Tuba | Yagyagan | Improvement along Yagyagan-Ampusa Provincial Road | Road Pavement and Riprap | 3,500,000.00 | 3,355,654.43 | Pulicay Grandsons | 20% PDF 2019 | 2019-10-08 | 2020-08-01 | Completed | |
Sablan | Banangan | Improvement of FBB AWASAI Water Works System | Water Works | 2,500,000.00 | 2,492,167.26 | Anas Construction | 20% PDF CY 2018 | 2019-10-21 | 2020-03-14 | Completed | |
Kapangan | Lomon | Improvement of Lomon - Kapangan Provincial Road | Road | 4,600,000.00 | 4,563,281.78 | | 20% PDF CY 2019 | 2020-03-11 | 2020-07-27 | Completed | |
Itogon | Ampucao | Improvement of FMR at Pasiday-Tocod-Sigsiglay, Ampucao, Itogon | FMR | 1,000,000.00 | 931,078.83 | | 20% PDF 2019 | 2019-08-08 | 2020-10-01 | Completed | |
Itogon | Tinongdan | Construction of Shed Leading Towards the Emergency Room | Building | 1,000,000.00 | 997,933.89 | Reko Gen. Konstruct | General Fund - All Offices CY 2016 | 2018-04-16 | 0000-00-00 | Completed | Completed on June 7, 2018. |
Buguias | Amlimay | Opening of Bana-ao - Mangakew FMR | Roads | 500,000.00 | 486,428.46 | Jamil Sean Construction | General Fund CY 2014 | 2017-01-31 | 2017-05-08 | Completed | Completed with underrun and LD |
La Trinidad | Wangal | Improvement of Existing Cold Chain Building at the Benguet Cold Chain Project | Building Improvement | 2,000,000.00 | 1,910,419.00 | Anitos Construction | 20% PDF CY 2014 Resolution No. 2017-74 | 2020-01-29 | 2020-08-05 | Completed | Completed with change order.
|
Itogon | Tinongdan | Construction of Guardhouse at Itogon District Hospital | Building | 180,000.00 | 179,358.73 | Bemada Construction | SB No. 2 CY 2015 & 2015 20% PDF | 2018-07-26 | 2018-08-29 | Completed | completed and usable |
La Trinidad | Wangal | Reconstruction of Walkway Shed from Main road to Benguet National High School, Benguet Sped Center and Benguet Sports Center Multi-Purpose Gym | Road Side | 1,500,000.00 | 1,497,847.32 | Sharamelle Construction & Gen. Eng'g | 20% PDF CY 2015 | 2018-05-18 | 2018-07-28 | Completed | 1) Completed with Liquidated Damages
2) Revised Target Date of Completion is on September 12, 2018 |
Bokod | Ambuklao | Construction of Comfort Rooms at Patadan, Banao, Ambuklao, Bokod, Benguet | Semi-permanent Structure | 400,000.00 | 394,797.91 | Pulicay Grandsons Construction | General Fund - 2015 | 2018-07-06 | 2018-08-15 | Completed | |
Sablan | Banangan | Construction of Keddeng - Batag Footpath | Footpath | 150,000.00 | 149,078.13 | Anas Construction | SB #5, CY 2015 | 2018-10-05 | 2018-10-27 | Terminated | Suspended as of October 2018.
Mutual termination. |
Tuba | San Pascual | Construction of Perimeter and divisional fence | Construction of fence | 1,000,000.00 | 993,610.65 | DMCD Engineering and Construction | 20% PDF 2015 | 2018-05-18 | 2018-08-14 | Completed | Ongoing. Revised Target Date = 06/27/2019. Issued w/ Notice of Pre-termination.Show cause letter was submitted by the contractor for verification.
|
La Trinidad | Tawang | Improvement of Barangay Hall Ground (Basketball Court) | Improvement | 100,000.00 | 94,446.42 | AKIP Construction and Enterprises | General Fund 2015 Non Office | 2018-04-25 | 2018-05-11 | Completed | |
Tuba | Taloy Sur | Improvement of Extension of Asinan-Soysoyan-Doyong FMR, Taloy Sur, Tuba, Benguet | Road Opening and PCCP | 1,500,000.00 | 1,497,494.80 | Ruben Ronas Construction | General Fund 2015 Non Office | 0000-00-00 | 0000-00-00 | Terminated | Recommended for mutual termination due to site problem |
Kapangan | Gaswiling | Improvement of Barangay Hall Toilet | Toilet Construction | 120,000.00 | 118,668.33 | Vanket Engineering & Construction | General Fund-2015 | 2018-11-28 | 2018-12-24 | Completed | Completed w/ LD |
Atok | Caliking | Completion of 4-classroom two-storey building in Atok National High School - Annex | Building | 2,000,000.00 | 1,957,532.66 | Rigne Construction | SEF-2015 | 2020-02-24 | 2020-09-21 | Completed | Suspended due to community quarantine. |
Kapangan | Balakbak | Repair of public comfort room and installation of waterworks system, Balakbak, Kapangan | Building Repair | 500,000.00 | 499,083.53 | | GENERAL FUND - NON OFFICE CY 2015 | 0000-00-00 | 0000-00-00 | Completed | |
Kapangan | Labueg | Construction of Labueg Barangay Hall | Building | 500,000.00 | 498,830.86 | | GENERAL FUND - NON OFFICE CY 2015 | 2015-07-08 | 0000-00-00 | Completed | |
Kapangan | Datakan | Improvement of Datakan Multi-purpose Building (Barangay Hall) Datakan | Building | 700,000.00 | 698,254.90 | | GENERAL FUND - NON OFFICE CY 2015 | 2015-11-11 | 0000-00-00 | Completed | |
Buguias | Sebang | Completion of Sebang Barangay Hall | Building | 300,000.00 | 298,817.56 | On Top Construction | General Fund Non Office CY 2015 | 2017-08-15 | 2017-09-25 | Completed | |
Bokod | Ekip | Improvement of Multi-Purpose Building(Phase II), Benguet | Building Repair | 1,700,000.00 | 1,693,780.68 | Aroboan Construction | General Fund CY 2015 | 2017-08-03 | 2017-12-26 | Completed | CLUSTERED a) Control No.:03-15-00007 - Aroboan Construction
clustered projects: a) imp of multi-purpose hall, pethal, ekip, bokod; b) imp of multi-purpose bldg (phase II) located at ekip, bokod |
Kabayan | Pacso | Improvement of Multi-Purpose Hall, Apanberang | Building Repair | 300,000.00 | 298,935.86 | Almond Engineering and Construction Rogelio Alimondo | SB No. 5 CY 2015 GF | 2016-08-26 | 2016-10-18 | Completed | |
Kibungan | Tacadang | Construction of Toilet at Batangan Elementary School, Tacadang | Building | 800,000.00 | 799,670.06 | Akip Construction and Enterprises/ Bobby wayan | General Fund - Non Office 2015 | 2016-12-12 | 2017-11-15 | Completed | |
Mankayan | Taneg, Guinaoang and Suyoc | Construction of COMPAC building, Panat area, the tri political boundaries of barangay Taneg, Guinaoang and Suyoc, Mankayan | Building | 800,000.00 | 797,768.20 | Malco Construction | General Fund CY 2015 | 2017-10-25 | 2018-02-01 | Temporarily suspended | 1) Suspended on October 25, 2017 due to site problem
2) Update as of June 2019 |
Tuba | Poblacion | Construction of Police sub-station at Sto. Tomas | Building | 1,200,000.00 | 1,198,742.58 | Roben Runas Construction | 20% PDF CY 2016 | 2016-12-01 | 0000-00-00 | Terminated | Mutually terminated due to site problems |
Tuba | Twin Peaks | Opening of Dalabi FMR | Roads | 1,000,000.00 | 998,130.76 | Aguinsod Construction | General Fund CY 2015 - Capital outlay | 2017-04-03 | 2017-02-20 | Completed | |
Tublay | Tuel | Opening of Degwey-Deg-ong FMR | Roads | 650,000.00 | 566,144.84 | | General Fund - Non Office CY 2015 | 2017-04-19 | 2017-06-22 | Completed | Project with underrun, needs additional fund for additional works for the road to be completely usable |
La Trinidad | Betag | Cementing and Fencing with-in the PHO Compound | Fence | 1,700,000.00 | 1,644,516.47 | Summerlin Construction | General Fund CY 2015 PHO | 2017-07-13 | 2018-02-22 | Completed | Completed on February 18, 2018 |
Sablan | Banangan | Continuation (Extension) of Keddeng Footpath | Roads | 400,000.00 Clustered | 398,580.55 | Anas Construction | General Fund - Non Office CY 2015 | 2017-07-31 | 2017-10-15 | Completed | |
Buguias | Catlubong | Construction of Gymnasium (Phase 3) at Bot-oan E/S | | 2,000,000.00 | 1,997,914.72 | SEJ Construction and Aggregates/ Mr. Eric De Leon | General Fund | 2016-02-16 | 2016-09-21 | Completed | |
Kibungan | Tacadang | Construction of Multi-Purpose Pavement with Complete Bleachers at Batangan Barrio School | | 300,000.00 | 298,853.75 | Safelink Builders/ Ponciano Andiso | General Fund - Non Office 2015 | 2016-03-16 | 2016-09-15 | Completed | |
Kabayan | Pacso | Construction of Barangay Health Station (Phase III) | Building | 500,000.00 | 498,895.81 | Solonio Construction | General Fund - Non Office 2015 | 2017-02-01 | 2017-04-05 | Completed | |
Mankayan | Balili | Completion of Balili Multi-Purpose Building, Atayan, Balili | | 1,000,000.00 | 998,000.00 | Donato-Sakiwat Construction/ Jerome-Stephen Sakiwa | General Fund - Non Office 2015 | 2016-06-23 | 2016-10-22 | Completed | |
Sablan | Banengbeng | Construction of Barangay Hall (Additional), Banengbeng | | 1,000,000.00 | | Guardian Construction - Ruben B. Pacheco Jr. | General Fund CY 2015 | 2016-04-18 | 2016-08-07 | Completed | |
La Trinidad | Poblacion | Construction of additional cell rooms at the Benguet Provincial Jail, Construction of 3 cell rooms at the Benguet Provincial Jail | Building Repair | 2,000,000.00 | 1,984,623.56 | Almond Engineering and Construction | General Fund CY 2015 PGO, General CY 2014 PGO Jail | 2016-12-05 | 0000-00-00 | Completed | Date of project completion |
Sablan | Balluay | A) Completion of Public CR Beside Multi-Purpose Hall, Balluay; B) Construction of Public CR at Balluay Barangay Hall, Balluay, Sablan (Additional) | Construction of Comfort Room | 450,000.00 | 447,622.02 | Guardian Construction | General Fund 2015 & General Fund 2017 | 2018-11-28 | 2019-01-20 | Temporarily suspended | 1 suspension.
Suspended as of December 28, 2018 |
Bakun | Sinacbat | Improvement of Safety Railings and Improvement of Foottrail | Roads | 200,000.00 | 190,384.91 | Pulicay Grandsons Construction | General Fund CY 2016 | 2017-11-29 | 2018-04-08 | Completed | 1) Cluster "G" - Pulicay Grandsons Construction
2) Completed on April 8, 2018
|
La Trinidad | Wangal | Construction of Equipment Shed at PEO | Building | 1,000,000.00 | 999,950.63 | anitos construction/ marty manayos | General Fund CY 2016 - PEO | 2016-04-15 | 2016-07-15 | Completed | |
La Trinidad | Poblacion | Improvement of Reception Area at Benguet Provincial Jail | Building Repair | 350,000.00 | | | General Fund All Offices 2016 | 2018-03-01 | 2018-05-03 | Completed | Completed on May 16, 2018, with 349,263.84 total cost incurred |
Atok | Naguey | Completion of Day Care Center and Multi-Purpose Hall | Building | 600,000.00 | 597,592.38 | Balangcod Construction | General Fund - Non Office CY 2017 | 2018-02-06 | 2018-04-14 | Completed | |
La Trinidad | Wangal | Improvement of PEO Perimeter Fence | Fence | 700,000.00 | 698,403.42 | EaJr De Leon Construction - Edwardo De Leon Jr | General Fund - All Offices CY 2016 | 2016-06-13 | 2016-12-05 | Completed | Completed |
Sablan | Bagong | Construction of Palva Footbridge Connecting Asin, Pappa to Sadul | Bridge | 1,500,000.00 | 1,423,953.79 | Guardian Construction | General Fund CY 2016 - Tourism | 2018-01-17 | 2018-06-06 | Completed | Completed on July 10, 2018 with revised target date of completion changed to August 11, 2018 |
La Trinidad | Betag | Extension of Provincial Water Analysis Laboratory, Phase I; PHO, La Trinidad Benguet | Building Repair | 700,000.00 | 698,986.39 | RNAA Builders | General Fund CY 2016 | 2018-04-03 | 2018-06-26 | Completed | |
Buguias | Catlubong | Construction of Bekes-Palakad Tirepath FMR | Roads | | 498,199.21 | | 2016 SB No. 2 | 2018-04-04 | 2018-05-10 | Completed | Completed for post inspection |
La Trinidad | Puguis | Restoration of the retaining wall along Timoy-Paswek Road; Puguis, La Trinidad, Benguet | Roadside | 300,000.00 | 259,000.00 | | General Fund CY 2016, LDRRMF-2017 | 2018-04-04 | 2018-04-24 | Completed | Completed on June 30, 2018, with 258,543.60 total cost incurred to date |
Buguias | Poblacion | Opening of Lower Naybo-Benged FMR Poblacion | FMR | 1,000,000.00 | | | 2016 SB No. 2 | 2018-02-09 | 2018-04-23 | Completed | Completed for Post Inspection |
Bokod | Karao | Improvement of Karao FMR | PCCP and Slope Protection | 1,000,000.00 | 938,724.88 | MALCO Construction | General Fund 2016 | 2018-07-06 | 2018-09-17 | Completed | 1) 1 Suspension
2) Completed; Revised Target Date of Completion = 11/13/2018 |
Kabayan | Pacso | Improvement of Mankeo FMR | PCCP | 600,000.00 | 598,400.90 | QPJ General Engineering Const. & Supply | SB #2, CY 2016 | 2018-10-30 | 2018-12-06 | Completed | |
Buguias | Sebang | Abatan - Kabayan - Gurel National Road to Alapang Elementary School road opening | Roads | 500,000.00 | 494,998.10 | JYP Construction | SB #2, CY 2016 | 2018-09-25 | 2018-10-21 | Temporarily suspended | Temporarily suspended due to the procurement of CNC |
Buguias | Natubleng | Construction of CR (with PWD room) and ramp with handrail at Pakpakitan | Construction of CR | 1,000,000.00 | 996,621.74 | Dipas Builders | General Fund 2016 | 2018-07-24 | 2018-11-03 | Temporarily suspended | 1) 1 Suspension
2) Temporarily suspended pending resolution of boundary dispute between barangays natubleng and amgaleyguey which had affected the proposed site where the project will be constructed.
|
Buguias | Buyacaoan | Road opening / Extension and improvement of Tagpaya - Peggueyna FMR | PCCP | 100,000.00 | 98,635.28 | Juricmarc Construction | 20% PDF CY 2016 | 2018-09-04 | 2018-09-24 | Completed | 1) 1 suspension
2) Completed. Revised target Date = 12/17/2018
|
Kabayan | Tawangan | Improvement Along Talabing - Tinoc Road, Tawangan, Kabayan | Roads | 8,974,516.34 | 8,969,686.24 | Jamil - Sean Construction | Pamana 2016 | 2017-10-27 | 2018-01-24 | Completed | 1) Completed on February 3, 2018 |
Kibungan | Tacadang | Improvement of foot rail and provision of hand rail at Mt. Oten | Foot rail | | 698,290.71 | Malco Construction | GF 2016 - Tourism | 2019-01-17 | 2019-04-22 | Completed | |
Atok | Paoay | Construction of Comfort Room Station with water works system at Paoay, Atok | Construction of comfort room | 1,000,000.00 | 998,769.88 | Haight's Construction | GF-2017 Tourism | 2019-02-04 | 2019-04-23 | Completed | Completed with LD |
Kibungan | Palina | Construction of toilet and water works system at Mayos, Palina | Waterworks System | 700,000.00 | 688,064.21 | Four Brothers Construction | GF-2016 | 2019-01-17 | 2019-03-18 | Completed | Completed |
Kabayan | Bashoy | Reconstruction of Mt. Pulag Elementary School Building (3 Classroom) | Building | 3,000,000.00 | 2,879,039.72 | Jamil Sean Construction | Trust Fund LDRRMF 2016 | 2018-12-12 | 2019-09-08 | Completed | |
Atok | Naguey | Rehab. of Naguey - Pasdong Vehicular Bridge, Naguey (Abutment), Atok, Benguet | Bridge | 2,000,000.00 | 1,958,897.14 | EMNAR Construction and Engineering Services | LDRRM TRUST FUND 2019 | 2020-02-20 | 2020-06-24 | Completed | |
Kibungan | Poblacion | Construction of Polis Barrio School Cottage Building | Building | 1,000,000.00 | 980,081.81 | Ebtitiwa General Engineering and Construction Services | 20% PDF CY 2016 | 2019-12-01 | 2020-03-21 | Completed | 1.) Suspended on March 17,2020 due to community quarantine;
2.) Actual date of completion: October 26, 2020.
