Municipality Barangay Project Title Appropriation Source of Fund Contractor Status Remarks Actions
Municipality Barangay Project Title Appropriation Source of Fund Contractor Status Remarks Actions
KabayanPacsoImprovement of Multi-Purpose Hall, Apanberang300,000.00SB No. 5 CY 2015 GFAlmond Engineering and Construction Rogelio AlimondoCompleted
KabayanPacsoConstruction of Barangay Health Station (Phase III)500,000.00General Fund - Non Office 2015Solonio ConstructionCompleted
KabayanPacsoImprovement of Mankeo FMR600,000.00SB #2, CY 2016QPJ General Engineering Const. & SupplyCompleted
KabayanTawanganImprovement Along Talabing - Tinoc Road, Tawangan, Kabayan8,974,516.34Pamana 2016Jamil - Sean ConstructionCompleted1) Completed on February 3, 2018
KabayanBashoyReconstruction of Mt. Pulag Elementary School Building (3 Classroom)3,000,000.00Trust Fund LDRRMF 2016Jamil Sean ConstructionCompleted
KabayanLusodImprovement of Proper Lusod-Landing FMR1,000,000.00SB #1, CY 2017Jamil Sean ConstructionTemporarily suspended1) 1 suspension 2) Suspended since May 9, 2018 up to present (awaiting for CNC) 3) Update as of July 2019
KabayanLusodConstruction of Lusod Footbridge1,000,000.00SB #1, CY 2017Haight's ConstructionCompletedCompleted with revised target date of November 29, 2018 for preparation of voucher
KabayanBashoyImprovement of Abukot - Nandupit FMR500,000.0020% PDF CY 2017Vanvin Construction and SupplyCompleted
KabayanBallayImprovement of Barangay Road at Toneleg, Ballay 500,000.0020% PDF CY 2018Jamil Sean ConstructionCompletedCompleted - October 5, 2018
KabayanBallayConstruction of Flood Control at Kubo-Ballay250,000.0020% PDF 2018YKL-LHAT General ConstructionCompleted
KabayanPacsoRepair of Asokong Pacso Elementary School900,000.00SEF 2018Four Brothers ConstructionCompleted
KabayanBallayImprovement of Indaoac - Tinaleb - Barangay Road1,500,000.0020% PDF CY 2019Jamil Sean ConstructionCompleted
KabayanEddetConstruction of Retaining Wall & Widening of Sharp Curve500,000.00SB #1 CY 2019Vanvin Construction and supplyCompleted
KabayanGusaranConstruction of Flood Control with Spillway at Basil, Asokong6,000,000.0020% PDF 2019Jamil Sean ConstructionCompleted
KabayanPacsoRoad opening - Pacso500,000.00SB #1 CY 2019Jamil Sean constructionCompleted
KabayanPoblacionConstruction of Abapang Cotcot Access Road800,000.0020% PDF CY 2019Jamil Sean ConstructionCompleted
KabayanAdaoayImprovement of Lt. Alisandro Marquez Barangay Center500,000.00SB #1, CY 2019Vanvin Construction and SupplyCompleted
KabayanGusaranImprovement of Bakbakan - Akikian Farm to Market Road1,000,000.00SB #3 CY 2019 & 20% PDF CY 2019Vanvin Construction and SupplyCompleted1.) Revised target date of completion is: March 17, 2020; 2.) Actual date of completion is: March 17, 2020;
KabayanPacsoCompletion of Barangay Hall Extension500,000.00General Fund Vanvin Construction and SupplyCompletedActual date of completion: February 27, 2020.
KabayanBallayImprovement of Darat-Lower Tamangan Farm to Market Road3,000,000.00SB #03 CY 2019Jamil Sean ConstructionCompleted
KabayanBallayImprovement along Taaw-Luban FMR1,000,000.00SB #03 CY 2019Jamil Sean ConstructionCompleted
KabayanBallayImprovement along Akikian-Lindawan (Besocol) FMR1,000,000.00SB #03 CY 2019Jamil Sean ConstructionCompleted1.) Suspended on March 17, 2020 due to community quarantine; 2.) Date resumed: September 4, 2020; 3.) Actual date of completion: October 12, 2020.
