Proper Lusod Section)980,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedCLUSTERED Control No.: b) 02-16-00085 - Jamil Sean
KabayanBallayImprovement along Lower Taaw FMR980,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedCLUSTERED Control No.: a) 02-16-00084 - Jamil Sean Construction
KabayanGusaranConstruction of Sub-Clinic800,000.0020% PDF CY 2016Solonio ConstructionCompletedCompleted and usable with underrun and liquidated damages.
KabayanBashoyConstruction of Tirepath along Nandupit Junction along Dumamay FMR250,000.0020% PDF CY 2016Solonio ConstructionCompletedCompleted and usable with underrun and liquidated damages
KabayanTawangana) Tawangan - Lusod National High School Ground Levelling with Riprap and Retaining Wall b) Riprap and Leveling of Lusod-Tawangan National High School Grounds1,500,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedcontract a)riprapping & improvement of Lusod-Tawangan national high school grounds @ tawangan, kabayan, benguet B)riprap of lusod-tawangan national high school ground @ tawangan kabayan be
KabayanBallayImprovement of Dinamili - Tinaleb FMR500,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedClustered L projects - b) imp of tinaleb - naybo FMR @ Ballay, Kabayan; c) imp of tinaleb - pangawan FMR @ Ballay, kabayan
KabayanBallayImprovement along Taaw - Kubo FMR1,000,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Tinaleb - Naybo FMR500,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Tinaleb - Pangawan FMR500,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedClustered L projects - b) imp of tinaleb - naybo FMR @ Ballay, Kabayan; c) imp of tinaleb - pangawan FMR @ Ballay, kabayan
KabayanEddetConstruction of Eddet Elementary School Stage800,000.0020% PDF CY 2016Akiki BuildersCompletedCompleted on February 27, 2018
KabayanTawanganImprovement of Proper Nakilo FMR, Tawangan1,000,000.0020% PDF CY 2016CompletedCompleted on September 9, 2016
KabayanAnchukeyImprovement of Upper Agat Rice Field Access200,000.0020% PDF CY 20164 Brothers ConstructionCompletedCluster "A" - 4 Brothers Construction
KabayanAnchukeyConstruction of Tirepath along Anchukey, Baok150,000.0020% PDF CY 20164 Brothers ConstructionCompletedCluster "A" - 4 Brothers Construction
KabayanAnchukeyConstruction of Tirepath along Anchokey FMR100,000.0020% PDF CY 20164 Brothers ConstructionCompletedCluster "A" - 4 Brothers Construction
KabayanTawanganCompletion of Multi-Purpose Building (Phase II), Tawangan, Kabayan500,000.0020% PDF 2016Akiki BuildersCompleted
KabayanBallayImprovement of Basketball Court in Besocol, Ballay300,000.0020% PDF 2016Four Brothers ConstructionCompleted
KabayanPacsoConstruction of Barangay Multi-Purpose Building/Hall Comfort Room500,000.0020% PDF 2016Akiki BuildersTerminated1 suspension. Suspended on December 10, 2018 due to site problem
KabayanDuacanImprovement of Bekes - Balangbang FMR500,000.0020% PDF CY 2017Akiki BuildersCompleted
KabayanTawanganImprovement of Nadaklan - Pangaya FMR500,000.0020% PDF CY 2017Jamil Sean ConstructionCompleted
KabayanGusaranConcreting of Adereg - Aponan Footpath200,000.0020% PDF CY 2017Jamil Sean ConstructionCompleted
KabayanKabayan BarrioConstruction of Cauliflower Drying Shed, Balaban500,000.0020% PDF CY 2017Solonio ConstructionCompletedCompleted on March 20, 2018 with liquidated damages
KabayanGusaranImprovement / Construction of PCCP along National Road Junction - Diboong - Bangao Provincial Road5,000,000.0020% PDF CY 2017Kuatako Construction and General ConstructionCompletedCompleted on September 17, 2017 with PCCP deficiency
KabayanEddetImprovement of Balang-Sokong-Pinanchay-Talukip-Cable FMR, Eddet, Kabayan500,000.002017 20% PDFCompleted
KabayanAnchokeyConstruction of Tirepath Along Anchokey FMR, Abat, Anchokey500,000.0020% PDF 2017Four BrothersCompleted
KabayanPacsoImprovement of Apanberang-Washington Acess Road, Pacso, Kabayan500,000.0020% PDF 2017Four Brothers ConstructionCompleted
KabayanGusaranImprovement of Farm to Market Road at Maebat600,000.0020% PDF 2017Jamil Sean ConstructionCompletedSuspended effective November 29, 2018 due to closed access road caused uncleared slides on various sections 1 suspension
KabayanPacsoRoad Opening Pacso, Kabayan500,000.0020% PDF 2017Akiki BuildersTerminated
KabayanBallayImprovement of Ballay liang to taaw FMR2,000,000.0020% PDF 2018Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Barangay Road at Tinaleb, Ballay, Kabayan, Benguet500,000.0020% PDFCompleted
KabayanGusaranConstruction of PCCP Along National Road JCT - Diboong - Bangao Provincial Road at Kabayan20% PDF 2018Solonio Construction (Ritchie Solonio)TerminatedTerminated due to site problem. Contract terminated as of June 28, 2019
KabayanBallayImprovement of Inuman WWS, Ballay150,000.00SB #2 - 2015 & 20%PDF-2016Four BrothersCompleted
KabayanEddetConstruction of Eddet Waterworks System1,000,000.00SB No. 5 CY 2015CompletedCompleted and usable with underrun and liquidated damages.