|
Bakun | Bagu | Improvement of Barbarit Primary School | Building and Ground Improvement | 400,000.00 | 398,513.37 | FMC Warriors Construction | SEF 2016 | 2020-03-04 | 2020-10-21 | Completed | Suspended on March 17, 2020, due to community quarantine. |
La Trinidad | Puguis | Construction of Box Culvert at Lamtang | Box Culvert | 200,000.00 | 187,739.55 | | General Fund CY 2016 | 0000-00-00 | 0000-00-00 | Completed | |
Atok | Paoay | Fencing of Benguet-Kochi Sisterhood Park at Haights Place | Fence | 1,000,000.00 | 967,960.52 | Compass Rose Builders | General Fund-All Offices CY 2017 | 2017-07-13 | 2017-10-02 | Completed | |
Atok | Caliking | Improvement of Caliking Proper - Anapol FMR | Roads | 500,000.00 | 499,174.95 | Sangin Construction | General Fund - Non Office CY 2017 Capital Outlay | 2017-12-01 | 2018-03-11 | Completed | |
Atok | Topdac | Improvement of Powal - Nalseb Barangay Road | Roads | 500,000.00 | 499,135.26 | Drichloui Construction | General Fund - Non Office CY 2017 Capital Outlay | 2017-12-01 | 2018-01-24 | Completed | Project Completed on January 8, 2018. |
Atok | Paoay | Construction of Footpath at Half Tunnel to Osokan | Roads | 500,000.00 | 499,366.55 | | General Fund - Non Office CY 2017 Capital Outlay | 2017-12-01 | 2018-03-05 | Completed | |
Itogon | Ucab | Construction of 2 Classrooms at Goldcreek E/S Aleb | Building | 2,000,000.00 | 1,997,309.22 | WDG Construction and Suppy | General Fund CY 2015 Non Office CY 2017 | 2017-07-31 | 2018-06-28 | Completed | 1) Needs additional funding (cluster)
2) Contract under cluster a: a) const of 2 classroom at goldcreek e/s, b) const of 2 classroom at goldcreek e/s at ucab, itogon. Total amount paid includes the additional fund of Php 100,000.00
3) Completed on April 1, 2018 |
Itogon | Virac | Construction of Virac E/S Gymnasium (Phase II) | Building | 2,600,000.00 | 2,479,706.84 | ICO Construction | General Fund - Non Office CY 2017 | 2017-11-22 | 2018-04-01 | Completed | 1) 100.00% Completed
2) 1 suspension |
La Trinidad | Wangal | Construction of Perimeter Fence, Wangal, La Trinidad, Benguet | Fence | 995,000.00 | 993,591.16 | Sangin Construction | General Fund All Offices CY 2017 | 2017-10-28 | 2018-03-30 | Completed | Completed with liquidated damages |
La Trinidad | Wangal | Improvement of Indigenous Building Compound | Building Repair | 1,000,000.00 | 998,471.46 | SEJ Construction and Aggregate | General Fund Non Office 2017 | 2017-12-13 | 2018-02-22 | Completed | 1) 1 Suspension
2) Revised Target Date of Completion is on October 20, 2018 |
La Trinidad | Poblacion | Construction of Capitol Building II, 4th Floor | Building | 15,000,000.00 | 14,994,969.02 | Buganheirs Engineering Construction | General Fund Non Office CY 2017 CO | 2017-12-01 | 2019-02-01 | On going | 1) Ongoing with 78.06% completion as of January 2019
2) 1 Suspension
3) On Going w/ LD. Revised target date= 03/03/19. |
Mankayan | Taneg | Completion of Lupa-ac Footbridge | Bridge | 900,000.00 | 897,290.03 | Malco Construction | General Fund - Non Office CY 2017 | 2017-10-02 | 2017-12-10 | Completed | |
Sablan | Bayabas | Riprapping of a portion along Sawili-Boliweng FMR | Road Side | 500,000.00 | 494,286.44 | Sangin Construction | General Fund - Non Office CY 2017 | 2017-10-06 | 2017-11-19 | Completed | "Cluster" contract under cluster q: a) const of deep well with jet matic at matal-og, poblacion, sablan; b)riprapping of a portion along sawili-boliweng fmr at sawili, poblacion, sablan |
Tuba | Taloy Sur | Improvement along Taloy - Bayacsan Provincial Road | Roads | 5,000,000.00 | 4,940,107.74 | hdg construction and enterprises/Hanivall Guilando | General Fund Non-Office CY 2017 | 2017-07-29 | 2017-10-31 | Completed | partial accomplishment, re:imp along Taloy-Bayacsan Prov'l Road @ Tuba, Benguet |
La Trinidad | Wangal | Construction of Nursery Shed and Storage Room, Wangal | Building | 240,000.00 | 239,314.81 | ICO Construction | General Fund All Offices 2017 | 2018-02-07 | 2018-03-14 | Completed | Completed on March 15, 2018 |
La Trinidad | Wangal | Construction of Perimeter Fence at Wangal Nursery (Phase II) | Fence | 250,000.00 | 249,449.98 | ICO Construction | General Fund All Offices 2017 | 2018-02-07 | 2018-03-19 | Completed | Completed on March 19, 2018 |
La Trinidad | Poblacion | Construction of Rice Storage Room | Building | 500,000.00 | 498,873.76 | Random Builders | General Fund All Offices 2017 | 2018-02-07 | 2018-04-22 | Completed | Completed on April 22, 2018 |
Kapangan | Datakan | Construction of Extension and Comfort Room Station of the SLT Training Center | Building | 300,000.00 | 295,699.67 | Vanket Engineering and Construction | General Fund All Offices 2017 | 2018-02-15 | 2018-04-08 | Terminated | |
La Trinidad | Poblacion | Vertical Extension of Jail Perimeter Fence | Fence | 200,000.00 | 199,048.67 | ADL Construction | General Fund All Offices 2017 | 2018-03-01 | 2018-04-04 | Completed | Completed on May 12, 2018, with 199,048.67 total cost incurred. |
La Trinidad | Wangal | Extension/Improvement of PEO Building | Building Repair | 3,500,000.00 | 3,496,981.27 | Buganheirs Engineering Construction | General Fund All Offices CY 2017 | 2018-01-11 | 2018-09-09 | Completed | completed on September 5, 2018 |
La Trinidad | Poblacion | Improvement of Capitol Main Building | Building Repair | 3,000,000.00 | 2,909,706.01 | Sharamelle Construction and General Engineering | General Fund CY 2017 | 2018-02-15 | 2018-08-18 | Completed | 1) 1 Suspension
2) Revised Target Date of Completion is on October 12, 2018 |
Kibungan | Madaymen | Improvement of Tagpaya-Vemayoca FMR, Madaymen, Kibungan, Benguet | Roads | 2,000,000.00 | 1,893,998.35 | | SB No. 1 2017 | 2018-05-11 | 2018-07-05 | Completed | Completed: July 9, 2018
Revised Target Date of Completion: July 26, 2018 |
Tuba | Taloy Norte | Improvement of Dang-ay - Bontagel FMR, Taloy Norte, Tuba | Road | | 480,273.68 | | 20% PDF CY 2017 | 2018-04-25 | 2018-05-18 | Completed | Completed on May 16, 2018, with 480,273.68 total cost incurred. |
Itogon | Ucab | Construction of two (2) Classrooms at Goldcreek Elementary School Aleb | Building | 2,500,000.00 | 2,497,309.22 | WDG Construction and Suppy | 20% PDF CY 2017 | 2017-07-31 | 2017-12-29 | Completed | CLUSTERED - a) Control No.: 01-17-00005 - WDG Construction and Suppy |
Bokod | Pito | Construction of Quarantine Checkpoint Along Bokod Viscaya Road, Bokod, Benguet | Building | 450,000.00 | 444,807.92 | BLDY Engineering & Construction | 20% PDF CY 2017 | 2018-05-08 | 2018-06-24 | Completed | |
Mankayan | Tabio | Improvement/ Construction along Mankayan - Bato Provincial Road. Tabio, Mankayan, Benguet | Retaining wall | 1,500,000.00 | 1,384,927.30 | | SB no. 1 2017 | 2018-05-10 | 2018-07-02 | Completed | |
Buguias | Amlimay | Completion of Barangay Health Station (Clinic) Amlimay, Buguias, Benguet | Building | 1,000,000.00 | 964,710.56 | Pulicay Grandsons Construction | SB No. 1 - 2017 | 2018-05-29 | 2018-08-16 | Completed | Completed: 09/15/2018 |
La Trinidad | Poblacion | Upgrading of Provincial Jail Electrical System | Electrical | 400,000.00 | 398,167.33 | Organic Construction | General Fund - 2017 All Offices | 2018-05-20 | 2018-07-01 | Completed | Completed |
Itogon | Poblacion | Installation of Gate and Road Improvement Going to Sitio Suyo, Poblacion | Road Side | 150,000.00 | 149,044.06 | Bemada Construction | 20% PDF 2017 | 2018-07-28 | 2018-08-17 | Completed | Update as of October 9, 2018 |
Kibungan | Tacadang | Improvement of School Ground and Fencing, Tacadang, Kibungan, Benguet | Concreting of school ground and fencing | 500,000.00 | 498,755.44 | Malco Construction | 20% PDF 2017 | 2018-07-06 | 2018-10-24 | Completed | completed on 9/11/2018 |
La Trinidad | Betag | Improvement of Pharmacy and Installation of Cooling System and Ventilation | Building Repair | 1,100,000.00 | 1,047,130.34 | ADL Construction | 20% PDF CY 2017 | 2018-08-02 | 2018-10-03 | Completed | |
Tuba | Ansagan | Improvement along Kias-Ansagan FMR (Lumandi Section) | Construction of PCCP | 500,000.00 | 497,759.00 | Reasons Construction and Supplies | 20% PDF CY 2017 | 2018-09-30 | 2018-08-31 | Completed | |
La Trinidad | Wangal | A.)Construction Of PCL-LNB Multi-Purpose Building(Phaseii), Wangal; B.) A.)Construction Of PCL-LNB Multi-Purpose Building(Phaseii), Wangal, La Trinidad, Benguet | Building | 14,000,000.00 | 13,987,577.85 | RNAA Builders | General Fund (GF) 2018 / GF 2016 / GF 2017 Non-Office | 2018-07-06 | 2019-08-11 | Completed | Update as of January 24, 2020. |
Mankayan | Colalo | Construction of Pacda FMR Riprap, Suyoc | Road Side | 500,000.00 | 459,828.97 | A.L. Saganday Construction | SB #1, CY 2017 | 2018-08-20 | 2018-10-10 | Completed | 1) 1 Suspension |
Tuba | Tabaan Sur | Improvement of Indaoac-Pasiday FMR | Roads | 500,000.00 | 498,268.36 | Roben R. Runas Construction | 20% PDF CY 2017 | 2018-09-03 | 2018-10-04 | Completed | |
Bakun | Dalipey | Construction of View Deck with Comfort Room at Liwang, Dalipey | Building | 800,000.00 | 798,078.53 | NAIR Construction & Engineering | SB #2, CY 2017 | 2018-07-29 | 2018-08-20 | Completed | Completed and usable. |
Buguias | Abatan | Completion of Tabbacan Barangay Health Station or Birthing Facility | Building | 600,000.00 | 598,105.02 | Juricmarc Construction | SB #4, CY 2017 | 2018-09-24 | 2018-11-26 | Completed | |
Buguias | Abatan | Construction of Septic Tank and Installation of pipeline system and Improvement of Ramp and Handrails | Waterworks System | 346,400.00 | 319,578.92 | On Top Construction | SB #1, CY 2017 | 2018-10-10 | 2018-12-05 | Completed | |
Kapangan | Pudong | Construction of Loading Platform and Waiting Shed at Tadayan Proper | Waiting Shed | 500,000.00 | 474,998.69 | Ebtitwa General Eng'g & Construction | SB #1, CY 2017 | 2018-10-03 | 2018-12-19 | Completed | |
La Trinidad | Puguis | Improvement of Lamtang FMR | Box Culvert, Parapet, and PCCP | 500,000.00 | 459,530.40 | Pulicay Grandson's Construction | 20% PDF CY 2017 | 2018-10-31 | 2018-11-27 | Terminated | For Termination |
La Trinidad | Balili | Construction of Drainage Canal with cover, Central Balili | Drainage Canal with Cover | 150,000.00 | 139,970.00 | Pulicay Grandson's Construction | 20% PDF CY 2017 | 2018-10-28 | 2018-11-21 | Terminated | For termination |
Bokod | Daclan | Improvement and widening of footrail leading to DMMH-bejeng to Mariano Lake Asin Hot Spring | Footpath | 300,000.00 | 285,111.95 | SRBA General Construction | SB #1, CY 2017 | 2018-10-16 | 2018-11-30 | Completed | 1) 1 suspension resumed on 1/14/2019 |
Buguias | Baculongan Norte | Improvement of JBR Mandal-em Salidet FMR | Construction of PCCP | 500,000.00 | 489,975.26 | MACGAT Construction | 20% PDF CY 2017 | 2018-07-06 | 2018-08-07 | Completed | 1 suspension; Completed |
Kabayan | Lusod | Improvement of Proper Lusod-Landing FMR | Excavation, PCCP, Grouted riprap | 1,000,000.00 | 984,315.96 | Jamil Sean Construction | SB #1, CY 2017 | 2018-05-09 | 0000-00-00 | Temporarily suspended | 1) 1 suspension
2) Suspended since May 9, 2018 up to present (awaiting for CNC)
3) Update as of July 2019 |
Kabayan | Lusod | Construction of Lusod Footbridge | Footbridge | 1,000,000.00 | 998,190.77 | Haight's Construction | SB #1, CY 2017 | 2018-05-09 | 2018-07-11 | Completed | Completed with revised target date of November 29, 2018 for preparation of voucher |
Mankayan | Taneg | Construction of Mabilig - Aquili Footbridge (Additional) | Footbridge | 880,000.00 | 874,206.27 | On Top Construction | 20% PDF - 2018 | 2018-10-16 | 2019-01-03 | Completed | 1 Suspension due to road closure |
Tuba | Camp 4 | Improvement of flood control structure at Riverside, Camp 6 | Flood control | 2,000,000.00 | 1,685,139.95 | Anas Construction | SB #1, CY 2017 | 2018-07-23 | 2018-11-30 | Completed | On Going.Revised Target Date = 08/07/2019
|
Tublay | Ambongdolan | Improvement of Trail and provision of handrail at paterno cave, Ambongdolan, Tublay | Stairs, Footpath& Shed | 400,000.00 | 379,998.63 | E.B. Titiwa General Eng'g & Construction | GF tourism 2017 | 2018-11-06 | 2018-12-27 | Completed | |
Bokod | Tickey | Concreting of Camanggaan - Liboong FMR | Roads | 300,000.00 | 293,603.97 | SRBA General Construction | SB #1 CY 2017 | 2018-11-07 | 2018-11-24 | Completed | |
La Trinidad | Poblacion | Improvement and upgrading of Electrical System (PGSO) | Electrical System | 1,000,000.00 | 994,972.88 | On Top Construction | General Fund CY 2017 | 2018-11-14 | 2019-04-26 | Completed | completed
|
Kibungan | Tacadang | Construction of Barangay Hall with Tourism Information Center of Barangay Tacadang, Kibungan, Benguet | Reconstruction of Building | 1,000,000.00 | 997,276.15 | Malco Construction | GF 2017 All Offices | 2018-11-08 | 2019-04-18 | Completed | |
Mankayan | Balili | Construction of Water Tank at Nagawaan, Balili, Mankayan, Benguet | Water Works | 200,000.00 | 199,359.70 | Baldas Construction | 20% PDF | 0000-00-00 | 2019-03-12 | Completed | Completed, final inspection, March 12, 2019 |
Bokod | Bobok-Bisal | Completion of Comfort Room, Bobok-Bisal, Bokod, Benguet | Comfort Room | 400,000.00 | 397,730.55 | SRBA Gen. Construction | N/A | 2019-01-29 | 2019-04-02 | Completed | |
Itogon | Ampucao | Construction of Senior Citizen's Building (phase II) Dalicno, Itogon | Building | 500,000.00 | 499,408.08 | Renton Eng'g Services/Enrique Waldo | GF-2017 | 2019-02-14 | 2019-06-26 | Completed | 1.) Inspection was done on March 19, 2019. There is a contract variation from tiles to riprap.
2.) Post-inspection was done on June 27, 2019. |
La Trinidad | Beckel | Construction of drainage canal at sitio sapsing | Canal | 497,958.15 | 494,866.13 | Haight's Construction | SB#2 2017 | 2019-02-04 | 2019-04-11 | Completed | Still ongoing as of April 30, 2019 |
Itogon | Tinongdan | Construction of Waterworks System Binga Riverside, Tinongdan | Waterworks system | 500,000.00 | 460,489.83 | Aljune Builders | 20% PDF | 2019-02-17 | 2019-03-07 | Completed | Completed and usable as to the final inspection on March 22, 2019. |
La Trinidad | Poblacion | Construction of Session Hall at the Capitol Legislative Building | Session Hall Construction | 1,000,000.00 | 985,000.00 | Hillstone Builders | General Fund-2017,PGSO,Capital Outlay | 2019-03-27 | 2019-05-05 | Completed | |
Bokod | Bobok-Bisal | Construction of Bisal Waterworks System | Waterworks System | 500,000.00 | 495,080.17 | QPJ General Eng'g Construction and Supply | 20% PDF CY 2017 | 2018-12-12 | 2019-04-29 | Completed | |
Itogon | Dalupirip | Construction of Water tank at Kawadan, Dalupirip, Itogon, Benguet | Waterworks system | 500,000.00 | 498,872.58 | Aljune Builders | 20% PDF CY 2017 | 2019-03-22 | 2019-05-15 | Completed | |
Itogon | Tuding | Construction of three classroom building with basic facilities at Pacalso Elementary School | Building | 6,500,000.00 | 6,437,049.71 | Compass Rose Builders | CSR Program Mitigation Fund, SN Aboitiz | 2018-04-27 | 2019-07-06 | Completed | |
Bakun | Ampusongan | Completion of Ampusongan Multi-Purpose Building, Ampusongan | Building | 3,000,000.00 | 2,889,372.50 | Reasons Construction | General Fund 2017 | 2019-06-07 | 2019-12-14 | Completed | Images taken on June 18, 2019 |
Itogon | Ucab | Completion of Two Classroom at Goldcreek E/S at Aleb | Building | 1,200,000.00 | 1,194,018.70 | Reko Gen. Konstruct | 20% PDF CY 2017 | 0000-00-00 | 0000-00-00 | Completed | |
Buguias | Catlubong | Completion of Closed Gym, Bot-oan, Catlubong, Buguias, Benguet | Gymnasium | 2,000,000.00 | 1,997,809.96 | Mel-Soc Construction | SB #1, CY 2017 | 2018-11-10 | 2019-06-15 | Completed | |
Bokod | Tikey | Construction of Domestic Water System for Tikey Proper | Waterworks System | 668,000.00 | 668,000.00 | YKJ-LHAT General Construction | 20% PDF CY 2017 and Brgy. counterpart | 2019-04-03 | 2019-12-27 | Completed | |
Kabayan | Bashoy | Improvement of Abukot - Nandupit FMR | Road | 500,000.00 | 497,063.87 | Vanvin Construction and Supply | 20% PDF CY 2017 | 2020-03-11 | 2020-04-17 | Completed | |
La Trinidad | Balili | Improvement of viewdeck & Construction of comfort room w/ Septic Tank at Km. 3 | Comfort Room | 657,934.93 | 650,704.14 | Vanvin Construction and Supply | SB #01 CY 2017 | 0000-00-00 | 0000-00-00 | Completed | |
Mankayan | Cabiten | Rehabilitation along Baguyos-Maduto FMR | Road | 1,680,000.00 | 1,511,163.93 | Layad General Engineering Construction & Aggregates | SB #03 CY 2019 GF | 2020-01-29 | 2020-10-09 | Completed | 1.) Suspended 2/24/20 due to closed access road.
2.) Actual date of completion: September 29, 2020.
|
La Trinidad | Wangal | Construction of multi-purpose gym | Building | 1,000,000.00 | 997,070.38 | On Top Construction | SB #04 CY 2017 | 0000-00-00 | 0000-00-00 | On going | |
Tuba | Poblacion | Construction of Senior Citizens Multipurpose Building | Building | 1,500,000.00 | 1,498,640.33 | Ruben Runas Construction | 20% PDF 2017 & General Fund CY 2017-Non Office | 2020-02-25 | 2020-06-28 | Completed | Suspended on March 17,2020 due to community quarantine.
|
Bokod | Ekip | Improvement of Poodan Water System | Waterworks System | | 1,770,000.00 | N-J Construction | SB #1, CY 2017 | 2020-01-27 | 2020-09-24 | Completed | Original target completion date: June 4, 2020. |
La Trinidad | Wangal | Perimeter fencing of Benguet Sports Complex, Wangal (Phase I) ; Perimeter Fencing of Benguet Sports Complex (Phase II) | Fence | 5,000,000.00 | 4,364,128.07 | SEJ Construction & Aggregate | General Fund 2017 & General Fund 2018 PGSO | 2019-01-17 | 2019-06-02 | Completed | |
Kapangan | Datakan | Construction of Waiting Shed, Sitio Proper, Datakan, Kapangan | Building | 500,000.00 | 465,341.63 | Sandstream Construction | General Fund 2018 | 2018-05-09 | 2018-07-26 | Completed | Completed on July 19, 2018 |
Kapangan | Paykek | Improvement of Agro-Eco Park, Lomon, Kapangan | Agro-eco Park | 1,000,000.00 | 994,903.94 | EBTITIWA Gen. Eng'g & Construction Services | GF 2018 | 2019-02-20 | 2019-06-23 | Completed | |
Mankayan | Sapid | Improvement of Marivic to Gravel Pit Road, Sapid Mankayan, Benguet | Road | 1,000,000.00 | 869,011.93 | Eugao Construction | General Fund CY 2018 | 2018-07-06 | 2018-09-03 | Completed | |
La Trinidad | Tawang | Improvement of Boted Tawang FMR | Roads | 500,000.00 | 428,947.19 | Sangin General Construction | 20% PDF CY 2018 | 2018-09-27 | 2018-11-05 | Completed | |
Sablan | Bagong | Improvement of Asham-Cayapes FMR, | Roads | 500,000.00 | 495,499.07 | Guardians | 20% PDF 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Buguias | Sebang | Improvement of Pasbol-Impugong FMR, Sebang | Roads | 500,000.00 | 497,369.37 | MACGAT Construction | 20% PDF 2018 | 2018-07-03 | 2018-08-10 | Completed | 1) 1 Suspension
2) Revised target date of completion - October 8, 2018 |
Buguias | Baculungan Sur | Improvement of Obanga Crossing FMR, Baculungan Sur (Construction of Retaining Wall) | Road Side | 500,000.00 | 478,034.36 | Juricmarc Construction | 20% PDF CY 2018 | 2018-08-28 | 2018-10-03 | Completed | |
Buguias | Baculongan Sur | Improvement of Balintag-Dekan Road (Makbas Section) | Roads | 500,000.00 | 494,985.35 | MACGAT Construction | 20% PDF CY 2018 | 2018-09-18 | 2018-10-22 | Completed | |
Kabayan | Ballay | Improvement of Barangay Road at Toneleg, Ballay | Road Side | 500,000.00 | 498,901.56 | Jamil Sean Construction | 20% PDF CY 2018 | 2018-09-11 | 2018-10-19 | Completed | Completed - October 5, 2018 |
La Trinidad | Lubas | Improvement of Guitley Barangay Road,Lubas,La Trinidad,Benguet | Roads | 2,000,000.00 | 1,942,845.50 | On Top Construction | 20% PDF CY 2018 | 2018-07-04 | 2018-09-10 | Completed | Revised Target Date of Completion is on October 12, 2018 |
Bakun | Gambang | Improvement of Cagam-is to Ingaan Farm to Market Road, Gambang, Bakun | Road Pavement | 400,000.00 | 399,463.91 | SRBA General Construction | 20% PDF CY 2018 | 2018-09-28 | 2018-10-24 | Completed | Project Completed on 11-29-2018 |
Bokod | Ekip | Construction of Footpath from Gwetig going to Poodan | Roads | 500,000.00 | 496,285.09 | Hillbrand Engineering | 20% PDF CY 2018 | 2018-09-11 | 2018-11-17 | Completed | Completed with LD |
Kapangan | Sagubo | Construction of Comfort Room at Kapangan National High School - Sagubo Annex | Building | 500,000.00 | 487,442.67 | Vanket Engineering and Construction | 20% PDF CY 2018 | 2018-09-24 | 2018-11-27 | Completed | |
Tuba | Tadiangan | Improvement of Tawangan-Pacac Road | Roads | 500,000.00 | 494,732.60 | Juricmarc Construction | 20% PDF CY 2018 | 2018-09-24 | 2018-11-11 | Completed | |
Bakun | Ampusungan | Rehab of Ay-ay to Cabutotan Farm to Market Road | Riprap | 1,000,000.00 | 989,445.66 | Pulicay Grandson's Construction | SB #1, CY 2018 | 2018-10-31 | 2018-12-25 | Completed | Ongoing
1 suspension
Recommended for suspension to undergo variation
Revised Target Date =04/09/2019
|
Bokod | Ekip | Construction of Dirty Kitchen at the Barangay Health Sub-Station, Sitio Poodan | Dirty Kitchen | 500,000.00 | 467,571.82 | Sangin General Construction | 20% PDF CY 2018 | 2018-10-16 | 2018-12-02 | Completed | |
Bakun | Sinacbat | Improvement of Macbas-Beyeng FMR | PCCP | 1,000,000.00 | 963,919.78 | Pulicay Grandsons Construction | 20% PDF CY 2018 | 2018-08-04 | 2018-08-22 | Completed | Completed and usable |
Mankayan | Bedbed | Construction of pavement of Aliwandey FMR | Construction of PCCP | 500,000.00 | 497,992.75 | Sapid Builders | 20% PDF CY 2018 | 2018-08-01 | 2018-09-06 | Completed | 1) 1 suspension
2) Temporarily suspended due to the closed road because of the typhoon/monsoon.