KabayanBatanRehabilitation of Lower Batan Farm to Market Road2,000,000.00LDRRMF Trust FundQPJ General Engineering Construction and SupplyCompletedActual date of completion: September 23, 2020.
KabayanGusaranConstruction of Flood Control at Gusaran3,000,000.00SB #3, 2019Vanvin Construction and SupplyCompleted
KabayanEddetConstruction of Eddet Barangay Hall Comfort Rooms375,000.00General Fund CY 2015 SB No. 5 CY 2015akiki builders/ ruben aguinseCompletedCompleted and usable with liquidated damages
KabayanLusodConstruction of Cabulao - Hoyocto FMR500,000.0020% PDF CY 20154 Brothers ConstructionCompletedCompleted and usable with underrun
KabayanAdaoayConstruction of Cattle Barn/Shed at Adaoay500,000.0020% PDF CY 2015solonio construction/ritchie solonioCompletedCompleted and usable with underrun
KabayanBashoyImprovement of Grounds Bashoy Multi-Purpose Warehouse and Nursery Site500,000.0020% PDF CY 20154 Brothers ConstructionCompletedCompleted and usable with underrun
KabayanLusodImprovement of Riprap along Portions of Baay-Madayag FMR300,000.0020% PDF CY 2015Akiki BuildersCompletedwith liquidated damages
KabayanBallayImprovement along Bagto - Bacanganga FMR1,000,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanGusaranConstruction of Shed, Barangay Ground1,500,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanGusaranConstruction of Culture and Arts Building at Kamora National High School (Phase 2)1,000,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanBallayImprovement of Tongotong FMR1,500,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Dinamili - Bolagabog Takitak FMR1,070,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBashoya) Construction (Extension/Continutation) of FMR along Palansa - Pinanshay b)Widening and Construction of FMR access along Palansa - Pinanshay 450,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanBallayImprovement along Besocol FMR500,000.0020% PDF CY 2016Akiki BuildersCompleted
KabayanBallayTirepathing of Upper Dumipayas100,000.0020% PDF CY 2016Akiki BuildersCompletedproject contract cluster "D" a)tirepathing of upper dumipayas ballay, kabayan b)const. of tirepath along kubo-tinaleb fmr ballay,kabayan both located @ ballay, kabayan, benguet
KabayanBallayConstruction of Tirepath along Kubo - Tinaleb FMR100,000.0020% PDF CY 2016Akiki BuildersCompleted contract cluster "D" a)tirepathing of upper dumipayas ballay, kabayan b)const. of tirepath along kubo-tinaleb fmr ballay,kabayan both located @ ballay, kabayan, benguet
KabayanLusodImprovement of Baay - Ballay - Lusod FMR (Proper Lusod Section)980,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedCLUSTERED Control No.: b) 02-16-00085 - Jamil Sean
KabayanBallayImprovement along Lower Taaw FMR980,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedCLUSTERED Control No.: a) 02-16-00084 - Jamil Sean Construction
KabayanLusodRoad Opening at Lusod - Dagdag FMR2,300,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedCompleted on March 6, 2018
KabayanGusaranConstruction of Sub-Clinic800,000.0020% PDF CY 2016Solonio ConstructionCompletedCompleted and usable with underrun and liquidated damages.