KabayanBatanImprovement of Batan FMR150,000.00SB No. 5 CY 20154 Brothers ConstructionCompleted
KabayanPoblacionImprovement of Poblacion Barangay Hall1,000,000.00SB No. 5 CY 2015Akiki BuildersCompleted90.00% Completed with liquidated damages - Total Cost Incurred PhP 898,621.05 as of March 2018; post-inspected on January 15, 2018
KabayanBashoyImprovement of Day Care Center, Pulag, Bashoy800,000.00SB No. 5 CY 2015Aroboan ConstructionCompletedCompleted on February 22, 2018
KabayanBatanConstruction of Bajeng Waterworks System, Batan200,000.00SB #5 - 2015Four BrothersCompleted
KabayanBallayImprovement of Unnoy - Taaw FMR1,000,000.00SB No. 2 CY 2016Completed
KabayanTawanganImprovement of Lusod - Tawangan National High School Road at Tawangan400,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanBatanRehabilitation of Penged Waterworks System500,000.00SB No. 2 CY 2016Sangin General ConstructionCompletedCompleted and usable with liquidated damages
KabayanBallayImprovement of Bagto - Akikian FMR at Ballay300,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanBallayConstruction of Riprap along Tinaleb FMR at Ballay500,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanGusaranImprovement of Road at Bangao - Gusaran500,000.00SB No. 2 CY 2016Solonio ConstructionCompleted
KabayanGusaranConstruction of Footpath at Tekeng - Mogaben, Gusaran, Kabayan250,000.00SB No. 2 CY 2016Akiki BuildersCompleted95.00% Completed with liquidated damages - Total Cost Incurred PhP 236,829.11 as of March 2018; Post-inspected on January 5, 2018
KabayanGusaranConstruction of Footpath at Naysuyoc250,000.00SB No. 2 CY 2016Akiki BuildersCompleted
KabayanAdaoayConcreting of Pathway along Adaoay National High School, Binado300,000.00SB No. 2 CY 2016Akiki BuildersCompleted
KabayanTawanganImprovement of Lubban - Hahagod FMR200,000.00SB No. 3 CY 2016Completed
KabayanAdaoayExtension of COMPAC at Adaoay500,000.00SB No. 4 CY 2016Completed
KabayanBallayGround Levelling and Construction of Retaining Wall at Ballay Elementary School Coumpound1,000,000.00SB # 1 2017Jamil Sean ConstructionCompleted
KabayanTawanganImprovement of Talabing - Tinoc Road, Tawangan12,000,000.00PAMANA 2016Cabuguisan BuildersTerminated1) 44.6821% completion which is equivalent to Php 4,202,384.37 2) Project terminated for default
KabayanTawanganLeveling and Improvement of Tawangan Elementary School Ground, Tawangan Kabayan300,000.00SB No. 2, 2016Akiki BuildersCompleted
KabayanKabayan BarrioGround Improvement of Kamora National High School500,000.00SEF CY 2016Completed
KabayanBallayConstruction of Fence at Ballay Elementary School, Ballay, Kabayan500,000.00SEF 2017Haight's ConstructionTerminated
KabayanBatanImprovement of KM 49 - Ambakian FMR203,655,000.00PRDPFIAT CONSTRUCTION SERVICESTerminated1) On-going with 15.29% accomplishment - Total Cost Incurred PhP 30,302,134.38 as of March 2018 with 9.35% slippage 2) Suspended as of November 15, 2017 for the preparation of Variation Order. 3) Still suspended as of October 2018