3) Completed
4) Revised Target Date=02/19/2019
|
Tuba | Taloy Norte | Construction of BPATS Outpost | Construction of BPATS | 500,000.00 | 493,924.03 | Roben B. Runas Construction | General Fund 2018 | 2018-10-31 | 2019-01-08 | Terminated | Recommended for mutual termination |
La Trinidad | Beckel | Completion of Lamut Elementary School Perimeter Fence, Lamut, Beckel, LTB | School Fencing | 1,000,000.00 | 919,626.83 | Pulicay Grandsons Construction | 2018 GF- PEO | 2018-10-10 | 0000-00-00 | Completed | Completed and usable. |
Sablan | Bayabas | Bulala warehouse ground improvement, Agri-eco farm, Bulala | Ground Improvement | 1,500,000.00 | 1,219,979.84 | Anas Construction | 20% PDF 2018 | 2018-10-05 | 2018-12-28 | Completed | |
Atok | Topdac | Construction of Pavement, Topdac Elementary School, Atok, Benguet | Construction of Pavement | 500,000.00 | 480,735.93 | | GF CY 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Mankayan | Cabiten | Construction of Clipper Foot Bridge Las-igan, Cabiten, Mankayan, Benguet | Foot bridge | 250,000.00 | 247,483.74 | Baldas Construction | 20% PDF - 2018 | 2018-11-14 | 2018-12-15 | Completed | |
La Trinidad | Beckel | Road improvement of Pagal Barangay Road | Roads | 2,000,000.00 | 1,996,542.78 | On Top Construction | 20% PDF 2018 | 2018-10-15 | 2019-01-22 | Completed | |
Bokod | Bobok-Bisal | Construction of Comfort Room at Japas | Comfort Room | 500,000.00 | 489,469.46 | Summerlin Construction and Development Corporation | 20% PDF 2017 | 2018-12-12 | 2019-02-13 | Completed | |
Mankayan | Tabio | Improvement along Mankayan - Bato Provincial Road | Roads | 5,000,000.00 | 4,980,000.00 | Donato - Sakiwat Construction (Jerome Stephen Sakiwat) | 20% PDF CY 2018 | 2018-10-10 | 2019-01-31 | Completed | Completed |
Tuba | Tadiangan | Improvement along Yagyagan - Ampusa Provincial Road | Roads | 5,000,000.00 | 4,703,160.60 | Sapdoy Enterprise (William W. Sapdoy) | 20% PDF CY 2018 | 2018-11-19 | 2019-04-20 | Completed | Update as of July 11, 2019
On-going
with liquidated damages |
Itogon | Dalupirip | Improvement of Access Going to Mt. Pigingan, Dalupirip, Itogon, Benguet | Pathway Improvement | 500,000.00 | 499,481.49 | SRBA General Construction | GF 2018 - Tourism | 2018-12-12 | 2019-02-18 | Completed | Completed |
La Trinidad | Wangal | Extension of Benguet Indigenous People Building, Wangal, La Trinidad | Extension of Building | 1,000,000.00 | 945,246.45 | On Top Construction | General Fund 2018 | 2018-11-14 | 2019-02-19 | Completed | |
La Trinidad | Wangal | Construction of Power House Benguet Cold Chain Project La Trinidad, Benguet | Power house Construction | 500,000.00 | 489,486.03 | Akip Construction & Enterprise | General Fund 2018 | 2018-11-29 | 2019-03-28 | Completed | |
Atok | Poblacion | Completion of Banayakew Multi-Purpose Building, Banayakew | Building | 800,000.00 | 797,830.20 | Four Brothers Construction | General Fund 2018-Tourism | 2019-01-17 | 2019-04-14 | Completed | Completed |
Bakun | Gambang | Improvement of Alam-am - Nasyotean FMR, Gambang | Construction of PCCP | 1,000,000.00 | 998,472.71 | Drichloui Construction | General Fund 2018 | 2019-01-17 | 2019-03-11 | Completed | |
Itogon | Ampucao | Construction of Basketball Court at Pasiday | Basketball court | 400,000.00 | 392,505.00 | BABECOR BUILDERS | General Fund CY 2018 and General Fund Non Office CY 2015 | 2018-12-12 | 2019-01-29 | Completed | |
Bokod | Poblacion | Construction of fence at Bulo Elementary School | Fence | 850,000.00 | 808,381.57 | SRBA General Construction | SB #1 - SEF 2018 | 2018-11-10 | 2019-01-25 | Completed | |
Itogon | Dalupirip | Improvement of Comfort Room, Barangay Hall, Dalupirip, Itogon | Building improvement | 600,000.00 | 584,197.42 | Aljune Builders | GF 2018 | 2019-01-10 | 2019-03-25 | Completed | |
Sablan | Bayabas | Construction of Reception Building and CR with Lavatory, Bulala Agri-Eco Farm, Bulala | Building | 3,000,000.00 | 2,670,039.96 | Anas | General Fund 2018 | 2019-01-22 | 2019-06-04 | Completed | Completed |
Tublay | Caponga | Improvement along Acop - Kapangan JCT- Ambongdolan Provincial Road | Roads | 1,000,000.00 | 947,003.20 | Family Circle Construction | LDRRMF 2018 | 2018-03-18 | 2018-10-09 | Completed | |
Bokod | Tikey | Completion of Basketball Court at Tikey | Basketball Court | 270,000.00 | 268,499.50 | N. J. Construction | SB #1, CY 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Kapangan | Beleng Belis | Construction of Multi-purpose cottage, Proper Beleng Belis | Cottage | 1,687,000.00 | 1,668,004.27 | Norbano Builders | SB #1, CY 2018 | 2019-02-14 | 2019-05-17 | Completed | Ongoing with LD
|
Itogon | Tuding | Rehabilitation of canal and ripraping along upper Mangga - Luneta Road | Canal and Riprap | 500,000.00 | 498,011.72 | ARJY Construction | 20% PDF 2018 | 2019-02-11 | 2019-03-27 | Completed | Inspection was done on March, 26, 2019 |
La Trinidad | Balili | Rehabilitation of footpath with drainage at Mamaga, Balili, La Trinidad (starting from Guinodan's Residence) | Footpath | 500,000.00 | 449,202.75 | Hillstone Builders | LDRRMF 2018 | 2019-02-03 | 2019-04-06 | Completed | Inspection was done on March 19, 2019 |
Kapangan | Balakbak | Concreting of Entrance Road at Governor Bado Dangwa Agro - Industrial School Main and Balakbak E/S, Kapangan | Road Concreting | 500,000.00 | 463,939.29 | EBTitiwa Gen Engineering and Construction Services | General Fund 2018 | 2019-03-04 | 2019-03-29 | Completed | |
Kapangan | Kapangan Central | Completion / Finishing of the basement of the garage / warehouse at Kapangan, Benguet | Completion of building | 300,000.00 | 296,674.01 | Family circle construction | GF 2018 | 2019-03-25 | 2019-04-30 | Completed | |
La Trinidad | Pico | Improvement of POCNA Road | Road Pavement and Riprap | 1.,500,000 | 1,429,481.76 | Malco Construction2 | 2018 SB #2 | 2019-01-07 | 2019-03-09 | Completed | Completed and Geotag on October 3, 2019 |
La Trinidad | Wangal | Construction of Comfort Room with Lavatory (Cold Chain) at Wangtal,La Trinidad,Benguet | CR construction | 1,615,000.00 | 1,544,829.13 | Four Brothers Construction | General Fund-2018 | 2019-03-25 | 2019-08-19 | Completed | |
Itogon | Loacan | Rehabilitation of Loacan Elementary School Building, Itogon | Building Repair | 1,000,000.00 | 859,414.48 | Reko Construction | GF-LDRRMF | 0000-00-00 | 2019-04-22 | Completed | completed |
La Trinidad | Wangal | Construction Of Training Center At Wangal (Phase II), La Trinidad,Benguet | Completion of building | 8,047,000.00 | 8,025,028.68 | Random Builders | General Fund-2018 | 2019-03-07 | 2019-12-31 | Completed | |
Sablan | Bayabas | Construction of Agri-Eco Farm Cottages at Bulala Agri-Eco Farm,Bulala,Bayabas | Construction of Building | 5,000,000.00 | 4,492,161.42 | Anas Construction | General Fund-2018 | 2019-03-25 | 2019-11-02 | Completed | |
Sablan | Pappa | Completion of Barangay Hall at Pappa | Completion of Building | 800,000.00 | 798,709.10 | Anas Construction | General Fund-2018 | 2019-03-25 | 2019-07-06 | Completed | |
Bakun | Gambang | Repair of Bagtangan Elementary School, Bakun - 3 classrooms at Gambang, Bakun | | 900,000.00 | 899,240.88 | Drichloui Construction | N/A | 2019-01-29 | 2019-05-23 | Completed | Completed |
La Trinidad | Poblacion | Construction of Material Recovery Facility, Capitol, LTB | MRF | 210,000.00 | 209,538.29 | Four Brothers Construction | General Fund 2018 | 2019-02-26 | 2019-03-13 | Completed | Completed |
Bokod | Karao | Construction of Gweling to Santaan / Busok Waterworks | Waterworks | 1,800,000.00 | 1,682,839.51 | Summerlin Construction and Development Corporation | 20% PDF CY 2017 & SB#1 CY 2018 | 2019-06-24 | 2019-10-04 | Completed | |
Tuba | San Pascual | Construction of Comfort Room and Lavatories | Building | 2,000,000.00 | 1,805,273.54 | Pulicay Grandsons Construction | General Fund 2018 | 2019-07-10 | 2019-10-26 | Completed | Project Engineer: John Pilay
QC: Jaypee Cayamdas
Geotagged by JC |
Kabayan | Ballay | Construction of Flood Control at Kubo-Ballay | Flood Control | 250,000.00 | 248,656.88 | YKL-LHAT General Construction | 20% PDF 2018 | 2019-08-27 | 2019-10-02 | Completed | |
Tublay | Ambassador | Improvement of Nalseb-Los-oc Barangay Road. | Road Pavement | 1,000,000.00 20% PDF | 948,153.25 | Sangin | 20% PDF 2018 | 2019-07-10 | 2019-08-26 | Completed | Completed and Geo-tagged on October 18, 2019 |
Buguias | Amlimay | Concreting of Dagway Box culvert approach | Roads | 200,000.00 | 198,734.67 | | PDF CY 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Sablan | Bayabas | Improvement of Nursery Site Access Road at Agri-Eco Farm, Bulala | Road | 1,500,000.00 | 1,342,612.83 | Anas Construction | 20% PDF CY 2018 | 2019-10-28 | 2019-12-03 | Completed | |
La Trinidad | Poblacion | Improvement of the Provincial Library Building | Building | 2,500,000.00 | 2,499,000.00 | Cialmar Builders | General fund (All Offices) 2018 | 2019-11-07 | 2020-02-22 | Completed | |
Buguias | Sebang | Construction of slab bridge and improvement along Paneg-an, Tamangan (Lutaan Section) FMR | Road | 2,000,000.00 | 1,942,249.14 | JYP General Construction | 20% PDF CY 2018 | 2019-10-18 | 2020-01-03 | Completed | 1.) With extension of 20 calendar days.
2.) Revised target date of completion: January 23, 2020
3.) Actual date of completion: February 13, 2020. |
Bokod | Ambuklao | Construction of Multi-Purpose Open Gym at Sombrero | Gymnasium | 4,000,000.00 | 3,677,247.89 | Sharamalle Construction and General Engineering | 20% PDF 2018 | 2019-07-17 | 2019-12-11 | Completed | |
Bokod | Ambuklao | Construction of flood control | Flood control | 2,000,000.00 | 1,681,274.13 | Hillstone Builders | 20% PDF 2018 | 2019-10-28 | 2020-01-01 | Completed | Completed on February 12, 2020. |
Bokod | Karao | Construction of Barangay Health Station at Karao | Building | 2,500,000.00 | 2,496,655.84 | Hillbrand Engineering | 20% PDF CY 2018 | 2019-07-17 | 2020-01-20 | On going | Update as of February 21, 2020. |
La Trinidad | Poblacion | Improvement of Water Works System of Capitol Main Building, Legislative Building and Annexes (Phase I) | Waterworks system | 500,000.00 | 405,430.55 | Alber and Seven Construction | General Fund CY 2018 | 2019-12-02 | 2020-02-16 | Completed | |
La Trinidad | Wangal | Construction of a New Automotive Building with Ground Improvement (Phase I) | Building | 4,000,000.00 | 3,994,192.43 | LBJ Construction | 20% PDF CY 2018 | 2019-10-18 | 2020-01-10 | Completed | 1.) Revised date of completion: February 25, 2020.
2.) Actual date of completion: February 14, 2020. |
Atok | Caliking | Installation of Semi-Permanent Fence for the Old Cagui-ing Elementary School | Fence | 800,000.00 | 783,988.17 | Sangin General Construction | SEF 2018 | 2020-01-13 | 2020-02-18 | Completed | |
Buguias | Loo | Improvement/Widening of Lanas Panayaoan FMR (JCT NHS) | Road | 2,000,000.00 | 1,989,255.13 | JYP General Construction | 20% PDF 2018 | 0000-00-00 | 0000-00-00 | Completed | Suspended until such time that Loo NHS will allow the construction of PCCP within the school compound.
|
Kibungan | Sagpat | Construction of Comfort Room at Sagpat Proper | Comfort Room | 500,000.00 | 499,903.17 | Akip Construction and Enterprise | General Fund CY 2018 | 0000-00-00 | 0000-00-00 | Temporarily suspended | Suspended on November 12, 2019 due to awaiting for the implementation of the additional slope protection on the project site.
|
Sablan | Poblacion | Construction of Multi-purpose Building at Sitio Sabdang | Building | 2,000,000.00 | 1,840,062.35 | HGW=3 Engineering & Construction | 20% PDF - 2018 | 0000-00-00 | 0000-00-00 | Temporarily suspended | Suspended on July 17,2019 due to site problem. |
La Trinidad | Betag | Clustered Project for BeGH (8 Projects, A-H): A. Improvement of Roads & Sidewalks at BeGH B. Rehabilitation of Oxygen Generator System BeGH La Trinidad, Benguet C. Rehabilitation of Sewage Treatment Plant at BeGH D. Repair of Damages Brought by Typhoon Ompong "Mangkhut" at BeGH E. Repair of Damages of Morgue Building F. Repair of Damages at CT Scan Building G. Repair & Maintenance of Canteen Building H. Repair & Maintenance of Farmer Maternity Building | Various | A. 1,500000.00 B. 1,500000.00 C. 1,760,592.77 D. 1,500,000.00 E. 442,469.13 F. 92,852.76 G. 377,196.19 H. 393,731.81 | 7,411,733.37 | QPJ General Eng'g Construction & Supply | A. DOH 2018-11-12A B.DOH 2018-10-12B C. DOH 201 | 0000-00-00 | 0000-00-00 | On going | Suspended on March 17,2020 due to community quarantine.
|
La Trinidad | Wangal | Construction of PDRRMO Office Building Phase II | Building | 8,000,000.00 | 7,015,208.34 | Anitos Construction | LDRRMF 2018 | 0000-00-00 | 0000-00-00 | Completed | Suspended on March 17,2020 due to community quarantine.
|
Mankayan | Tabio | Construction of Quarantine Checkpoint/Outpost (Mankayan) Madaymen | Building | 1,500,000.00 | 1,439,473.97 | BTCJR Construction & Engineering Services | 20% PDF CY 2018 | 2020-03-05 | 2020-11-30 | Completed | Suspended on March 17,2020 due to community quarantine.