KabayanBashoyConstruction of Tirepath along Nandupit Junction along Dumamay FMR250,000.0020% PDF CY 2016Solonio ConstructionCompletedCompleted and usable with underrun and liquidated damages
KabayanBatanImprovement of Washington - Colong - Bajen - Agpay FMR250,000.0020% PDF CY 20164 Brothers ConstructionCompletedClustered a) imp of Batan FMR; b) imp of washington-colong-bajen-agpay FMR @ Batan, Kabayan
KabayanTawangana) Tawangan - Lusod National High School Ground Levelling with Riprap and Retaining Wall b) Riprap and Leveling of Lusod-Tawangan National High School Grounds1,500,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedcontract a)riprapping & improvement of Lusod-Tawangan national high school grounds @ tawangan, kabayan, benguet B)riprap of lusod-tawangan national high school ground @ tawangan kabayan be
KabayanBallayImprovement of Dinamili - Tinaleb FMR500,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedClustered L projects - b) imp of tinaleb - naybo FMR @ Ballay, Kabayan; c) imp of tinaleb - pangawan FMR @ Ballay, kabayan
KabayanBallayImprovement along Taaw - Kubo FMR1,000,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Tinaleb - Naybo FMR500,000.0020% PDF CY 2016Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Tinaleb - Pangawan FMR500,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedClustered L projects - b) imp of tinaleb - naybo FMR @ Ballay, Kabayan; c) imp of tinaleb - pangawan FMR @ Ballay, kabayan
KabayanEddetConstruction of Eddet Elementary School Stage800,000.0020% PDF CY 2016Akiki BuildersCompletedCompleted on February 27, 2018
KabayanBashoyConstruction of Comfort Room, Bashoy, Kabayan600,000.0020% PDF CY 2016Akiki BuildersCompletedCompleted on February 15, 2018
KabayanBallayImprovement of Liang FMR, Ballay500,000.0020% PDF CY 2016CompletedCompleted on July 18, 2016
KabayanBallayImprovement along Tamangan FMR, Ballay500,000.0020% PDF CY 2016CompletedCompleted on July 12, 2016
KabayanTawanganImprovement of Proper Nakilo FMR, Tawangan1,000,000.0020% PDF CY 2016CompletedCompleted on September 9, 2016
KabayanAnchukeyImprovement of Upper Agat Rice Field Access200,000.0020% PDF CY 20164 Brothers ConstructionCompletedCluster "A" - 4 Brothers Construction
KabayanAnchukeyConstruction of Tirepath along Anchukey, Baok150,000.0020% PDF CY 20164 Brothers ConstructionCompletedCluster "A" - 4 Brothers Construction
KabayanEddetImprovement of Nanchupit FMR, Eddet1,000,000.0020% PDF CY 2016CompletedCompleted on August 31, 2016
KabayanTawanganImprovement of Proper Nambangawan FMR500,000.0020% PDF CY 2016CompletedCompleted on August 11, 2016
KabayanAnchukeyConstruction of Tirepath along Anchokey FMR100,000.0020% PDF CY 20164 Brothers ConstructionCompletedCluster "A" - 4 Brothers Construction
KabayanAnchokeyConstruction of Tirepath along Anchokey FMR, Baok150,000.0020% PDF CY 2016CompletedCompleted on September 28, 2016
KabayanBallayConstruction of Riprap along Tuidan FMR250,000.0020% PDF CY 2016Jamil Sean ConstructionCompletedCompleted on October 4, 2016
KabayanPacsoImprovement of Sitio Champeg Waterworks System200,000.0020% PDF CY 2016Solonio ConstructionCompletedCompleted on October 18, 2016
KabayanTawanganCompletion of Tawangan Multi-Purpose Building/Hall100,000.0020% PDF CY 2016Haight's ConstructionCompleted
KabayanBallayImprovement of Minac-Batuan FMR, Ballay, Kabayan800,000.0020% PDF CY 2016Solonio ConstructionCompleted