|
Bokod | Ambuklao | Improvement of Waterworks System | Waterworks system | | 922,397.73 | Sherfelias Construction | 20% PDF CY 2018 | 2020-02-09 | 2020-03-29 | Completed | Actual date of completion: August 7, 2020. |
Tublay | Caponga | Improvement of Paoad Elementary School | Riprap with railings | 1,500,000.00 | 1,438,010.32 | Skalyndra Construction and Supply | SEF 2018 | 2020-08-20 | 2020-12-02 | Completed | Actual date of completion: October 7, 2020 |
Tuba | San Pascual | Construction of Apni - Colon Waterworks System | Waterworks System | 500,000.00 | 490,262.26 | Roben Runas Construction | 20% PDF CY 2018 | 2020-09-02 | 2020-11-18 | Completed | |
La Trinidad | Ambiong | Improvement of Ambiong Elementary School Perimeter Fencing | Fencing | 500,000.00 | 444,344.70 | Efler Construction and Enterprise | SEF CY 2018 | 2021-01-04 | 2021-03-16 | Completed | |
Mankayan | Tabio | Ground Improvement for Senior High School at Tabio National High School, Lepanto | Ground Improvement | | 3,390,046.10 | | General Fund CY 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Kabayan | Pacso | Repair of Asokong Pacso Elementary School | Classrooms | 900,000.00 | 894,016.29 | Four Brothers Construction | SEF 2018 | 2019-02-04 | 2019-05-21 | Completed | |
Bokod | Ambuclao | Construction of Lower Minac Flood Control | Flood Control | 1,000,000.00 | 999,174.78 | BLDY Eng'g & Construction | LDRRMF | 2019-01-31 | 2019-04-12 | Completed | Completed with LD |
La Trinidad | Bahong | Construction of Retaining Riprap along upper Sadag Provincial Road (near Comiles Residence) | Riprap | 1,500,000.00 | 1,310,809.96 | MACGAT Construction | SB #1, CY 2017 | 2019-02-05 | 2019-09-04 | Completed | Completed with Liquidated Damages (LD). |
La Trinidad | Betag | Construction of Extension of Provincial Water Analysis Laboratory (Phase II) | Building Repair | 1,000,000.00 | 994,721.65 | Hillstone Builders | General Fund 2018 | 2019-02-01 | 2019-05-22 | Completed | |
La Trinidad | Poblacion | Construction of Annex Building (Phase I); and Construction of Annex Building Capitol (Phase II) | Building | 43,000,000.00 | 42,888,888.88 | Jomarcann General Construction | SB #4 CY 2017; GF CY 2018; and SB#1 CY 2018 | 2019-02-20 | 2020-04-04 | Completed | Actual date of completion: March 17, 2020. |
Tuba | Twin Peaks | Completion of Open Gymnasium | Gymnasium | 500,000.00 | 496,529.74 | BABECOR BUILDERS | 20% PDF CY 2017 | 2019-02-07 | 2019-03-22 | Completed | Final inspection was made on March 11, 2019 |
Tuba | San Pascual | Construction of Quarantine Checkpoint/Outpost at San Pascual, Tuba | Construction of Building | 1,500,000.00 | 1,493,793.02 | Roben Runas Construction | 20% PDF CY 2018 | 2019-03-04 | 2019-08-30 | Completed | Revised target date of completion from July 12, 2019 to August 30, 2019. |
Bakun | Gambang | Improvement of Liwang - Bolbolo Farm to Market Road, Bagtangan | Road | 3,000,000.00 | 2,995,980.71 | Apaklo Kin Construction & Eng'g Services | SB #3, CY 2019 | 2020-03-22 | 2020-09-27 | Completed | 1.) Original target date of completion: June 25, 2020; Suspended due to community quarantine;
2.) Date resumed: June 24, 2020. |
Tuba | San Pascual | Improvement of Native Pig Multiplier Farm | Native Pig Multiplier | 1,000,000.00 | 995,754.32 | Roben B. Runas Construction | General Fund CY 2018 | 2019-02-07 | 2019-04-18 | Completed | |
Atok | Paoay | Fencing of the Beng. Kochi Sisterhood Park at Haight's Place | Fence | 1,000,000.00 | 997,807.51 | Four Brothers Construction | GF 2017 | 0000-00-00 | 0000-00-00 | Temporarily suspended | Suspended due to the inappropriate program of work (From hollow blocks to square bar/interlinks) |
Bokod | Nawal | Rehabilitation of Nawal Elementary School Waterworks System | Waterworks System | 315,000.00 | 315,000.00 | N-J Construction | 20% PDF 2018 | 2019-01-31 | 2019-03-12 | Completed | ntp as of January 2019 |
Sablan | Bayabas | Perimeter fencing at Agro-Eco farm (Phase IV) | Fence | 1,000,000.00 | 998,878.53 | Anas Construction | 20% PDF CY 2018 | 2019-02-11 | 2019-04-06 | Completed | |
Tuba | Tadiangan | Rehabilitation along Yagyagan-Ampusa Provincial Road | Roads | 1,000,000.00 | 998,351.19 | Anas Construction | 20% PDF 2019 | 2019-04-02 | 2019-05-09 | Completed | |
Bokod | Pito | Rehabilitation of Pilpiloy Waterworks System at Pito, Bokod, Benguet | Waterworks | 450,000.00 | 449,204.24 | BLDY Engineering and Construction | N/A | 2019-02-26 | 2019-04-07 | Completed | |
Bokod | Pito | Construction of Administrative Building with Comfort Room | Building | | | Hillbrand Engineering | N/A | 2019-04-13 | 0000-00-00 | Completed | |
Kapangan | Kapangan Central | Repair & Repainting of the Hospital Main Building (door jambs,ceilings,etc.,including damaged roofs) at Central,Kapangan,Benguet | Building repair | 1,500,000.00 | 1,436,891.33 | Haight's Construction | General Fund 2019 | 2019-06-11 | 2019-09-01 | Completed | |
La Trinidad | Poblacion | Installation of Razor Barbed Wire | Fencing | 400,000.00 | 387,716.64 | Haight's Construction | General fund 2019, PGO-Jail | 2019-06-07 | 2019-07-05 | Completed | completed with slippage
|
Sablan | Banangan | Rehabilitation of Calot - Wassit FMR | Riprap | 600,000.00 | 509,335.28 | Anas Construction | General Fund CY 2019 | 2019-07-10 | 2019-08-18 | Completed | |
Sablan | Bayabas | Construction of Waiting Shed at Calamay | Waiting shed | 200,000.00 | 176,394.89 | Anas Construction | General Fund CY 2019 | 2019-07-12 | 2019-08-14 | Completed | |
Buguias | Amgaleyguey | Construction of Sagandoy Elementary School | School Building | 2,020,075.00 | 2,000,809.37 | Mel-soc Construction | SB #1, SEF 2018 | 2019-03-15 | 2019-08-30 | Completed | |
Kibungan | Palina | Repair of Palina Elementary School Building, Palina Kibungan, Benguet | School Repair (Building) | 1,100,000.00 | 1,070,610.25 | LBJ Construction | 20% PDF 2019 | 2019-07-03 | 2019-10-15 | Completed | Completed and geo-tagged on Oct. 15, 2019 by JC |
Kabayan | Ballay | Improvement of Indaoac - Tinaleb - Barangay Road | Road | 1,500,000.00 | 1,494,020.10 | Jamil Sean Construction | 20% PDF CY 2019 | 2019-07-12 | 2019-09-22 | Completed | |
Tuba | Camp 6 | Construction of Flood Control along Bued River Riverside Camp 6 | Flood Control | 2,500,000.00 | 2,227,206.94 | Boyet Builders | 20% PDF 2019 | 2019-06-27 | 2019-09-17 | Completed | Completed and geo-tagged on October 25, 2019 by JC |
Tuba | Tabaan Norte | Improvement of along Pugo-Balangabang Provincial Road | Road Pavement | 5,000,000.00 | 4,894,504.23 | Remnant Builders | 20% PDF 2019 | 2019-07-12 | 2019-10-28 | Completed | Completed and geo-tagged by JC on November 14, 2019. |
Buguias | Buyacaoan | Improvement of Tagpaya Peggueyna Farm to Market Road | Road | 1,000,000.00 | 917,475.95 | Tepanlu Construction and Supply | General Fund 2019 | 2019-10-31 | 2020-02-11 | Completed | 1.) With suspension.
2.) Revised target date of completion: February 11, 2020. |
Buguias | Natubleng | Completion of Police Substation and Tourism Information / Assistance Center | Building | 500,000.00 | 496,463.14 | On Top Construction | General Fund 2019 | 2019-10-30 | 2019-12-24 | Completed | |
Buguias | Loo | Rehabilitation of J207 Becaeg-Kitongan Farm to Market Road | Road | 800,000.00 | 796,609.39 | On Top Construction | LDRRMF Trust Fund CY 2019 | 2019-10-19 | 2019-11-24 | Completed | |
Buguias | Amgaleyguey | Improvement of Km. 73 Amgaleyguey Proper Barangay Road | Road | 500,000.00 | 483,653.18 | Ebtitiwa General Engineering and Construction Services | 20% PDF CY 2019 | 2019-07-22 | 2019-11-08 | Completed | |
Buguias | Loo | Construction of Alakan flood control, Dagdag-Nagubgubbang section | Flood control | 3,000,000.00 | 2,976,103.78 | BTCJR Constrution & Engineering Services | 20% PDF 2019 | 2019-07-22 | 2019-09-16 | Completed | |
Kabayan | Eddet | Construction of Retaining Wall & Widening of Sharp Curve | Retaining Wall | 500,000.00 | 499,847.08 | Vanvin Construction and supply | SB #1 CY 2019 | 2019-10-31 | 2019-12-12 | Completed | |
Kabayan | Gusaran | Construction of Flood Control with Spillway at Basil, Asokong | Flood Control | 6,000,000.00 | 5,994,086.16 | Jamil Sean Construction | 20% PDF 2019 | 2019-06-07 | 2019-10-18 | Completed | |
Kabayan | Pacso | Road opening - Pacso | Road opening | 500,000.00 | 498,369.66 | Jamil Sean construction | SB #1 CY 2019 | 2019-10-21 | 2019-11-24 | Completed | |
Kabayan | Poblacion | Construction of Abapang Cotcot Access Road | Road | 800,000.00 | 797,992.64 | Jamil Sean Construction | 20% PDF CY 2019 | 2019-10-21 | 2019-12-04 | Completed | |
Sablan | Bayabas | Rehabilitation of Tamaan - Bayabas Farm to Market Road | Road | 1,200,000.00 | 1,010,903.44 | Anas Construction | 20% PDF CY 2019 | 2019-10-28 | 2019-12-29 | Completed | |
La Trinidad | Balili | Rehabilitation of footpath and drainage canal along Gungabon Residence, Mamaga, Balili | Footpath and Canal | 1,000,000.00 | 1,000,000.00 | Rigne Construction | General Fund CY 2019 | 2019-10-21 | 2020-01-12 | Completed | Actual completion: December 27, 2019 |
Buguias | Sebang | Improvement of Panig-an - Bot-oan Farm to Market Road | Road | 500,000.00 | 497,070.10 | JYP General Construction | General Fund CY 2019 | 2019-11-01 | 2019-12-03 | Completed | |
Mankayan | Bedbed | Rehabilitation of Mankayan - Bedbed Provincial Road | Road | 3,000,000.00 | 2,994,075.80 | Cliff Construction and Aggregates | LDRRMF CY 2019 | 2019-10-23 | 2020-02-04 | Completed | |
Buguias | Sebang | Improvement of Panig-an - Tamangan, Sebang Farm to Market Road (Longilong Section) | Road | 1,000,000.00 | 996,794.09 | On Top Construction | SB #3, CY 2019 | 2020-01-02 | 2020-02-10 | Completed | Actual date of completion: February 29, 2020. |
Buguias | Sebang | Improvement of Pasbol - Impugong Farm to Market Road | Road | 2,500,000.00 | 2,440,462.25 | JYP General Construction | SB #1 CY 2019 | 2019-10-28 | 2020-02-03 | Completed | |
La Trinidad | Bahong | Improvement along Bahong - Sadag Provincial Road | Road | 4,000,000.00 | 3,900,818.14 | Efler Construction and Enterprise | 20% PDF CY 2019 | 2019-07-17 | 2020-01-08 | Completed | |
Buguias | Poblacion | Rehabilitation of Retaining Wall along Walayan-Naybo-Padang FMR | Road | 1,000,000.00 | 977,253.35 | ICO Construction Services | LDRRM Trust | 2019-12-06 | 2020-01-19 | Completed | 1.) Revised target date of completion: February 3, 2020.
2.) Actual date of completion: February 22, 2020. |
Buguias | Catlubong | Improvement of Ponopon - Lusab Farm to Market Road | Road | 1,000,000.00 | 997,017.77 | On Top Construction | SB #3 CY 2019 | 2020-01-31 | 2020-03-10 | Completed | |
Kabayan | Adaoay | Improvement of Lt. Alisandro Marquez Barangay Center | Building | 500,000.00 | 498,891.45 | Vanvin Construction and Supply | SB #1, CY 2019 | 2020-03-11 | 2020-05-03 | Completed | |
Mankayan | Cabiten | Completion of Multi-Purpose Building at Camanpaguey | Building | 500,000.00 | 496,285.01 | Baldas Construction | SB #1, CY 2019 | 2020-01-02 | 2020-02-17 | Completed | |
Kabayan | Gusaran | Improvement of Bakbakan - Akikian Farm to Market Road | Road | 1,000,000.00 | 981,387.80 | Vanvin Construction and Supply | SB #3 CY 2019 & 20% PDF CY 2019 | 2020-01-09 | 2020-03-02 | Completed | 1.) Revised target date of completion is: March 17, 2020;
2.) Actual date of completion is: March 17, 2020;
|
Kabayan | Pacso | Completion of Barangay Hall Extension | Building | 500,000.00 | 499,218.89 | Vanvin Construction and Supply | General Fund | 2019-12-20 | 2020-02-27 | Completed | Actual date of completion: February 27, 2020. |
Buguias | Buyacaoan | Construction of Gusadan Creek Flood Control | Flood Control | 1,000,000.00 | 996,581.06 | | 20% PDF 2019 | 2020-01-02 | 2020-03-06 | Completed | |
Sablan | Poblacion | Construction of Multi-Purpose Gym, at Poblacion Elementary School, Sablan, Benguet | Gym | 4,000,000.10 | 3,918,154.10 | Anas Construction | 20% PDF CY 2019 | 2020-02-22 | 2020-07-21 | Completed | |
Itogon | Tuding | Rehabilitation of Tuding - Manga - Luneta Road | Road | 1,000,000.00 | 994,775.75 | ICO Construction Services | LDRRMF Trust Fund 2019 | 2020-02-11 | 2020-04-08 | Completed | |
Buguias | Sebang | Construction of Waterworks System for Bacasen - Wakit Elementary School | Waterworks System | 1,500,000.00 | 1,469,598.00 | JYP General Construction | SEF 2019 | 2020-01-29 | 2020-03-29 | Completed | |
Kapangan | Balakbak | Construction of Balakbak Elementary School Comfort Room and Wash Station | Comfort Room | 500,000.00 | 464,097.45 | Vanvin Construction and Supply | SNAP Benguet & SB #1 CY 2019 | 2020-03-09 | 2020-09-01 | Completed | 1.) Suspended on March 17, 2020 due to COVID;
2.) Date resumed: July 20, 2020. |
Bokod | Nawal | Construction of Slope Protection along Nawal FMR | Slope Protection | 600,000.00 | 535,000.00 | N-J Construction | General Fund CY 2019 | 2019-11-18 | 2020-09-24 | Completed | 1.) Original target date of completion: December 21, 2019; Suspended due to ongoing DPWH widening project;
2.) Date resumed: August 22, 2020.
|
Buguias | Buyacaoan | Construction of concrete pavement along Peggueyna FMR | Road | 1,000,000.00 | 917,371.40 | Tepanlu construction & Supply | SB # 01- CY 2019 | 2019-10-31 | 2020-09-18 | Completed | 1.) Suspended on November 19, 2019;
2.) Resumed on March 5, 2020;
3.) Suspended again on March 17,2020 due to community quarantine;
4.) Resumed on September 12, 2020;
5.) Actual date of completion: September 16, 2020. |
Buguias | Poblacion | Improvement of Insalong - Lower Naybo - Bengad Farm to Market Road | Road | 3,000,000.00 | 2,986,585.76 | MXC Construction | SB # 03- CY 2019 & 20% PDF | 2020-03-23 | 2021-05-05 | Completed | 1.) Original Target Date of Completion: June 28, 2020;
2.) Suspended on March 17,2020 due to community quarantine;
3.) Date Resumed: January 28, 2021.
|
Kapangan | Paykek | Construction of Flood Control w/ slope protection at the Municipal ground | Flood Control | 4,000,000.00 | 3,916,996.27 | Bolos Engineering and Construction | 20% PDF CY 2019 | 0000-00-00 | 0000-00-00 | On going | Suspended on March 17,2020 due to community quarantine.
|
La Trinidad | Puguis | Improvement of Kibungan Village FMR | Road | 500,000.00 | 433,591.68 | Sangin General Construction | 20% PDF - 2019 | 0000-00-00 | 0000-00-00 | Terminated | Terminated as of Jan 30, 2020.
|
Bakun | Sinacbat | Opening of Makbas to Tenglawan Farm to Market Road | Road | 1,000,000.00 | 998,931.86 | FMC Warriors Construction | SB #03 CY 2019 & 20% PDF | 2020-03-04 | 2020-12-04 | Completed | 1.) Suspended effective on March 10,2020 due to procurement of ECC;
2.) Original target date of completion: April 28, 2020.
|
Kabayan | Ballay | Improvement of Darat-Lower Tamangan Farm to Market Road | Road | 3,000,000.00 | 2,937,340.49 | Jamil Sean Construction | SB #03 CY 2019 | 0000-00-00 | 2020-07-29 | Completed | |
Kabayan | Ballay | Improvement along Taaw-Luban FMR | Road | 1,000,000.00 | 998,799.00 | Jamil Sean Construction | SB #03 CY 2019 | 0000-00-00 | 2020-08-25 | Completed | |
Kabayan | Ballay | Improvement along Akikian-Lindawan (Besocol) FMR | Road | 1,000,000.00 | 998,974.16 | Jamil Sean Construction | SB #03 CY 2019 | 2020-04-24 | 2020-10-12 | Completed | 1.) Suspended on March 17, 2020 due to community quarantine;
2.) Date resumed: September 4, 2020;
3.) Actual date of completion: October 12, 2020. |
Kapangan | Gadang | Rehabilitation of Gadang FMR | Road | 1,200,000.00 | 1,035,919.04 | EKC Construction & Aggregates | 20% PDF CY 2019 | 0000-00-00 | 0000-00-00 | Terminated | Project lapsed, recommended for termination.
|
Mankayan | Balili | Improvement of Mogao-Dimoyog FMR | Road | 1,000,000.00 | 999,711.82 | ZMC General Construction | SB #03 CY 2019 - 20% PDF | 0000-00-00 | 0000-00-00 | Terminated | Recommended for termination due to blacklisting.
|
Mankayan | Bulalacao | School perimeter riprapping at Balili National High School-Cabacab annex | Riprap | 750,000.00 | 744,554.41 | Layad General Engineering Construction & Aggregates | SEF CY 2019 SB# 02 | 2020-03-17 | 2020-08-22 | Completed | 1.) Suspended on March 19,2020 due to community quarantine.
2.) Resumed on July 11, 2020.
3.) Completed on August 1, 2020.
|
Mankayan | Bulalacao | Improvement of Caew (Posdo)- Bulalacao FMR | Road | 2,000,000.00 | 1,994,060.48 | Sharamelle Construction and Engineering | SB #03 CY 2019 20% PDF | 2020-03-23 | 2020-11-19 | Completed | 1.) Suspended on March 23, 2020 due to community quarantine;
2.) Resumed on October 4, 2020.
|
Sablan | Poblacion | Construction of multi-purpose gym @ Poblacion Elem. School | Gymnasium | 4,000,000.00 | 3,918,154.10 | Anas Construction | 20% PDF CY 2019 | 0000-00-00 | 0000-00-00 | On going | Suspended on March 17,2020 due to community quarantine.
|
Tublay | Tuel | Construction of Slope Protection at Sitio Asin beside Sayangan footbridge | Slope Protection | 2,400,000.00 | 2,388,470.83 | Polo Engineering & Construction | General Fund CY 2019 | 0000-00-00 | 2020-09-12 | On going | |
Bakun | Dalipey | Construction of Flood Control at Sitio Lower Sipitan | Flood Control | 2,000,000.00 | 1,996,324.30 | Apaklo Kin Construction & Eng'g Services | 20% PDF CY 2019 | 2020-07-12 | 2020-09-12 | Completed | |
Buguias | Poblacion | Improvement of Giweng - Kimpit - Amlimay Farm to Market Road | Road | 1,000,000.00 | 996,969.98 | MXC Construction | SB #3, CY 2019 | 2020-07-30 | 2020-09-18 | Completed | Original target completion date: September 4, 2020. |
Buguias | Baculungan Sur | Improvement of Paneg-an - Obanga Farm to Market Road | Road | 2,000,000.00 | 1,998,496.70 | JYP General Construction | 20% PDF & SB #3, CY 2019 | 2020-09-10 | 2020-11-10 | Completed | |
Mankayan | Balili | School Perimeter Riprapping at Dagadag Elementary School | Riprap | | 747,644.76 | Baldas Construction | SEF CY 2019 | 2020-07-15 | 2020-09-08 | Completed | |
Buguias | Sebang | Improvement of Pasbol - Motyokna Farm to Market Road | Road | 2,000,000.00 | 1,998,752.18 | JYP General Construction | SB #3, CY 2019 | 2020-09-08 | 2020-11-22 | Completed | |
La Trinidad | Puguis | Improvement of Kibungan Village Farm to Market Road | Road | 500,000.00 | 499,226.72 | Layad General Engineering, Construction & Aggregates | 20% PDF, CY 2019 | 2020-08-26 | 2020-09-13 | Completed | Actual date of completion: September 8, 2020. |
Kabayan | Batan | Rehabilitation of Lower Batan Farm to Market Road | Road | 2,000,000.00 | 1,954,768.10 | QPJ General Engineering Construction and Supply | LDRRMF Trust Fund | 2020-08-14 | 2020-10-08 | Completed | Actual date of completion: September 23, 2020. |
Tublay | Baayan | Reconstruction of Barangay Health Station | Building Repair | 1,500,000.00 | 1,498,349.99 | Emnar Construction and Engineering Services | SB #1, CY 2019 | 2020-08-18 | 2020-11-11 | Completed | |
Kibungan | Badeo | Improvement of Badeo School Ground and Fencing | Ground Improvement and Fencing | 500,000.00 | 498,348.80 | JMLP Builders | SEF | 2020-02-27 | 2020-10-12 | Completed | 1.) Original target date of completion: June 23, 2020.
2.) Actual date of completion: October 4, 2020. |
Tuba | Ansagan | Construction of Concrete Drainage Canal at Evelio Javier Memorial National High School | Canal | 500,000.00 | 499,472.85 | Aroboan Construction and Supply | SEF | 2020-09-11 | 2020-10-20 | Completed | |
Kabayan | Gusaran | Construction of Flood Control at Gusaran | Flood Control | 3,000,000.00 | 2,976,943.08 | Vanvin Construction and Supply | SB #3, 2019 | 2020-08-31 | 2020-12-11 | Completed | |
Mankayan | Balili | Construction of Two-Storey Palpaltogan Child Development Center and Multi-Purpose Hall | Building | 1,500,000.00 | 1,479,825.73 | Layad General Engineering, Construction and Aggregates | SEF | 0000-00-00 | 0000-00-00 | Completed | |
Tuba | San Pascual | Improvement of the Access Road at the Benguet Animal Learning Site and Farm Tourism | Retaining Wall | 2,000,000.00 | 1,997,033.51 | Roben Runas Construction | SB #1, CY 2019 | 2020-08-31 | 2020-11-15 | Completed | |
Kabayan | Kabayan Barrio | Construction of Elbag to Kinapol Footbridge | Footbridge | 1,000,000.00 | 999,385.12 | Botjack Construction | SB #3 CY 2019 | 2020-09-07 | 2020-12-22 | Completed | Original target date of completion: November 20, 2020 |
Buguias | Loo | Improvement of Modayan Becaeg Kitongan Farm to Market Road | Road | 1,000,000.00 | 997,900.51 | Potpotan General Construction | 20% PDF CY 2019 | 2020-09-28 | 2020-11-19 | Completed | |
Kabayan | Tawangan | Improvement of Aw-awa to Ankatit Farm to Market Road | Road | 1,500,000.00 | 1,498,514.47 | Jamil Sean Construction | SB #3 CY 2019 & 20% PDF | 2020-09-02 | 2020-12-04 | Completed | |
Bakun | Gambang | Improvement of Sookan - Gambang Farm to Market Road | Road | 4,000,000.00 | 3,996,710.43 | Drichloui Construction | SB #3 CY 2019 | 0000-00-00 | 0000-00-00 | Completed | |
Tublay | Central Tublay | Improvement of Tublay School of Home Industries Extension Grounds | Ground Improvement | 2,000,000.00 | 1,927,613.70 | Apwaltz Construction Services and Supplies | General Fund 2019 | 2020-09-18 | 2021-01-12 | Completed | |
La Trinidad | Wangal | Construction of Drainage Canal at the Benguet Sports Center | Canal | 3,000,000.00 | 2,898,610.53 | MXC Construction | General Fund CY 2019 | 2020-09-08 | 2021-03-04 | Completed | Actual date of completion: March 3, 2021. |
Kabayan | Tawangan | Improvement of Nanhabitan - Kapalan Farm to Market Road | Road | 1,500,000.00 | 1,498,432.82 | Jamil Sean Construction | 20% PDF CY 2019 | 2020-09-02 | 2021-03-04 | Completed | |
Kabayan | Pacso | Completion of One-Storey Building for Asokong Pacso Elementary School | Building | 800,000.00 | 798,540.12 | Botjack Construction | SEF CY 2019 | 2021-01-11 | 2021-03-29 | Completed | |
Kibungan | Madaymen | Rehabilitation of Halsema - Madaymen Provincial Road Pakpakitan Section | Road | 5,000,000.00 | 4,998,499.78 | LBJ Construction | LDRRM - Trust Fund CY 2019 | 2021-01-17 | 2021-07-26 | Completed | |
Sablan | Bagong | Construction of Riprap along Bito - Cayapes Farm to Market Road | Road | 300,000.00 | 289,490.06 | Bolos Construction | LDRRMF Trust Fund CY 2017 | 2020-02-04 | 2020-03-12 | Completed | |
Buguias | Bangao | Improvement of Cotcot - Bolinaca Farm to Market Road | Road | 500,000.00 | 498,486.44 | On Top Construction | General Fund CY 2020 | 2020-03-04 | 2020-03-31 | Completed | |
Bakun | Dalipey | Improvement along Bengdana - Bao-edan Road | Road | 1,000,000.00 | 999,360.70 | Apaklokin Construction & Engineering Services | 20% PDF CY 2020 | 2020-08-10 | 2020-09-18 | Completed | |
Bakun | Dalipey | Improvement along Sayangan - Toplao Farm to Market Road | Road | 1,000,000.00 | 994,736.70 | NAIR Construction and Engineering | 20% PDF CY 2020 | 2020-08-10 | 2020-09-18 | Completed | |
Buguias | Sebang | Improvement Suyong - Malmalbeng Farm to Market Road | Road | 1,000,000.00 | 997,858.50 | On Top Construction | 20% PDF CY 2020 | 2020-07-16 | 2020-09-10 | Completed | Original target date of completion: August 26, 2020 |
Atok | Paoay | Improvement of Paoay Barangay Hall | Building | | 650,350.13 | Vanvin Construction and Supply | General Fund CY 2020 | 2020-08-10 | 2020-09-18 | Completed | |
Bokod | Bila | Construction of Concrete Pavement at Balangabang Degiw Farm to Market Road | Road | 500,000.00 | 499,231.41 | Sherfelias Construction | 20% PDF, CY 2020 | 2020-08-10 | 2020-09-18 | Completed | |
La Trinidad | Wangal | Construction of Sidewalk with Railings and Fence along Stockfarm Road (near PDRRMO and Allied Building) | Sidewalk | 1,500,000.00 | 1,487,235.57 | MXC Construction | LDRRMF Trust Fund | 2020-07-30 | 2020-12-14 | Completed | Actual date of completion: October 7, 2020. |
Buguias | Baculongan Sur | Improvement of Obanga - Dekan - Lengaoan Farm to Market Road | Road | 500,000.00 | 484,521.36 | JNA Construction and Supply | 20% PDF, CY 2020 | 2020-09-18 | 2020-10-18 | Completed | Actual date of completion: October 10, 2020. |
Tuba | Camp 6 | Construction and Installation of Waterworks System at Golden Eagle Tollgate | Waterworks system | 700,000.00 | 699,514.73 | AMPSLEO Construction | 20% PDF 2020 | 2020-08-20 | 2020-10-24 | Completed | |
Mankayan | Colalo | Improvement of Bonie - Salingay Farm to Market Road | Road | 1,000,000.00 | 998,864.38 | DIPAS Builders | 20% PDF, CY 2020 | 2020-09-09 | 2020-10-15 | Completed | |
Buguias | Natubleng | Concreting of Apanberang ABB - Upper Patkiaw Road | Road | 1,000,000.00 | 997,139.82 | Potpotan General Construction | 20% PDF, CY 2020 | 2020-08-31 | 2020-10-31 | Completed | |
Buguias | Loo | School Improvement of Pan-ayaoan Elementary School, Pan-ayaoan, Loo | Riprap and Footpath | 1,000,000.00 | 996,305.07 | On Top Construction | SEF CY 2020 | 2020-08-24 | 2020-10-03 | Completed | |
Tuba | Poblacion | Construction of Erosion Control | Erosion Control | 1,000,000.00 | 998,413.59 | Roben Runas Construction | 20% PDF, CY 2020 | 2020-08-30 | 2020-10-30 | Completed | |
Sablan | Bagong | Concreting of Footpath with Railings along Bito to Tofil Footpath | Footpath | 500,000.00 | 495,894.56 | Bolos Engineering and Construction | General Fund CY 2020 | 2020-09-07 | 2020-10-04 | Completed | |
La Trinidad | Alapang | Construction of Flood Control at Alapang Proper (Sagubo Area towards Ogas Area) | Flood Control | 1,000,000.00 | 999,069.99 | Anitos Construction | 20% PDF CY 2020 | 2020-09-03 | 2020-11-06 | Completed | |
Mankayan | Guinaoang | Construction of Riprap (9 meters high by 45 meters long) on the Side of Guinaoang National High School Gymnasium | Riprap | 1,000,000.00 | 1,000,000.00 | Apwaltz Construction Services and Supplies | SEF CY 2020 | 2020-09-08 | 2020-11-08 | Completed | |
La Trinidad | Tawang | Construction of footpath with railings near Bautista Area to Boted, Tawang | Footpath with railings | 500,000.00 | 464,986.70 | QPJ General Engineering Construction and Supply | General Fund CY 2020 | 2020-10-07 | 2020-11-30 | Completed | Actual date of completion: November 14, 2020. |
Buguias | Amgaleyguey | Improvement of Junction 204 - Aguday Amgaleyguey Road | Road | 500,000.00 | 496,877.17 | | 20% PDF CY 2020 | 0000-00-00 | 0000-00-00 | Completed | |
Tublay | Daclan | Improvement of Malanac-Shekdan Road | Road | 1,000,000.00 | 990,037.27 | Anas Construction | 20% PDF 2020 | 2020-10-13 | 2020-12-10 | Completed | |
Mankayan | Bedbed | Rehabilitation of Longlong-Payeo Road | Road | 1,000,000.00 | 997,512.55 | Layad General Engineering Construction and Aggregates | 20% PDF CY 2020 | 2020-09-11 | 2021-01-03 | Completed | |
Mankayan | Bedbed | Construction of Concrete Pavement along Degway-Payeo Road | Road | 1,000,000.00 | 998,471.88 | Layad General Engineering Construction and Aggregates | 20% PDF CY 2020 | 2020-09-11 | 2020-12-23 | Completed | |
Buguias | Baculongan Norte | Improvement of JPMR-BPLS-PUGO-CUDAL-LAMMANGAN-JFMR OCDL (Tupinaw Section) | Road | 1,000,000.00 | 997,315.14 | Potpotan General Construction | 20% PDF CY 2020 | 0000-00-00 | 0000-00-00 | Completed | |
Buguias | Loo | Improvement of JPMR - LANAS - TABA-AO Sumilalaw JPMR BPLS (Upper Togtogyon Section) | Road | 1,000,000.00 | 997,315.14 | Potpotan General Construction | 20% PDF CY 2020 | 2020-11-06 | 2020-12-31 | Completed | |
Mankayan | Balili | Improvement of Pasna-an - Ayosep Community / Barangay Road | Road | 1,000,000.00 | 996,234.41 | Baldas Construction | General Fund CY 2020 | 2020-09-11 | 2020-11-02 | Completed | |
Tuba | Camp 3 | Improvement of eroded portion beside Philex Mines Elementary School | Riprap | 1,000,000.00 | 984,980.83 | Ampsleo Construction | 20% PDF CY 2020 | 2020-10-18 | 2021-01-05 | Completed | |
Bakun | Poblacion | Installation of hand railings going to Mt. Kabunian, Bakun | Railings | 400,000.00 | 398,652.93 | Pulicay Grandson's Construction | General Fund 2020 | 2020-12-16 | 2021-01-22 | Completed | |
Tuba | Camp 6 | Construction of shed with railings from EJMNH to Gusaran, Camp 6, Tuba | Shed with railings | 2,000,000.00 | 1,825,830.92 | Rigne General Construction | General Fund 2020 | 2020-10-01 | 2020-12-07 | Completed | |
Buguias | Amgaleyguey | Improvement of JFMR - NMS Baso Road | Road | 1,500,000.00 | 1,488,112.14 | BTCJR Construction and Engineering Services | 20% PDF CY 2020 | 2020-12-21 | 2021-01-31 | Completed | Actual date of completion: January 17, 2021. |
Buguias | Abatan | Improvement of Hospital Canal at Northern Benguet District Hospital | Canal | 500,000.00 | 499,088.71 | Potpotan General Construction | 20% PDF CY 2020 | 2020-12-09 | 2020-12-28 | Completed | |
Buguias | Baculongan Norte | Improvement of Pugo Farm to Market Road | Road | 1,000,000.00 | 995,230.24 | On Top Construction | 20% PDF CY 2020 | 2020-10-15 | 2020-12-26 | Completed | |
Buguias | Sebang | Improvement of Panig-an Tamangan Farm to Market Road (Suyong Section) | Road | 1,000,000.00 | 995,418.23 | On Top Construction | 20% PDF CY 2020 | 2020-11-16 | 2021-01-03 | Completed | Actual date of completion: January 12, 2021. |
Tuba | Ansagan | Construction of 8x8 water tank with 25 rolls 3/4" hose pipe | Waterworks | 500,000.00 | 496,729.78 | Mandiit Construction Services | 20% PDF CY 2020 | 2020-11-22 | 2021-01-09 | Completed | |
La Trinidad | Alno | Improvement / Rehabilitation along Alno-Tuel-Balway Provincial Road | Road | 2,000,000.00 | 1,949,511.08 | Sandstream Construction | LDRRMF CY 2020 | 2020-09-14 | 2020-12-24 | Completed | Actual date of completion: January 18, 2021 |
Bakun | Ampusongan | Improvement of Riverside Sawmill Access Road | Road | 600,000.00 | 599,315.32 | Apaklo Kin Construction & Engineering Services | PDF CY 2020 | 2020-12-09 | 2021-01-24 | Completed | |
Buguias | Baculungan Sur | Improvement of Man-asok Kaula-an to Sabeng Anito Farm to Market Road | Road | 1,000,000.00 | 995,950.18 | On Top Construction | PDF CY 2020 | 2020-12-23 | 2021-01-31 | Completed | |
Buguias | Poblacion | Improvement of Open Gym | Improvement of Gym | 500,000.00 | 496,813.50 | Wacaden Construction | General Fund CY 2020 | 2020-12-02 | 2021-01-16 | Completed | |
Mankayan | Poblacion | Construction of Panad Multi-Purpose Building, Panad West (Phase II) | Building | 1,000,000.00 | 995,976.66 | Eugao Construction | PDF CY 2020 | 2020-12-17 | 2021-02-19 | Completed | Actual date of completion: February 1, 2020. |
Buguias | Loo | Construction of Pusong Flood Control | Flood Control | 500,000.00 | 496,991.66 | Potpotan General Construction | 20% PDF CY 2020 | 2020-12-28 | 2021-02-02 | Completed | |
Buguias | Loo | Improvement of Togtogyon, Loo Road Section Farm to Market Road | Riprap | 1,000,000.00 | 996,742.79 | Potpotan General Construction | 20% PDF CY 2020 | 2020-12-29 | 2021-02-16 | Completed | |
Bakun | Sinacbat | Construction of Permanent Fence of Alicay-Segundo Elementary School | Fence | 500,000.00 | 499,137.35 | SRBA General Construction | SEF CY 2020 | 2021-01-11 | 2021-02-21 | Completed | |
Kibungan | Palina | Road Opening at Batbato - Nay-a Access Road | Road Opening | 2,000,000.00 | 1,999,892.66 | LBJ Construction | 20% PDF CY 2020 | 2020-09-28 | 2021-02-25 | Completed | Actual date of completion: February 19, 2021. |
Atok | Paoay | Fencing within the Benguet-Kochi Sisterhood Park | Fencing | 1,000,000.00 | 998,511.06 | Haight's Construction | General Fund CY 2020 | 2020-12-22 | 2021-02-11 | Completed | Actual date of completion: February 10, 2021. |
Bakun | Bagu | Construction of Catwalk Shed at Dio-alan Elementary School | Catwalk Shed | 600,000.00 | 599,599.08 | Kankaloi Construction | SEF CY 2020 | 2021-01-21 | 2021-03-24 | Completed | Actual date of completion: February 22, 2021. |
Bakun | Ampusongan | Road Opening from Damoag to Palag-ang | Road Opening | 1,000,000.00 | 998,923.38 | Pulicay Grandson's Construction | 20% PDF CY 2020 | 2021-01-08 | 2021-03-06 | Completed | Actual date of completion: March 3, 2021. |
Tuba | Tabaan Sur | Construction of Box Culvert at Punas Creek, Andolor, Tabaan Sur | Box Culvert, Grouted Riprap, PCCP, and Railings | 1,000,000.00 | 996,593.60 | CAMROCK Construction | 20% PDF CY 2020 | 2020-10-14 | 2021-03-11 | Completed | Actual date of completion: March 8, 2021. |
Atok | Topdac | Construction of Footbridge at Taytay, Cadian | Footbridge | 800,000.00 | 797,385.79 | Vanvin Construction and Supply | General Fund CY 2020 | 2021-01-18 | 2021-03-19 | Completed | |
Buguias | Baculongan Norte | Improvement of JFMR LPK - Pugo - Lengat Road | Road | 1,000,000.00 | 995,920.17 | On Top Construction | 20% PDF CY 2020 | 2020-11-16 | 2021-03-15 | Completed | 1.) Original Target Date of Completion: December 27, 2020;
2.) Date Suspended: January 7, 2021;
3.) Date Resumed: March 9, 2021;
4.)Actual Date of Completion: March 15, 2021 |
Tuba | Tabaan Sur | Improvement along Camp 1 - Indaoac - Twin Peaks Provincial Road | Road | 8,000,000.00 | 7,994,119.08 | Roben Runas Construction | 20% PDF CY 2020 | 2020-11-26 | 2021-03-30 | Completed | Original Target Date of Completion: February 26, 2021. |
Itogon | Ampucao | Improvement of Ground and Construction of Basketball Court, Upper Camp, Ampucao | Gym | 1,500,000.00 | 1,460,036.04 | Babecor Builders | GF CY 2019 | 2019-11-28 | 2020-01-10 | Completed | |
Mankayan | Tabio | Improvement along Mankayan Bato Provincial Road | Road Improvement | 5,000,000.00 | 4,885,222.88 | Layad Gen. Engineering, Construction & Aggregates | 20% PDF 2019 | 2019-11-25 | 2020-01-19 | Completed | |
Buguias | Bad-ayan | Improvement along Bad-ayan - Manhuyhoy Provincial Road | Road Improvement | 5,000,000.00 | 4,880,004.03 | JYP General Construction | 20% PDF 2019 | 2019-10-23 | 2020-01-28 | Completed | |
Tuba | Tadiangan | Construction of Police Outpost and Tourism Information and Assistance Center at Tadiangan, Tuba | Construction of Building | 1,500,000.00 | 1,495,954.42 | SAPDOY Enterprises | 2015 GF & 20% PDF 2015 | 2019-01-31 | 2019-05-19 | Completed | Completed |
Tuba | Camp 1 | a.) Reconstruction of Public Market Building, Klondykes, Camp 1; b.) Construction of Market (additional) Camp 1, Tuba | Building Repair | 2,165,000.00 | 2,162,703.44 | roben runas construction/roben runas | 20% PDF CY 2015 & 20% PDF CY 2016 | 2016-06-27 | 2017-04-28 | Completed | Clustered project (different fund & titles) a) reconst of Public Market Bldg Klondykes @ Camp , Tuba; b) const of market (add'l) @ Camp 1, Tuba |
Tublay | Tublay Central | a) Construction of Tanibao Footbridge; b) Construction of Tanibao Foot Bridge (Additional) | Bridge | 500,000.00 | 497,716.60 | Pulicay's Grandson Construction | 20% PDF - 2016 & SB No. 1 - 2017 | 2018-05-09 | 2018-06-16 | Completed | Completed = 07/10/2018 |
Itogon | Ampucao | Construction of drainage canal, Dontog, Dalicno | Road Side | 1,000,000.00 | 998,307.74 | renton engineering and services/ enrique waldo | SB No. 2 CY 2016 | 2017-02-17 | 2017-06-11 | Completed | |
Kapangan | Balakbak | Construction of Barangay Health Station (Phase III and Additional) | Building | 1,500,000.00 | 1,494,818.89 | Balangcod Construction | General Fund CY 2017 20% PDF CY 2016 | 2018-01-18 | 2018-06-11 | Completed | |
Kabayan | Eddet | Construction of Eddet Barangay Hall Comfort Rooms | Building | 375,000.00 | 366,124.92 | akiki builders/ ruben aguinse | General Fund CY 2015 SB No. 5 CY 2015 | 2016-12-01 | 2017-04-25 | Completed | Completed and usable with liquidated damages |
La Trinidad | Poblacion | Construction of Provincial Jail MPB at the Capitol Compound | Building | 1,000,000.00 | 989,456.73 | almond engineering and construction/ rogelio alimo | General Fund CY 2015 All Office, SB No. 9 CY 2015 | 2016-05-12 | 2017-04-10 | Completed | |
Kapangan | Pudong | Completion of Barangay Health Station at Pudong, Kapangan | Completion of Building | 800,000.00 | 799,489.84 | Four Brothers Construction | SB #2 GF 2015 | 2019-02-26 | 2019-06-22 | Completed | Completed.(Revised target date= 06/24/2019 ) |
Bokod | Ambuclao | Rehabilitation of Banao Footbridge | Bridge | 600,000.00 | 598,984.13 | BLDY Eng'g & Construction | GF (2015 LDRRMF lumpsum) | 2019-01-31 | 2019-03-01 | Completed | |
Sablan | Banangan | Construction of Historical Marker at Dakis Viewdeck ,Sablan | Construction of Marker | 100,000.00 | 94,842.46 | Anas Construction | SB # 05 - 2015, GF | 2019-03-25 | 2019-04-13 | Completed | Completed |
La Trinidad | Betag | Construction of Multi-purpose Building (DCC), Construction of Building at Betag (Additional), Construction of Betag Barangay Hall (Additional) | Building | 2,000,000.00 | 1,978,891.96 | Symon Engineering and Construction | General Fund CY 2015, SB No. 2 CY 2015, SB No. 2 CY 2016 GF | 2017-01-31 | 2017-05-28 | Completed | partial payment poc, const multi purpose bldg dcc betag la trinidad, const multi purpose bldg betag, const betag brgy hall |
La Trinidad | Balili | Construction of Sidewalk Shed-Halsema Road to UCCP Church, Balili, La Trinidad, Benguet | Roads and Bridges | 700,000.00 | 673,514.31 | SEJ Construction and Aggregate | SB No. 2 GF CY 2016 | 2018-04-25 | 2018-07-02 | Temporarily suspended | 1) The contractor submitted a letter for suspension due to the site issues
2) Suspended on April 30, 2018 because the BSU management is against the project since part of the structure to be put up will encroach their property.