KabayanTawanganCompletion of Multi-Purpose Building (Phase II), Tawangan, Kabayan500,000.0020% PDF 2016Akiki BuildersCompleted
KabayanBallayImprovement of Basketball Court in Besocol, Ballay300,000.0020% PDF 2016Four Brothers ConstructionCompleted
KabayanPacsoConstruction of Barangay Multi-Purpose Building/Hall Comfort Room500,000.0020% PDF 2016Akiki BuildersTerminated1 suspension. Suspended on December 10, 2018 due to site problem
KabayanDuacanImprovement of Bekes - Balangbang FMR500,000.0020% PDF CY 2017Akiki BuildersCompleted
KabayanTawanganImprovement of Nadaklan - Pangaya FMR500,000.0020% PDF CY 2017Jamil Sean ConstructionCompleted
KabayanGusaranConcreting of Adereg - Aponan Footpath200,000.0020% PDF CY 2017Jamil Sean ConstructionCompleted
KabayanKabayan BarrioConstruction of Cauliflower Drying Shed, Balaban500,000.0020% PDF CY 2017Solonio ConstructionCompletedCompleted on March 20, 2018 with liquidated damages
KabayanGusaranImprovement / Construction of PCCP along National Road Junction - Diboong - Bangao Provincial Road5,000,000.0020% PDF CY 2017Kuatako Construction and General ConstructionCompletedCompleted on September 17, 2017 with PCCP deficiency
KabayanBallayConstruction of Concrete Canal and Riprapping along Dimipiyas FMR500,000.0020% PDF CY 2017Jamil Sean ConstructionCompletedCompleted on March 23, 2018
KabayanLusodImprovement of Proper Lusod Ba-ayan FMR500,000.0020% PDF CY 2017Jamil Sean ConstructionCompletedCompleted on March 21, 2018 - for Post inspection
KabayanBatanConstruction of Multi-Purpose Building, Bajen (Phase I and Phase II)800,000.0020% PDF CY 2017Sangin ConstructionCompleted
KabayanEddetImprovement of Balang-Sokong-Pinanchay-Talukip-Cable FMR, Eddet, Kabayan500,000.002017 20% PDFCompleted
KabayanAnchokeyConstruction of Tirepath Along Anchokey FMR, Abat, Anchokey500,000.0020% PDF 2017Four BrothersCompleted
KabayanPacsoImprovement of Apanberang-Washington Acess Road, Pacso, Kabayan500,000.0020% PDF 2017Four Brothers ConstructionCompleted
KabayanGusaranImprovement of Farm to Market Road at Maebat600,000.0020% PDF 2017Jamil Sean ConstructionCompletedSuspended effective November 29, 2018 due to closed access road caused uncleared slides on various sections 1 suspension
KabayanPacsoRoad Opening Pacso, Kabayan500,000.0020% PDF 2017Akiki BuildersTerminated
KabayanBallayImprovement of Ballay liang to taaw FMR2,000,000.0020% PDF 2018Jamil Sean ConstructionCompleted
KabayanBallayImprovement of Barangay Road at Tinaleb, Ballay, Kabayan, Benguet500,000.0020% PDFCompleted
KabayanGusaranConstruction of PCCP Along National Road JCT - Diboong - Bangao Provincial Road at Kabayan20% PDF 2018Solonio Construction (Ritchie Solonio)TerminatedTerminated due to site problem. Contract terminated as of June 28, 2019
KabayanEddeta) Consruction of Daket-Oguban Footbridge, Eddet, Kabayan; b) Construction of Daket-Oguban Footbridge, Eddet (Additional)1,764,000.00 20% PDF-2014 & SB # 02 - 2016Random BuildersCompleted
KabayanBallayImprovement of Inuman WWS, Ballay150,000.00SB #2 - 2015 & 20%PDF-2016Four BrothersCompleted
KabayanPacsoConstruction of Mangoto Day Care Center (Phase 1 and Phase 2)1,050,000.0020% PDF CY 2015 SB No. 2 CY 2016Bosongan ConstructionCompletedCompleted on February 25, 2018
KabayanBallayConstruction of Multi-Purpose Building at Tinaleb1,000,000.00SB No. 5 CY 2015CompletedCompleted and usable with liquidated damages
KabayanEddetConstruction of Eddet Waterworks System1,000,000.00SB No. 5 CY 2015CompletedCompleted and usable with underrun and liquidated damages.