3) Update as of June 2019 |
Buguias | Amlimay | Improvement of Guioeng Kimpit FMR, Amlimay, Buguias, Benguet | Semi-permanent Structure | 200,000.00 | 198,887.83 | Juricmarc Construction | SB#02CY2016-GF Non Office | 2018-09-24 | 2018-10-21 | Completed | |
Kapangan | Pudong | Improvement of Cabilisan FMR | FMR Concreting | | 800,000.00 | 787,011.57 | SB # 02-2016,GF | 2018-11-13 | 2018-12-22 | Completed | Completed .Revised Target Date= 01/05/2019
|
Buguias | Catlubong | Construction of Padang - Palakad Footpath in Catlubong | Construction of Foot path | 350,000.00 | 346,308.80 | On Top Construction | SB # 2-2016, GF | 2018-04-13 | 2018-05-16 | Completed | |
Mankayan | Balili | Fencing of Balili National High school in Balili, Mankayan, Benguet | Construction of Fence | 100,000.00 | 98,822.67 | Baldas Construction | SB # 2 - 2016, GF | 2018-11-14 | 2018-12-02 | Completed | |
Kapangan | Gadang | Conctruction of Concrete Footbridge at Gadang, Kapangan | Construction of Footbridge | 412,000.00 | 390,781.54 | Four Brothers Construction | SB # 02-2016, GF01 | 2019-02-25 | 2019-04-15 | Completed | Completed with LD
|
Tuba | Camp 4 | Construction of Flood Control Riverside, Camp 6, Tuba | Road Side | 500,000.00 | 498,446.92 | Roben Runas Construction | SB No. 2 & GF CY 2016 | 2017-01-26 | 2017-03-22 | Completed | |
La Trinidad | Wangal | Improvement of Benguet Housing Project, Block 1, Phase II Alley, Wangal, La Trinidad, Benguet | | 540,000.00 | 475,411.75 | SEJ Construction and Aggregate | SB No.1 GF CY 2017 (PEO) | 2018-04-25 | 2018-06-18 | Completed | Completed September 5, 2018 |
Mankayan | Bulalacao | Construction of Senior Citizens Building (Phase II), Bulalacao, Mankayan | Building | 1,500,000.00 | 1,480,268.69 | Sharamalle Construction & Gen. Engineering | SB # 01-2017, GF | 2018-05-17 | 2018-09-23 | Completed | |
Tuba | Tabaan Norte | Improvement of Bonungbong-Toybungan FMR, Tabaan, Norte | FMR improvement | 500,000.00 | 494,022.08 | Juricmarc Construction | SB # 01-2017-GF | 2018-10-01 | 2018-11-09 | Completed | Completed. Revised Target Date = 01/06/2019 |
Itogon | Dalupirip | Construction of Laurencio Fianza NHS Annex TLE Classroom at Bantic, Dalupirip, Itogon | Classroom construction | 1,000,000.00 | 959,434.01 | SRBA General Construction | SB # 1-2017, GF | 2018-12-12 | 2019-03-11 | Completed | Completed.Revised Target Date = 26/03/2019
|
Itogon | Dalupirip | Construction of Vermi Compost Shed, Bantic, Itogon, Benguet | Vermi compost construction | 220,000.00 | 219,844.18 | SRBA General Construction | SB # 1-2017, GF | 2018-12-02 | 2019-02-07 | Completed | Completed and Usable. |
Kibungan | Tacadang | Construction of Lamagan-Litalit View Deck at Batangan, Tacadang, Kibungan, Benguet | Construction of View Deck | 600,000.00 | 597,651.04 | Malco Construction | SB # 1-2017, GF | 2018-11-08 | 2019-03-31 | Completed | |
Mankayan | Sapid | Improvement/Extension of Senior Citizen's Multi-Purpose Building Sapid, Mankayan, Benguet | Senior Citizen Multi-purpose Building Improvement | 500,000.00 | 479,777.95 | Sandstream Construction | SB # 1-2017, GF | 2018-11-28 | 2019-02-20 | Completed | Completed |
Mankayan | Colalo | Improvement of Busan FMR, Colalo, Mankayan, Benguet | Construction of PCCP | 800,000.00 | 797,202.07 | Malco Construction | SB # 01 - 2017, GF | 2018-07-05 | 2018-09-02 | Completed | Completed on August 30, 2018
Revised Target date of completion - September 9, 2018 |
La Trinidad | Poblacion | Improvement of access road (phase II) at Windy Hill, Central Buyagan | Roads | 1,000,000.00 | 995,600.40 | BTCJR Construction and Eng'g Services | SB #2 2018 General Fund PEO | 2019-06-07 | 2019-08-06 | Completed | |
Kibungan | Sagpat | Construction of Sagpat Gymnasium, Sagpat | Building | 2,300,000.00 | 2,297,806.51 | Drichloui Construction | General Fund - Non Office CY 2017, PSBF CY 2016 | 2017-08-05 | 2017-11-24 | Completed | Additional fund: Php 1,500,000.00 under PSBF CY 2016;
Has a total ABC of Php 2,300,000.00
Partial accomplishment, Clustered "C" Project - a) const of sagpat gym @ sagpat, kibungan; b) const of gym for sagpat E/S @ Sinagpat, Kibungan (Add'l) |
Kapangan | Paykek | Road upgrading and improvement of Lomon-Sagubo provincial road, Kapangan, Benguet | Road Improvement | 63,829,590.00 | 59,850,000.00 | Jomarcann General Construction | CMGP 2018 | 2018-12-18 | 2019-08-24 | Completed | |
Mankayan | Guinaoang, Suyoc, Gambang | Road upgrading and improvement of Guinaoang - Suyoc - Gambang Provincial Road (Phase II) | Road Improvement | 44,000,000.00 | 39,679,432.27 | Rodekom General Construction | CMGP | 2019-03-25 | 2019-10-07 | Completed | Completed and usable, Geo-tagged on October 30, 2019. |
La Trinidad | Beckel | Installation of complete electrical system of Barangay Beckel Senior Citizens | Electrical System | 100,000.00 | 82,901.46 | Haight's Construction | SB#1 2018 | 2019-02-07 | 2019-02-17 | Completed | Inspection was done on March 1, 2019.
Electrical wiring was completed but, the there is no connection yet with BENECO Power and electrical post and meter is not yet installed. |
Buguias | Sebang | Construction of Tamangan - Wakit - Bacasen Primary School Gymnasium, Construction of Bacasen - Wakit Elementary School Gymnasium (Phase 2) | Building | 5,000,000.00 | 4,988,781.88 | JYP General Construction | 20% PDF CY 2016 SB No. 2 CY 2016 | 2016-12-14 | 2017-06-15 | Completed | final payment - a) const of tamangan-wakit-bacasen P/S gym, sebang (phase I); b) const of bacasen wakit E? gym (phase II) @ sebang |
Kapangan | Sagubo | Rehabilitation of Landing - Bileng FMR at Sitio Bileng | Raod Improvement | 600,000.00 | 598,254.54 | Bolos Eng'g and Construction | Gen. Fund 2019 | 2019-11-01 | 2020-01-29 | Completed | |
Tublay | Daclan | Improvement of Open Gym, Daclan, Tublay, Benguet | Gym | 500,000.00 | 497,399.98 | Right Achor Construction | SB-03 CY 2019 | 0000-00-00 | 2020-01-20 | Completed | Project Engineer: John G. Pilay
Quality Control Representative: Harris Bill T. Palangdan |
Buguias | Baculungan Sur | Improvement Along Palinta-Ang-Abbao FMR, Baculungan Sur | PCCP | 1,000,000.00 | 998,136.22 | On Top Construction | GF 2019 | 2019-11-26 | 2020-01-20 | Completed | Project Engineer: Arthur P. Banasan
QC Representative: Engr. Teofilo Lacaden |
Buguias | Baculungan Sur | Improvement along Bad-ayan - Balintag -Deckan - BPI Baculungan Sur, Buguias, Benguet (156 Malsema Creek Riprap) Buguias, Benguet | Road Improvement | 1,000,000.00 | 998, 136.22 | Potpotan General Construction | SB # 3 2019 | 2020-01-12 | 2020-02-04 | Completed | Project Engineer: Arthur P. Banasen
Quality Control Representative : Engr. Teofilo Lacaden |
Bakun | Apusongan | Opening and Improvement of Palitay-Kegangan FMR, Ampusongan, Bakun, Benguet | Road Opening | 800,000.00 | 795,679.85 | | GF 2017 | 2020-05-01 | 2020-02-10 | Completed | Project Engineer: Devereux Khyle Heinrich A. Oliano
QC: Mosi
Geotagged by: JC |
Sablan | kamog | Construction of Retaining Wall Along Balluay-Bagong FMR (Peril Section), Bagong, Sablan | Road Improvement | 1,700,000.00 | 1,663,341 | Bolos Eng'g and Construction | LDRRMF | 2020-01-01 | 2020-10-01 | Completed | Project Engineer: Santos Asan
QC: Engineer Lacaden
Geotagged by: JC |
Sablan | Bagong | Construction of Foot Path and Railing Stallation along Depuac, Buyagan, Bagong, SablanAlong Depuac | Foot path and railing | 500,000.00 | 497,582.20 | Bolos Eng'g and Construction | 20% PDF | 2019-12-02 | 2020-02-11 | Completed | Project Engineer: Santos Asan
QC: Engr. Teofilo Lacaden
Geotagged by: J G. C |
Kapangan | Cayapes | Construction of Daycare Center, at Cayapes, Kapangan, Benguet | Construction of Building | 350,000.00 | 329,287.64 | On Top Construction | 20% PDF 2012 | 2019-01-31 | 2019-03-24 | Completed | |
Atok | Paoay | Completion of 2-Storey Multi-Purpose Building | Building | 200,000.00 | 199,464.55 | leo heirs construction/ emmanuel leo | 20% PDF CY 2013 | 2016-07-20 | 2016-09-29 | Completed | Completed with slippage |
La Trinidad | Poblacion | Construction of Daycare Center (Additional), Kesbeng | Building | 1,000,000.00 | 998,487.40 | on top construction/ thomas palileng | 20% PDF CY 2013 | 2016-06-29 | 2016-11-11 | Completed | |
Tuba | Tadiangan | Construction of Water Distribution Tank at Lower Ampusa, Yagyagan, Tuba | Waterworks | 201,408.00 | 200,444.65 | Anas Construction | 20% PDF 2013 | 2018-10-05 | 2018-10-27 | Completed | |
La Trinidad | Beckel | Construction of Waterworks System, Beckel Community, Beckel, La Trinidad, Benguet | Waterworks | 400,000.00 | 399,252.72 | Bemeda Construction | 20% PDF - 2014 | 2018-08-16 | 2018-11-11 | Completed | |
Atok | Paoay | Tirepathing of Togontongao FMR | Roads | 500,000.00 | 498,789.03 | JCA General Construction and Engineering Services | 20% PDF CY 2015 | 2017-07-04 | 2017-10-16 | Completed | Part of Clustered A projects, - b) completion of pathway shed, adoyunan elem school @ abiang, atok; c) concreting of boneng elem school grounds, boneng, naguey at atok d) tirepathing of tagontongaw FMR |
Bakun | Ampusongan | Construction of Concrete Tirepath along Gayabasan to Dalipey FMR | Roads | 650,000.00 | 647,268.98 | Reasons Construction | 20% PDF CY 2015 | 2017-01-20 | 2017-02-10 | Completed | Cluster "B" a) Control No. 02-16-00009 b) Control No. 02-16-00010 - Reasons Construction
contract clusterd b, a)imp of nursery bldg, bagtangan e/s; b)concreting of maudong-baoy pathway; c)const of concrete tirepath along gayabasan-dalipey FMR |
Bokod | Daclan | Improvement of Supply Room, DMMH | Building Repair | 1,000,000.00 (clustered) | | Summerlin Construction | 20% PDF CY 2015 | 2017-09-29 | 2017-12-28 | Completed | contract under cluster d: a) const of mrf dmdh; b) imp of supply room, dmdh; c) const of shaded parking for hospital vehicles, dmdh (daclan, bokod) |
Buguias | Abatan | Construction of Concrete Pavement of Nakiangan FMR to the Turning Point | Road | 400,000.00 | 399,759.72 | hgw=3 engineering & construction/hilbert willie | 20% PDF CY 2015 | 2017-11-29 | 2017-12-18 | Completed | For Post Inspection |
Kabayan | Lusod | Construction of Cabulao - Hoyocto FMR | Roads | 500,000.00 | 498,938.44 | 4 Brothers Construction | 20% PDF CY 2015 | 2016-11-09 | 2017-02-14 | Completed | Completed and usable with underrun |
Kabayan | Adaoay | Construction of Cattle Barn/Shed at Adaoay | Barn | 500,000.00 | 496,858.71 | solonio construction/ritchie solonio | 20% PDF CY 2015 | 2017-02-20 | 2017-04-27 | Completed | Completed and usable with underrun |
Kabayan | Bashoy | Improvement of Grounds Bashoy Multi-Purpose Warehouse and Nursery Site | Building | 500,000.00 | 497,640.00 | 4 Brothers Construction | 20% PDF CY 2015 | 2017-02-07 | 2017-04-10 | Completed | Completed and usable with underrun |
La Trinidad | Wangal | Construction of Soil less Potato Seed and Strawberry Runner Production Center | Building | 2,000,000.00 | 1,993,071.33 | Aguinsod Construction | 20% PDF CY 2015 | 2017-12-04 | 2018-04-23 | Completed | |
La Trinidad | Wangal | Construction of Benguet Multi-purpse Building (Training Center) | Building | 15,000,000.00 | 14,989,060.01 | | 20% PDF CY 2015 | 2016-06-27 | 2017-12-07 | Completed | Input the accurate coordinates of the project.
PARTIAL ACCOMPLISHMENT, re: Construction of Benguet Multi-purpose Building (training center) @ Wangal, LTB |
La Trinidad | Betag | Construction of Hospital Waste Management Facility | Building | 500,000.00 | 498,974.45 | almond engineering and construction/ rogelio alimo | 20% PDF CY 2015 | 2016-12-05 | 2017-03-22 | Completed | Completed with approved Change Order. |
Mankayan | Bulalacao | Ripraping of FMR, Caew, Bulalacao, Mankayan | Road Side | 500,000.00 | 496,880.09 | balangcod construction/fermin balangcod | 20% PDF CY 2016 | 2016-12-01 | 2017-01-08 | Completed | |
Kibungan | Sagpat | Improvement along Sagpat-Sapdaan Provincial Road | Roads | 2,500,000.00 | 2,497,482.66 | EaJr De Leon Construction/ Edwardo De Leon Jr | 20% PDF CY 2015 | 2016-01-26 | 2016-07-22 | Completed | Usable; 100% completed with Liquidated Damages equivalent to Php 59,766.56 |
Tuba | Tadiangan | Improvement along Yagyagan - Ampusa Provincial Road | Roads | 1,000,000.00 | 988,748.23 | Guava Construction / Evelyn F. Balag-ey | 20% PDF CY 2015 | 2016-02-03 | 2016-09-07 | Completed | Usable; 98.846% completed with underrun equivalent to Php 11,409.5 and also with Liquidated Damages equivalent to Php 6,149.03 |
Tublay | Caponga | Construction of PCCP along Tublay Gate - Tublay Presidensia Provincial Road | Roads | 2,000,000.00 | 1,994,077.22 | balangcod construction/fermin balangcod | 20% PDF CY 2015 | 2016-03-07 | 2016-07-26 | Completed | Usable; 97.97% completed due to underrun of Php 40,448.83
payment of partial accomplishment on the const. pccp along tublay gate-tublay presidencia prov'l road |
La Trinidad | Poblacion | Improvement along La Trinidad - Capitol - Bineng Provincial Road | Roads | 3,000,000.00 | 2,988,782.65 | Anas Construction/ Dionisio L. Anas | 20% PDF 2015 | 2016-01-26 | 2016-07-22 | Completed | payment is for partial accomplishment of contract on the imp. along La Trinidad-capitol-Bineng Provincial Road, LA Trinidad, Benguet |
Buguias | Baculongan Sur | Completion of Box Culvert at Wakallan Creek along Balintag-Dekkan-Nakga-an Road | | 250,000.00 | | jyp general construction/yonie palonan | 20% PDF CY 2015 | 2016-06-30 | 2016-07-30 | Completed | |
Buguias | Catlubong | Construction of Padang Footpath (Phase 1) | | 100,000.00 | | On Top Construction/ Thomas R. Palileng Sr. | 20% PDF CY 2015 | 2016-07-01 | 2016-07-13 | Completed | |
Kabayan | Lusod | Improvement of Riprap along Portions of Baay-Madayag FMR | Road Side | 300,000.00 | | Akiki Builders | 20% PDF CY 2015 | 2016-06-29 | 2016-07-16 | Completed | with liquidated damages |
Tuba | Taloy Sur | Construction of PCCP along Taloy - Bayacsan Provincial Road | Roads | 2,000,000.00 | 1,998,409.97 | hdg construction and enterprises/hanivall guilando | 20% PDF CY 2015 | 2016-01-26 | 2017-03-21 | Completed | Usable; 100% completed |
La Trinidad | Shilan | Improvement / Construction of PCCP along Shilan - Sagpawe Provincial Road | Roads | 1,000,000.00 | 997,978.76 | drichloui construction/ roy balay-odao | 20% PDF CY 2015 | 2016-03-07 | 2016-07-08 | Completed | Usable; 100% completed with Liquidated Damages equivalent to Php 9,410.87 |
La Trinidad | Pico | Improvement / Construction of PCCP along Pico-Stockfarm Provincial Road | Roads | 7,000,000.00 | 6,994,613.96 | sej construction and aggregates/ mr. eric de leon | 20% PDF 2015 | 2016-04-15 | 0000-00-00 | Completed | Suspended since August 12, 2016 with an accomplishment of 55.178594% |
Bokod | Bila | Riprapping of Balangabang-Digew FMR - Entrance | Road Side | 1,500,000.00 | 1,498,150.33 | Jamil Sean Construction/Barmino T. Bugnay | 20% PDF CY 2015 | 2016-06-24 | 2016-10-01 | Completed | Completed - September 13, 2016 |
Itogon | Tinongdan | Construction of Comfort Room at IMH | Building | 500,000.00 | 498,500.00 | Jessie Construction Services | 20% PDF CY 2015 | 2016-07-29 | 2016-10-01 | Completed | |
La Trinidad | Wangal | Improvement of BTS Building and Entrance Gate | Building | 1,000,000.00 | 998,487.36 | Guava Construction / Evelyn F. Balag-ey | 20% PDF CY 2015 | 2016-01-25 | 2016-08-27 | Completed | Completed - August 27, 2016 |
Atok | Paoay | Opening of Salat - Talongtongao - Boneng FMR | Roads | 700,000.00 | 699,027.74 | DJY Construction | 20% PDF CY 2015 SB No. 6 | 2016-07-04 | 2016-08-23 | Completed | Completed on August 15, 2016 |
Buguias | Sebang | Construction of Riprap (Protective Wall) at Kamanbagang FMR | Road Side | 800,000.00 | 798,186.17 | Random Builders | 20% PDF CY 2015 | 2016-06-27 | 2016-08-08 | Completed | |
Sablan | Bayabas | Construction of Greenhouse at Agri-Eco Farm, Bulala | Building | 300,000.00 | 299,106.38 | anas construction/ dionisio anas | 20% PDF CY 2015 | 2016-07-07 | 2016-08-14 | Completed | |
Bakun | Ampusongan | Improvement and Extension of Namagtey - Mabilig Alternate Road | Roads | 500,000.00 | 498,824.40 | safelink builders/ ponciano andiso | 20% PDF CY 2016 | 2016-09-14 | 2016-10-13 | Completed | Completed - November 14, 2016, with liquidated damages |
Tuba | San Pascual | Opening and Slope Protection of Farm Access Road, San Pascual | Road Side | 1,000,000.00 | 998,573.43 | aguinsod general construction/christopher aglolo | 20% PDF CY 2015 | 2016-04-18 | 2016-11-16 | Completed | Completed - November 16, 2016 |
Mankayan | Balili | Construction of Hilltop Footpath at Mankingao, Cada | | 200,000.00 | | On Top Construction/ Thomas Palileng | 20% PDF CY 2015 | 2016-06-27 | 2016-07-19 | Completed | Completed - July 18, 2016 |
Tuba | San Pascual | Construction of Forage Nursery and Potting Area, Tuba, Benguet | Building | 300,000.00 | 297,712.14 | Aguinsod Construction | 20% PDF CY 2017 | 2018-03-12 | 2018-04-24 | Completed | Completed on April 23, 2018 |
Itogon | Ucab | Construction of Pathway at Sitio Midas | Roads | 200,000.00 | 198,412.30 | MK Construction | 20% PDF CY 2015 | 2018-01-24 | 2018-02-14 | Completed | Completed on February 13, 2018 |
La Trinidad | Puguis | Construction of 8x8x10 Water Tank at Paswek, Puguis, La Trinidad, Benguet | Water tank | 200,000.00 | 184,993.94 | Four Brothers Construction | 20% PDF 2015 | 2019-02-15 | 2019-12-03 | Completed | |
La Trinidad | Wangal | Construction of Tirepath from Windy Hills Turning Point-Upper Gayasi, Wangal La Trinidad | Roads | 250,000.00 | 248,922.86 | Sangin Construction | 20% PDF CY 2015 | 2018-02-07 | 2018-04-08 | Completed | 100% Completed April 7, 2018 - Total Cost Incurred PhP 248,922.86 as of April 30, 2018 |
Itogon | Loacan | Concreting of Mangga - Luneta Alternate Road | PCCP | 1,050,000.00 | 1,041,056.44 | WDG Construction | 20% PDF 2015 | 0000-00-00 | 0000-00-00 | Terminated | |
Itogon | Tinongdan | Improvement of Delivery Room,Laboratory Room,Operating Room Complex | Building improvement | 1,000,000.00 | 946,757.48 | Boyet Builders | 20% PDF-2015 | 2019-06-27 | 2018-08-30 | Completed | completed and geotag on October 2, 2019
|
Atok | Abiang | Completion of Pathway Shed at Adoyunan Elementary School | Building | 150,000.00 | 149,816.40 | JCA General Construction and Engineering Services | 20% PDF CY 2016 | 2017-07-04 | 2017-08-03 | Completed | Satisfactorily Completed, Revised target date of completion on August 14, 2017.
Part of Clustered A projects, - a) completion of pathway shed, adoyunan elem school @ abiang, atok; b) concreting of boneng elem school grounds, boneng, naguey @ atok |
Atok | Naguey | Concreting of Boneng Elementary School Grounds | Building | 200,000.00 | 199,783.04 | JCA General Construction and Engineering Services | 20% PDF CY 2016 | 2017-07-04 | 2017-08-09 | Completed | Part of Clustered A projects, - b) completion of pathway shed, adoyunan elem school @ abiang, atok; c) concreting of boneng elem school grounds, boneng, naguey at atok d) tirepathing of tagontongaw FMR
Clustered A projects, - a) completion of pathway shed, adoyunan elem school @ abiang, atok; b) concreting of boneng elem school grounds, boneng, naguey @ atok |
Bakun | Gambang | Improvement of Nagawa-Ubbon FMR | Roads | 1,000,000.00 | 998,384.53 | Drichloui Construction | 20% PDF CY 2016 | 2017-07-11 | 2017-09-08 | Completed | Project Completed as per Plan |
Bakun | Gambang | Improvement of Alam-am to Kilong FMR | Roads | 1,000,000.00 | 998,476.59 | Drichloui Construction | 20% PDF CY 2016 | 2016-12-04 | 2017-05-31 | Completed | Completed as per plan. |
Bakun | Sinacbat | Opening of Pidpid - Lamew FMR | Roads | 2,000,000.00 | 1,406,158.16 | FMC Warriors Construction | 20% PDF CY 2016 | 2016-08-22 | 2017-03-24 | Completed | 70.44% Completed with underrun. |
Bakun | Bagu | Improvement of Ca-ang Waterworks System | Waterworks System | 500,000.00 | 497,658.13 | Toclo Construction | 20% PDF CY 2016 | 2017-02-08 | 2017-03-26 | Completed | Completed as per plan. |
Bakun | Gambang | Completion of Sookan Multi-Purpose Building | Building | 500,000.00 | 498,425.29 | drichloui construction/ roy balay-odao | 20% PDF CY 2016 | 2016-11-21 | 2017-03-02 | Completed | Completed as per plan |
Bakun | Ampusongan | Completion of Multi-purpose Gym | Building | 2,000,000.00 | 1,997,747.29 | Reasons Construction | 20% PDF CY 2016 | 2016-12-04 | 2017-03-10 | Completed | |
Bakun | Gambang | Improvement of School Nursery Building, Bagtangan Elementary School | Building Repair | 650,000.00 | 647,268.98 | Reasons Construction | 20% PDF CY 2016 | 2017-01-20 | 2017-02-01 | Completed | Cluster "B" - b) 02-16-00010 c) 02-15-00002 Reasons Construction
clustered B projects, a)imp of school nursery bldg, bagtangan E/S @ Gambang, bakun; b)concreting of maudang-baoy pathway, pob, bakun; c) const of concrete tirepath along gayabasan to |
Bakun | Poblacion | Concreting of Maudang-Baoy Pathway | Roads | 650,000.00 | 647,268.98 | Reasons Construction | 20% PDF CY 2016 | 2017-01-20 | 2017-02-10 | Completed | Cluster "B" a) Control No. 02-16-00009 c) Control No. 02-15-00002 - Reasons Construction |
Bakun | Ampusongan | Improvement of Drainage Canal | Road Side | 150,000.00 | 149,036.24 | Pulicay Grandsons Construction | 20% PDF CY 2016 | 2017-10-20 | 2017-11-12 | Completed | Completed as per plan
Clustered, construction of catwalk shed from bakun nhs to bakun cs; b) improvement of drainage canal, ampusongan, bakun, benguet |
Mankayan | Suyoc | Concreting of Tambalaken FMR, Suyoc, Mankayan | Roads | 450,000.00 | 449,014.45 | Eugao Construction | 20% PDF CY 2016 | 2017-12-01 | 2017-01-03 | Completed | Need additional fund |
Bakun | Gambang | Improvement of Alibacong Child Development Center | Building Repair | 150,000.00 | 149,431.46 | srba general construction/ ray angluben | 20% PDF CY 2016 | 2017-11-24 | 2017-12-26 | Completed | Completed as per plan.
contract under cluster c: a) imp of kayapa fmr @ kayapa, bakun; b) imp of alibacong child development center @ gambang, bakun
Total payment = 542,854.14 |
Mankayan | Balili | Construction of Sayapot Day Care Center, Balili | Building | 1,000,000.00 | 978,670.33 | Toclo Construction/Elmer S.Toclo | 20% PDF CY 2016 | 2017-03-15 | 2017-03-15 | Completed | Completed as programmed and usable, need additional fund |
Mankayan | Cabiten | Improvement of Las-igan Primary School ground | School Grounds | 100,000.00 (Clustered) | 99,239.79 | baldas construction/samson b. benny | 20% PDF CY 2016 | 2017-12-01 | 2017-01-05 | Completed | Completed as programmed and usable, need additional fund
contract under cluster "E" a) Improvement of Las-igan Primary School Ground, cabiten, Mankayan b)construction of concrete pathway, Camanpaguey, Mankayan, Benguet |
Mankayan | Guinaoang | Construction of FMR Pathway, Sakatal, Guinaoang, Mankayan | Roads | 350,000.00 | 348,476.08 | Baldas Construction | 20% PDF CY 2016 | 2017-01-23 | 2017-02-15 | Completed | Cluster "G" a) Control No. 03-15-00027 b) 03-15-00028 - Baldas Construction
a)construction of waiting shed @ poked, las-igan cabiten,mankayan b)tirepathing @lower doweg, guinaoang,mankayan c) const. of FMR pathway @sakatal, guinaoang, mankayan |
Mankayan | Bedbed | Improvement of Barangay Road, Bedbed | Roads | 500,000.00 | 498,457.72 | sandstone mt. general construction & aggregates/ca | 20% PDF CY 2016 | 2017-01-25 | 2017-02-26 | Completed | Completed as programmed and usable, need additional fund
|
Mankayan | Guinaoang | Concreting of Guinaoang Elementary School Access Road, Guinaoang | Roads | 400,000.00 (Clustered) | 398,690.76 | malco construction/ malote copite | 20% PDF CY 2016 | 2017-01-25 | 2017-02-23 | Completed | Completed as programmed and usable, need additional fund
clustered H project a)imp of brgy road bedbed, mankayan; b)concreting of guinaoang elem school access road |
Mankayan | Colalo | Reconstruction of Multi-Purpose Building, Busan, Colalo | Building | 800,000.00 | 797,320.83 | Malco Construction | 20% PDF CY 2016 | 2017-01-25 | 2017-04-09 | Completed | Completed as programmed and usable, need additional fund |
Mankayan | Cabiten | Extension of Lucapan-Lanas to Cabali FMR | Roads | 400,000.00 | 397,796.49 | On Top Construction | 20% PDF CY 2016 | 2017-01-26 | 2017-02-24 | Completed | Completed as programmed and usable, need additional fund |
Mankayan | Suyoc | Completion of Barangay multipurpose building / hall, Suyoc | Building | 1,000,000.00 | 972,515.98 | eugao construction/eugenio aglasi | 20% PDF CY 2016 | 2017-02-06 | 2017-04-25 | Completed | Completed as programmed and usable, need additional fund |
Mankayan | Paco | Construction of Farm to Market Road, Paco, Mankayan, Benguet | Roads | 1,000,000.00 | 844,511.94 | jyp general construction/yonie palonan | 20% PDF CY 2016 | 2017-02-08 | 2017-03-10 | Completed | Satisfactorily Completed, need additional fund |
Mankayan | Paco | Opening/ Concreting of Lamdagan Farm to Market Road | Roads | 700,000.00 | 689,498.55 | JYP Construction | 20% PDF CY 2016 | 2018-03-01 | 2018-04-04 | Completed | Satisfactorily Completed, need additional fund |
Bakun | Dalipey | Construction of Tanod Outpost | Building | 200,000.00 | 199,574.93 | NAIR Construction & Engineering | 20% PDF CY 2016 | 2017-12-13 | 2018-01-19 | Completed | 1) Cluster "D" - NAIR Construction & Engineering
2) Completed on February 13, 2018 with liquidated damages.
cluster d: a) const of tanod outpost, dalipey, bakun; b) imp of alam-am-nasayotean fmr, gambang, bakun |
Mankayan | Cabiten | Riprapping-Biwak, Guiweng, Cabiten Mankayan | Road Side | 900,000.00 | 888,594.74 | Eugao Construction | 20% PDF CY 2016 | 2017-06-12 | 2017-07-13 | Completed | Satisfactorily Completed and usable
clustered R project - a)riprapping of biwak gueweng, cabiten; b) const of old concrete perimeter fence balili E/S; c) brgy suyoc FMR Side riprapping @ Mankayan, Benguet
Total amount paid - 888,594.74 |
Mankayan | Balili | Construction of Old Concrete Perimeter Fence Balili Elementary School, Balili, Mankayan | Building | 900,000.00 | 888,594.74 | Eugao Construction | 20% PDF CY 2016 | 2017-06-12 | 2017-07-17 | Completed | Completed as programmed and usable, need additional fund
clustered R project - a)riprapping of biwak gueweng, cabiten; b) const of old concrete perimeter fence balili E/S; c) brgy suyoc FMR Side riprapping @ Mankayan, Benguet |
Mankayan | Suyoc | Barangay Suyoc Farm to Market Road Side Riprapping | Road Side | 900,000.00 | 888,594.74 | Eugao Construction | 20% PDF CY 2016 | 2017-06-12 | 2017-07-25 | Completed | Completed as programmed and usable
clustered R project - a)riprapping of biwak gueweng, cabiten; b) const of old concrete perimeter fence balili E/S; c) brgy suyoc FMR Side riprapping @ Mankayan, Benguet |
Mankayan | Cabiten | Construction of Cabiten Elementary School Stage | Building | 800,000.00 | 797,274.51 | Malco Construction | 20% PDF CY 2016 | 2017-07-29 | 2017-09-11 | Completed | Completed as programmed and usable, need additional fund |
Mankayan | Tabio | Construction of Antangila Vehicular bridge | Bridge | 1,115,000.00 | 972,717.61 | Eugao Construction | 20% PDF CY 2016 | 2017-04-25 | 2017-08-09 | Completed | Completed as programmed and usable |
Atok | Topdac | Improvement of Km. 34-Jappa FMR, Topdac, Atok, Benguet | Roads | 800,000.00 | 798,205.12 | Hillstone Builders | 20% PDF CY 2016 | 2016-09-19 | 2016-11-17 | Completed | |
Bokod | Daclan | Completion of Nutrition and Dietary Facility (Phase II) DMMH, Daclan, Bokod, Benguet | Building Repair | 1,000,000.00 | 986,924.79 | Almond Engineering and Construction | 20% PDF CY 2016 | 2016-12-01 | 2017-06-28 | Completed | with Liquidated Damages |
Bokod | Poblacion | Construction of Bogyo-Bolo Footbridge, Poblacion, Bokod, Benguet | Bridge | 600,000.00 | 598,457.18 | Hillbrand Engineering | 20% PDF CY 2016 | 2017-11-26 | 2017-01-20 | Completed | Completed and usable |
La Trinidad | Beckel | Construction of Footpath, Obulan-Gongel, Beckel, La Trinidad, Benguet | Roadside | | 423,944.47 | | 20% PDF CY 2016 | 2018-05-09 | 2018-06-05 | Completed | 100.00% Completed(May 29,2018) with 423,944.47 Total cost incurred |
Bokod | Ambuklao | Concreting of Footpath at Alo-o - Eli, Bangao, Ambuklao, Bokod, Benguet | Footpath | 300,000.00 | 289,999.72 | BLDY Eng'g & Construction | SB No. 2 - 2016 | 2018-05-08 | 2018-06-17 | Completed | Completed as of July 31, 2018
The revised target date of completion: 07/02/2018 |
Bakun | Dalipey | Construction of Waterworks System, Dalipey, Bakun | Waterworks | 150,000.00 | 149,712.80 | SRBA General Construction | 20% PDF - 2016 | 2018-10-16 | 2018-11-12 | Completed | |
Bokod | Bila | Improvement of FMR along Gwiling-Yabo in Palansa | Roads | 100,000.00 | 96,510.62 | SRBA General Construction | SB #2 CY 2016 | 2018-11-07 | 2018-11-18 | Completed | |
Bokod | Bobok-Bisal | Daycare Center Stage and Ground Improvement, Kawal, Bobok-Bisal, Bokod | Building | 500,000.00 | 497,793.82 | Sangin General Construction | 20% PDF CY 2016 | 2017-01-31 | 2017-05-15 | Completed | with Liquidated Damages |
Bokod | Karao | Construction of Natural Swimming Pool at Karao, Bokod, Benguet | Pool | 1,000,000.00 | 982,938.15 | sangin general construction / sandy rafael | 20% PDF CY 2017 | 2017-02-06 | 2017-07-21 | Completed | The barangay officials must assign personnel to be responsible for cleaning and maintenance of the swimming pool |
Bokod | Pito | Construction of Barangay Health Center, Pito, Bokod, Benguet | Building | 1,500,000.00 | 1,498,355.70 | Solonio Construction | 20% PDF CY 2016 | 2017-01-23 | 2017-10-27 | Completed | Completed and usable |
Bokod | Karao | Construction of Busok Flood Control, Karao, Bokod | Road Side | 500,000.00 | 496,088.02 | hillbrand engineering/ hildobrando beray | 20% PDF CY 2016 | 2017-02-06 | 2017-03-18 | Completed | 100% Completed and usable |
Bokod | Karao | Construction of Coral Flood Control, Karao, Bokod | Road Side | 500,000.00 | 498,040.91 | hillbrand engineering/ hildobrando beray | 20% PDF CY 2016 | 2017-02-06 | 2017-03-18 | Completed | Completed and usable |
Sablan | Banangan | Construction of Socung Footpath | Construction of Footpath | 150,000.00 | 149,481.87 | Anas Consruction | 20%PDF-2016 | 2018-10-05 | 2018-11-12 | Completed | |
Buguias | Sebang | Improvement of Paneg-an - Takadang - Tamangan FMR | Roads | 400,000.00 | 396,839.22 | JYP General Construction | 20% PDF CY 2016 | 2016-12-02 | 2017-01-20 | Completed | Completed - January 20, 2017
project under cluster "C": a) improvement of Paneg-an-Takadang-Tamangan FMR in Sebang b) Improvement of Panig-an-Tamangan FMR in Sebang, Bugias |
Buguias | Baculongan Sur | Completion of Maselselne Footbridge | Bridge | 350,000.00 | 336,682.48 | on top construction/ thomas palileng | 20% PDF CY 2016 | 2016-11-28 | 2017-01-26 | Completed | Project Completed with underrun.
project contract under cluster "B" a) completion of Maselselne Footbridge at Buculungan, Bugias b)construction of Sebseb Flood Control at Buculungan Norte, Bugias, Benguet |
Buguias | Baculongan Norte | Construction of Sebseb Flood Control | Road Side | 500,000.00 | 499,030.33 | on top construction/ thomas palileng | 20% PDF CY 2016 | 2016-11-28 | 2017-01-26 | Completed | Completed - January 20, 2017, Project completed with LD.
project contract under cluster "B" a) completion of Maselselne Footbridge at Buculungan, Bugias b)construction of Sebseb Flood Control at Buculungan Norte, Bugias, Benguet |
Buguias | Sebang | Improvement of Pasbol - Motyokna - Mankaet FMR | Roads | 1,000,000.00 | 994,344.87 | JYP General Construction | 20% PDF CY 2016 | 2016-02-12 | 2017-01-30 | Completed | Completed - January 30, 2017
contract under cluster "B" projects with same funding source but different project titles. a)improvement and extension of makaet-motyokna fmr, sebang buguias benguet. b)improvement of p |
Buguias | Baculongan Sur | Improvement Along Bad-ayan - Obanga (Paing Crossing) | Roads | 1,000,000.00 | 994,153.89 | JYP General Construction | 20% PDF CY 2016 | 2016-12-02 | 2017-02-03 | Completed | Completed - February 3, 2017 |
Buguias | Baculongan Norte | Improvement of Sumill - Palaan FMR | Roads | 150,000.00 | 147,183.18 | Mel-Soc Construction | 20% PDF CY 2016 | 2016-12-02 | 2017-01-10 | Completed | Completed - January 10, 2017
clustered a project - a)imp of sumili-palaan FMR; b) const of calamagan-baglaw pathway; c)const of padang-palakad footpath @ buguias, benguet |
Buguias | Calamagan | Construction of Calamagan - Baglaw Pathway | Roads | 100,000.00 | 99,560.74 | mel-soc construction/engr. marveluz patian | 20% PDF CY 2016 | 2016-12-02 | 2017-01-05 | Completed | Completed - January 5, 2017
clustered a project - a)imp of sumili-palaan FMR; b) const of calamagan-baglaw pathway; c)const of padang-palakad footpath @ buguias, benguet |
Buguias | Catlubong | Construction of Padang - Palakad Footpath | Roads | 500,000.00 | 446,075.03 | mel-soc construction/engr. marveluz patian | 20% PDF CY 2016 | 2016-12-02 | 2017-01-20 | Completed | Completed - January 20, 2017, deducted PHP 500.00 due to the substandard billboard.