KabayanBatanImprovement of Batan FMR150,000.00SB No. 5 CY 20154 Brothers ConstructionCompleted
KabayanPoblacionImprovement of Poblacion Barangay Hall1,000,000.00SB No. 5 CY 2015Akiki BuildersCompleted90.00% Completed with liquidated damages - Total Cost Incurred PhP 898,621.05 as of March 2018; post-inspected on January 15, 2018
KabayanBashoyImprovement of Day Care Center, Pulag, Bashoy800,000.00SB No. 5 CY 2015Aroboan ConstructionCompletedCompleted on February 22, 2018
KabayanTawanganRiprap of Lusod - Tawangan NHS Grounds at Tawangan1,000,000.00SB No. 5 CY 2015 GFCompletedCompleted on July 18, 2016
KabayanBatanConstruction of Bajeng Waterworks System, Batan200,000.00SB #5 - 2015Four BrothersCompleted
KabayanBallayImprovement of Unnoy - Taaw FMR1,000,000.00SB No. 2 CY 2016Completed
KabayanTawanganImprovement of Lusod - Tawangan National High School Road at Tawangan400,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanBatanRehabilitation of Penged Waterworks System500,000.00SB No. 2 CY 2016Sangin General ConstructionCompletedCompleted and usable with liquidated damages
KabayanBallayImprovement of Bagto - Akikian FMR at Ballay300,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanBallayConstruction of Riprap along Taaw FMR at Ballay200,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanBallayConstruction of Riprap along Tinaleb FMR at Ballay500,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompleted
KabayanGusaranImprovement of Road at Bangao - Gusaran500,000.00SB No. 2 CY 2016Solonio ConstructionCompleted
KabayanGusaranConstruction of Footpath at Tekeng - Mogaben, Gusaran, Kabayan250,000.00SB No. 2 CY 2016Akiki BuildersCompleted95.00% Completed with liquidated damages - Total Cost Incurred PhP 236,829.11 as of March 2018; Post-inspected on January 5, 2018
KabayanGusaranConstruction of Footpath at Naysuyoc250,000.00SB No. 2 CY 2016Akiki BuildersCompleted
KabayanAdaoayConcreting of Pathway along Adaoay National High School, Binado300,000.00SB No. 2 CY 2016Akiki BuildersCompleted
KabayanLusodConstruction of Community Public Comfort Rooms at Proper Lusod300,000.00SB No. 2 CY 2016Completed
KabayanTawanganImprovement of Lubban - Hahagod FMR200,000.00SB No. 3 CY 2016Completed
KabayanAdaoayExtension of COMPAC at Adaoay500,000.00SB No. 4 CY 2016Completed
KabayanTawangana) Improvement of Kapalan FMR at Tawangan b) Improvement of Nanhabitan - Kapalan Extension FMR1,000,000.00SB No. 2 CY 2016Jamil Sean ConstructionCompletedCompleted: 07/08/2018 Revised target date of completion: per suspension order no. 1 is on 07/24/2018
KabayanBallayGround Levelling and Construction of Retaining Wall at Ballay Elementary School Coumpound1,000,000.00SB # 1 2017Jamil Sean ConstructionCompleted
KabayanLusod Consruction of Lusod Proper Footbridge, Lusod, Kabayan1,000,000.00SB # 01 - 2017Haight's ConstructionCompletedCompleted with 1 suspension and 1 extension Revised Target Date =11/21/2018
KabayanGusaranImprovement along National Road Junction - Diboong - Bangao Provincial Road2,000,000.00LDRRMF CY 2016Completed
KabayanGusaranRehabilitation of Diboong Provincial Road1,000,000.00LDRRMF Trust FundCompletedFor updating of actual Completion
KabayanBallayConstruction of Retaining Wall along Liang-Taaw FMR, Ballay, Kabayan350,000.00LDRRMF CY 2016 - TRUST FUNDJamil Sean ConstructionCompleted
KabayanGusaranGround Development at Kamora NHS500,000.00PSBF CY 2016Completed
KabayanTawanganImprovement of Talabing - Tinoc Road, Tawangan12,000,000.00PAMANA 2016Cabuguisan BuildersTerminated1) 44.6821% completion which is equivalent to Php 4,202,384.37 2) Project terminated for default
KabayanTawanganLeveling and Improvement of Tawangan Elementary School Ground, Tawangan Kabayan300,000.00SB No. 2, 2016Akiki BuildersCompleted
KabayanKabayan BarrioGround Improvement of Kamora National High School500,000.00SEF CY 2016Completed
KabayanBallayConstruction of Fence at Ballay Elementary School, Ballay, Kabayan500,000.00SEF 2017Haight's ConstructionTerminated
KabayanBallayConstruction of Fence at Pallay Elementary School,Ballay,Kabayan,Benguet500,000.00SEF-2017YKJ-LHAT General ConstructionCompleted
KabayanBatanImprovement of KM 49 - Ambakian FMR203,655,000.00PRDPFIAT CONSTRUCTION SERVICESTerminated1) On-going with 15.29% accomplishment - Total Cost Incurred PhP 30,302,134.38 as of March 2018 with 9.35% slippage 2) Suspended as of November 15, 2017 for the preparation of Variation Order. 3) Still suspended as of October 2018