clustered a project - a)imp of sumili-palaan FMR; b) const of calamagan-baglaw pathway; c)const of padang-palakad footpath @ buguias, benguet |
Buguias | Catlubong | Improvement of Bot-oan Elementary School Grounds | Building | 1,000,000.00 | 998,800.01 | Donato Sakiwat Construction | 20% PDF CY 2016 | 2016-12-02 | 2017-03-05 | Completed | Completed February 14, 2016, revised target completion date to March 5, 2017 |
Buguias | Amgaleyguey | Improvement of Katodtoda FMR in Amgaleyguey | Roads | 500,000.00 | 497,491.35 | JYP General Construction | 20% PDF CY 2016 | 2016-12-26 | 2017-01-23 | Completed | Completed - January 23, 2017 |
Kapangan | Gadang | Construction of Spelin Hanging Bridge,Suyoc,Gadang,Kapangan,Benguet | Hanging footbridge construction | 500,000.00 | 488,954.14 | Family Circle Construction | 20% PDF-2016 | 2019-06-11 | 2019-07-21 | Completed | |
Bokod | Tikey | Construction of Tickey Proper-Aran Footrail | Roads | 400,000.00 | 398,823.43 | hillbrand engineering/ hildobrando beray | 20% PDF CY 2016 | 2017-02-06 | 2017-02-25 | Completed | Cluster "C" a) Control No. 2-16-00268 b) Control No. 02-16-00269 d) Hillbrand Engineering
clustered C projects-a. imp of boning alternate road, pob; b)const of pangawan-eli footpath, bangao; c)const of tickey proper-aran footrail; d)const of lower dabidab footrail, tickey, bokod |
Bokod | Tickey | Construction of Lower Badidab Footpath, Tickey, Benguet | Roads | 100,000.00 | 99,701.89 | hillbrand engineering/ hildobrando beray | 20% PDF CY 2016 | 2017-02-06 | 2017-03-03 | Completed | Completed - January 23, 2017
clustered C projects-a) imp of boning alternate road, pob; b)const of pangawan-eli footpath, bangao; c)const of tickey proper-aran footrail; d)const of lower dabidab footrail, ticke |
Bokod | Tickey | CLUSTER: Construction of Flood Control in Betongay, Tickey, Bokod | Road Side | 537,000.00 | 536,101.40 | Vanket Engineering and Construction | 20% PDF CY 2016 | 2017-05-28 | 2017-07-29 | Completed | Clustered b) Control No.: 02-16-00044 - Vanket Engineering and Construction
Completed - January 23, 2017
cluster e: a) const of flood control in betongay tickey, bokod; b) re-opening of kamura foot trail nawal, bokod |
Bokod | Nawal | Re-Opening of Kamura Foot Trail, Nawal, Bokod, Benguet | Roads | 537,000.00 | 536,101.40 | Vanket Engineering and Construction | 20% PDF CY 2016 | 2017-05-28 | 2017-07-10 | Completed | Clustered a) Control No.: 02-16-00043 - Vanket Engineering and Construction
clustered E projects - a) const of flood control in Botengay Tickey Bokod; b) re-opening of kamura foot trail nawal, bokod |
Bokod | Daclan | Construction of Material Recovery Facility (MRF) | Building | 300,000.00 | 299,021.91 | | 20% PDF CY 2016 | 2017-09-29 | 2017-12-08 | Completed | |
Bokod | Daclan | Improvement of Supply Room, DMMH | Building Repair | 350,000.00 clustered | 349,039.62 | summerlin construction and development corp/anton | 20% PDF CY 2016 | 2017-09-29 | 2017-11-18 | Completed | cluster d: a) const of mrf dmdh; b) imp of supply room, dmdh; c) const of shaded parking for hospital vehicles, dmdh (daclan, bokod) |
Bokod | Bobok-Bisal | Improvement of Yapos Farm to Market Road-Bobok | Roads | 500,000.00 | 498,716.65 | Lincee General Construction | 20% PDF CY 2016 | 2017-01-26 | 2017-03-01 | Completed | |
Bokod | Bobok-Bisal | Widening of Ngano-an to Polis Foot Trail, Bobok-Bisal, Bokod | Roads | 70,000.00 | 69,577.00 | AG Chungalan Construction | SB No. 2 CY 2016 | 2017-07-24 | 2017-08-24 | Completed | |
Bokod | Ambuklao | Construction of Waiting Shed, Bayembeng, Bangao | Building | 220,000.00 | 219,517.57 | AG Chungalan Construction | 20% PDF CY 2016 | 2017-12-28 | 2018-01-31 | Completed | Completed on January 31, 2018 |
Bokod | Ekip | Concreting of FMR at Ekip, Bokod, Benguet | Roads | 150,000.00 | 149,530.60 | AG Chungalan Construction | 20% PDF CY 2016 | 2017-08-10 | 2017-08-22 | Completed | |
Buguias | Baculongan Norte | Construction of Multi-purpose Building (Additional), Baculongan Norte | Building | 700,000.00 | 697,712.91 | On Top Construction | 20% PDF CY 2016 | 2017-02-24 | 2017-04-26 | Completed | Completed on April 26, 2017 |
Buguias | Abatan | Completion of Buguias Federation Senior Citizen's Association Multi-Purpose Building, Completion of Buguias Federation Senior Citizen's Association MPB Phase II | Building | 2,000,000.00 | 1,994,943.46 | JYP General Construction | 20% PDF CY 2016 | 2016-12-02 | 2017-05-06 | Completed | Satisfactorily Completed with LD. Revised target completion date to May 6, 2017
A)completion of buguias federation senior citizen ass'n. multi-purpose bldg. B)completion og Buguias federation ass'n multi-purpose bldg. phase II @ abatan buguias |
Buguias | Bangao | CLUSTER: Improvement of Halsema - Gulodan FMR at Bangao | Roads | 650,000.00 | 647,365.50 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-07-01 | Completed | Clustered b) Control No.: 02-16-00057 - On Top Construction
Completed on July 1, 2017 |
Buguias | Loo | Construction of Loo Elementary School Athletic Oval Retaining Wall | Road Side | 850,000.00 | 691,668.64 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-07-01 | Completed | CLUSTERED b) Control No. 02-16-00063 c) 02-16-00056- On Top Construction
Clustered "H" Projects - a) const of Loo E/S athletic Oval Retaining Wall @ Loo, Buguias; b)impv't of Obanga Day Care Center Grounds @ Baculungan Sur, Buguias |
Buguias | Baculongan Sur | Improvement of Obanga Day Care Center Grounds | School Grounds | 850,000.00 | 691,668.64 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-19 | Completed | CLUSTERED- a) Control No.: 02-16-00055 b) 02-16-00063 - On Top Construction
Completed on June 19, 2017 |
Buguias | Poblacion | Improvement of Asinan Creek and Hot Spring | Swimming Pool | 650,000.00 | 647,365.50 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-25 | Completed | Clustered a) Control No.: 02-16-00054- On Top Construction Completed on June 25, 2017 |
Buguias | Baculongan Norte | Improvement of Lam-ayan FMR | Roads | 600,000.00 | 597,602.63 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-16 | Completed | Clustered b) Control No.: 02-16-00059 - On Top Construction
Completed on June 16, 2017 |
Buguias | Baculongan Norte | Construction of Sebseb - Takadang Creek Flood Control | Road Side | 600,000.00 | 597,602.63 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-23 | Completed | Clustered a) Control No.: 02-16-00058 - On Top Construction
Completed on June 23, 2017 |
Buguias | Amlimay | Construction of Tonglo Domestic Water Supply | Waterworks System | 200,000.00 | 199,549.02 | On Top Construction | 20% PDF CY 2016 | 2017-10-10 | 2017-11-20 | Completed | Revised target completion date to November 24, 2017 |
Buguias | Amlimay | Extension/Improvement of Damang - Besbes FMR | Roads | 500,000.00 | 498,630.47 | On Top Construction | 20% PDF CY 2016 | 2017-10-10 | 2018-04-06 | Completed | Completed and post inspected on April 4, 2018 |
Buguias | Amgaleyguey | Construction of Riprap along Nansabatan - Baso FMR | Road Side | 400,000.00 | 392,397.32 | Bosongan Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-07-12 | Completed | |
Buguias | Loo | Construction of Baybay Footbridge | Bridge | 850,000.00 | 691,668.64 | On Top Construction | 20% PDF CY 2016 | 2017-11-29 | 2017-12-20 | Completed | CLUSTERED- a) Control No.: 02-16-00055 C) 02-16-00056 - On Top Construction |
Buguias | Catlubong | Improvement / Extension of Abatan - Gatiley Luboy FMR | Roads | 1,000,000.00 | 998,545.97 | ICO Construction | 20% PDF CY 2016 | 2019-10-28 | 2020-01-04 | Completed | Temporarily suspended November 6, 2017 pending issuance of CNC from DENR. |
Buguias | Poblacion | Opening of Lower Naybo - Benged FMR, Cayabyab | Roads | 1,000,000.00 | 994,871.00 | Hillstone Builders | 20% PDF CY 2016 | 2018-02-08 | 2018-04-23 | Completed | 75% Completed - Total Cost Incurred PhP 746,153.25 as of April 30, 2018 |
Buguias | Amlimay | Improvement of Guioeng - Kimpit FMR | Roads | 500,000.00 | 498,493.72 | On Top Construction | 20% PDF CY 2016 | 2017-10-20 | 2017-12-16 | Completed | Completed on December 16, 2017 |
Itogon | Dalupirip | Improvement of Waterworks System at Calew | Waterworks System | 650,000.00 | 648,000.00 | Jessie Construction Services | 20% PDF CY 2016 | 2016-11-09 | 2017-03-01 | Completed | Cluster "C" - Control No.: 02-16-00068 Jessie Construction Services |
Itogon | Dalupirip | Improvement of Sayo Waterworks System | Waterworks System | 650,000.00 | 648,000.00 | Jessie Construction Services | 20% PDF CY 2016 | 2006-11-09 | 2107-03-01 | Completed | Cluster "C" - Control No.: 02-16-00067 Jessie Construction Services
a)imp. of waterworks system @ calew b)imp. of sayo waterworks system @ dalupirip |
Itogon | Ampucao | Improvement of foot trail from Dam3 going to Viewdeck of San Roque Dam in Ampucao | Roads | 500,000.0 | 493,720.22 | Babecor Builders | 20% PDF CY 2016 | 2016-11-25 | 2017-02-10 | Completed | |
Itogon | Ampucao | Improvement of riprap at PLDT-Cruz road | Roads | 1,000,000.00 | 934,718.25 | Aljune Builders | 20% PDF CY 2016 | 2017-01-17 | 2017-03-12 | Completed | |
Itogon | Dalupirip | Improvement of Karil FMR | Roads | 800,000.00 | 798,000.00 | Jessie Construction Services | 20% PDF CY 2016 | 2017-02-22 | 2017-03-26 | Completed | |
Itogon | Gumatdang | Construction of Orengao-Muyot Footbridge | Bridge | 500,000.00 | 498,700.82 | Compass Rose Builders | 20% PDF CY 2016 | 2017-09-05 | 2017-11-30 | Completed | |
Kabayan | Ballay | Improvement along Bagto - Bacanganga FMR | Roads | 1,000,000.00 | 998,833.65 | Jamil Sean Construction | 20% PDF CY 2016 | 2016-12-09 | 2017-02-19 | Completed | |
Kabayan | Gusaran | Construction of Shed, Barangay Ground | Building | 1,500,000.00 | 1,498,460.05 | Solonio Construction | 20% PDF CY 2016 | 2016-12-23 | 2017-03-25 | Completed | |
Kabayan | Gusaran | Construction of Culture and Arts Building at Kamora National High School (Phase 2) | Building | 1,000,000.00 | 998,456.85 | Solonio Construction | 20% PDF CY 2016 | 1016-12-23 | 2017-04-19 | Completed | |
Kabayan | Ballay | Improvement of Tongotong FMR | Roads | 1,500,000.00 | 1,498,452.59 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-02-07 | 2017-04-06 | Completed | |
Kabayan | Ballay | Improvement of Dinamili - Bolagabog Takitak FMR | Roads | 1,070,000.00 | 1,068,618.02 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-01-24 | 2017-02-15 | Completed | |
Kabayan | Bashoy | a) Construction (Extension/Continutation) of FMR along Palansa - Pinanshay b)Widening and Construction of FMR access along Palansa - Pinanshay | Roads | 450,000.00 | 448,282.14 | Solonio Construction | 20% PDF CY 2016 | 2017-04-11 | 2017-05-13 | Completed | |
Kabayan | Ballay | Improvement along Besocol FMR | Roads | 500,000.00 | 498,434.20 | Akiki Builders | 20% PDF CY 2016 | 2017-02-02 | 2017-03-06 | Completed | |
Kabayan | Ballay | Tirepathing of Upper Dumipayas | Roads | 100,000.00 | 99,629.81 | Akiki Builders | 20% PDF CY 2016 | 2017-02-02 | 2017-02-16 | Completed | project contract cluster "D" a)tirepathing of upper dumipayas ballay, kabayan b)const. of tirepath along kubo-tinaleb fmr ballay,kabayan both located @ ballay, kabayan, benguet |
Kabayan | Ballay | Construction of Tirepath along Kubo - Tinaleb FMR | Roads | 100,000.00 | 99,779.04 | Akiki Builders | 20% PDF CY 2016 | 2017-02-07 | 2017-02-19 | Completed | contract cluster "D" a)tirepathing of upper dumipayas ballay, kabayan b)const. of tirepath along kubo-tinaleb fmr ballay,kabayan both located @ ballay, kabayan, benguet |
Kabayan | Lusod | Improvement of Baay - Ballay - Lusod FMR (Proper Lusod Section) | Roads | 980,000.00 | 977,333.68 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-21 | Completed | CLUSTERED Control No.: b) 02-16-00085 - Jamil Sean |
Kabayan | Ballay | Improvement along Lower Taaw FMR | Roads | 980,000.00 | 977,333.68 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-20 | Completed | CLUSTERED Control No.: a) 02-16-00084 - Jamil Sean Construction |
Kabayan | Lusod | Road Opening at Lusod - Dagdag FMR | Roads | 2,300,000.00 | 2,294,097.38 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-12-05 | 2018-03-07 | Completed | Completed on March 6, 2018 |
Kabayan | Gusaran | Construction of Sub-Clinic | Building | 800,000.00 | 780,677.67 | Solonio Construction | 20% PDF CY 2016 | 2017-05-31 | 2017-09-06 | Completed | Completed and usable with underrun and liquidated damages. |
Kabayan | Bashoy | Construction of Tirepath along Nandupit Junction along Dumamay FMR | Roads | 250,000.00 | 249,138.69 | Solonio Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-26 | Completed | Completed and usable with underrun and liquidated damages |
Kabayan | Batan | Improvement of Washington - Colong - Bajen - Agpay FMR | Roads | 250,000.00 | 249,210.30 | 4 Brothers Construction | 20% PDF CY 2016 | 2017-02-07 | 2017-02-27 | Completed | Clustered a) imp of Batan FMR; b) imp of washington-colong-bajen-agpay FMR @ Batan, Kabayan |
Kabayan | Tawangan | a) Tawangan - Lusod National High School Ground Levelling with Riprap and Retaining Wall b) Riprap and Leveling of Lusod-Tawangan National High School Grounds | Road Side | 1,500,000.00 | 1,497,764.31 | Jamil Sean Construction | 20% PDF CY 2016 | 0000-00-00 | 0000-00-00 | Completed | contract a)riprapping & improvement of Lusod-Tawangan national high school grounds @ tawangan, kabayan, benguet B)riprap of lusod-tawangan national high school ground @ tawangan kabayan be |
Kabayan | Ballay | Improvement of Dinamili - Tinaleb FMR | Roads | 500,000.00 | 499,310.05 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-08-27 | 2017-09-12 | Completed | Clustered L projects - b) imp of tinaleb - naybo FMR @ Ballay, Kabayan; c) imp of tinaleb - pangawan FMR @ Ballay, kabayan |
Kabayan | Ballay | Improvement along Taaw - Kubo FMR | Roads | 1,000,000.00 | 998,449.99 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-07-05 | 2017-08-03 | Completed | |
Kabayan | Ballay | Improvement of Tinaleb - Naybo FMR | Roads | 500,000.00 | 499,204.00 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-07-05 | 2017-07-26 | Completed | |
Kabayan | Ballay | Improvement of Tinaleb - Pangawan FMR | Roads | 500,000.00 | 499,268.46 | Jamil Sean Construction | 20% PDF CY 2016 | 2017-07-05 | 2017-08-01 | Completed | Clustered L projects - b) imp of tinaleb - naybo FMR @ Ballay, Kabayan; c) imp of tinaleb - pangawan FMR @ Ballay, kabayan |
Kabayan | Eddet | Construction of Eddet Elementary School Stage | Building | 800,000.00 | 781,833.25 | Akiki Builders | 20% PDF CY 2016 | 2017-10-27 | 2018-02-13 | Completed | Completed on February 27, 2018 |
Kabayan | Bashoy | Construction of Comfort Room, Bashoy, Kabayan | Building | 600,000.00 | 589,179.29 | Akiki Builders | 20% PDF CY 2016 | 2017-10-27 | 2018-01-24 | Completed | Completed on February 15, 2018 |
Kapangan | Sagubo | Construction of steps, Sagubo Elementary School, Kapangan, Benguet | Building | 200,000.00 | 197,364.78 | Balangcod Construction | 20% PDF CY 2016 | 2016-12-05 | 2017-01-02 | Completed | |
Kapangan | Kapangan Central | Construction of Gym in KCNHS, Kapangan | Building | 5,000,000.00 | 4,997,536.35 | Family Circle Construction | 20% PDF CY 2016 | 2016-06-24 | 2017-01-19 | Completed | |
Kapangan | Kapangan Central | Construction of Gymnasium for KNHS (additional) | Building | 5,000,000.00 | | Family circle construction/Marcos P. Luma-ang | 20% PDF CY 2016 | 2017-06-24 | 2017-01-19 | Completed | payment of partial accomplishment of clustered projects a)const. of a gymnasium in kapangan central national high school, central kapangan, beguet b)const. of a gymnasium for kapangan national high school.
|
Kibungan | Palina | Construction of Pikwila Building & Toilet, Palina | Building | 800,000.00 | 766,849.79 | Akip Construction and Enterprise | 20% PDF CY 2016 | 2016-12-12 | 2017-03-11 | Completed | |
Kibungan | Palina | Construction of Multi-Purpose Waiting Shed at Gotong, Palina | Waiting Shed | 150,000.00 | 129,024.63 | Akip Construction and Enterprise | 20% PDF CY 2016 | 2016-12-12 | 2017-01-09 | Completed | |
La Trinidad | Wangal | Construction of Multi-Purpose Shed for Horse Back Riding Area, Children's Park | Building | 950,000.00 | 941,181.63 | On Top Construction | 20% PDF CY 2016 | 2017-04-30 | 2017-07-20 | Completed | CLUSTERED b) Control No.: 02-16-00110 - On Top Construction |
Kibungan | Madaymen | Tirepathing of Sagangasang-Dalumpit FMR, Madaymen, Kibungan | Road | 150,000.00 | 139,304.39 | akip construction and ent/bobby wayan | 20% PDF 2016 | 2016-12-12 | 2017-01-03 | Completed | clustered "D" projects with same funding source but different project on, a. tirepathing of sagangasang-dalumpit fmr madaymen kibungan benguet |
Kibungan | Tacadang | Improvement of Batangan Elementary School Building | Building | 500,000.00 | 499,129.60 | akip construction and enterprises/ bobby wayan | 20% PDF 2016 | 2016-12-12 | 2017-01-29 | Completed | |
Kibungan | Lubo | Improvement of Amselwing FMR | Road | 800,000.00 | 799,251.23 | Akip Construction and Enterprise | 20% PDF 2016 | 2017-01-27 | 2017-05-22 | Completed | |
Kibungan | Lubo | Construction of Cottage in Lubo Elementary School, Kibungan, Benguet (additional) | Building Repair | 1,000,000.00 | 983,075.85 | Akip Construction and Enterprise | 20% PDF CY 2016 | 2017-01-27 | 2017-05-23 | Completed | |
La Trinidad | Cruz | Continuation of Construction of Covered Canal at Sunshine Alley | | 300,000.00 | | | 20% PDF CY 2016 | 2017-01-27 | 2017-03-04 | Completed | 63.22% accomplishment with under run
Update coordinates |
La Trinidad | Poblacion | Concreting of Access Road to Upper Buyagan Central - Balili | | 400,000.00 | 385,497.47 | akip construction and enterprises/ bobby wayan | 20% PDF CY 2016 | 2017-01-27 | 2017-05-20 | Completed | Input the accurate coordinates of the project |
La Trinidad | Betag | Improvement of EQA Laboratory at BeGH | Building Repair | 137,000.00 (clustered) | 136,679.82 | ICO Construction | 20% PDF CY 2016 | 2017-12-05 | 2017-12-30 | Completed | contract under cluster g: a) concreting of shilan-jappa brgy road, shilan, la trinidad; b) imp of eqa laboratory, begh, la trinidad |
La Trinidad | Lubas | Improvement of Sidewalk along Proper Lubas | Road Side | 950,000.00 (clustered) | 941,181.63 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-24 | Completed | CLUSTERED a) Control No.: 02-16-001016 - On Top Construction
contract under cluster "O" projects - b)imp of sidewalk along proper lubas, L Trinidad; c)const of covered canal @ upper bayabas, pico, LTB |
La Trinidad | Lubas | Construction of Covered Canal at Upper Lubas | Road Side | 250,000.00 (clustered) | 248,144.47 | On Top Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-06-28 | Completed | Input the accurate coordinates
contract under cluster "O" projects - b)imp of sidewalk along proper lubas, L Trinidad; c)const of covered canal @ upper bayabas, pico, LTB |
La Trinidad | Ambiong | Improvement of Upper Ambiong FMR | Roads | 612,000.00 | 611,343.33 | Summerlin Construction | 20% PDF CY 2016 | 2017-05-30 | 2017-10-07 | Completed | Completed with under run.
|
La Trinidad | Wangal | Improvement of School Building at Benguet Technical School | | 1,000,000.00 | 989,788.28 | Leo Heirs Construction | 20% PDF CY 2016 | 2016-11-28 | 2017-03-30 | Completed | |
La Trinidad | Pico | Road Improvement at Pinebreeze, Shamolog | Roads | 700,000.00 | 674,225.72 | Hillbrand Engineering | 20% PDF CY 2016 | 2017-04-02 | 2017-03-30 | Completed | 98.76% completed with under run.
Input the accurate coordinates |
La Trinidad | Poblacion | Improvement of Road Windy Hill, Concreting of the Road at Upper Central Buyagan | Roads | 450,000.00 | 447,407.91 | Sangin General Construction | 20% PDF CY 2016 | 2017-02-01 | 2017-02-26 | Completed | Concreting of the Road at Upper Central Buyagan - Project Completed on February 24, 2017 |
La Trinidad | Ambiong | Construction of Footbridge at Lanas Creek, Takinan | Bridge | 300,000.00 | 298,341.17 | Pulicay Grandson's Construction | 20% PDF CY 2016 | 2017-11-22 | 2018-02-02 | Completed | Input the accurate coordinates |
Mankayan | Suyoc | Slope protection of Mayangyang Road, Suyoc, Mankayan | Road Side | 500,000.00 | 498,903.75 | Cabuguiasan Builders | 20% PDF CY 2016 | 2017-12-01 | 2017-01-09 | Completed | |
La Trinidad | Puguis | Finishing of Waiting Lounge at CTS Puguis | Building | 200,000.00 | 133,766.05 | JURICMARC CONSTRUCTION | 20% PDF CY 2016 | 2018-10-01 | 2018-11-08 | Completed | |
Bokod | Bila | Improvement of FMR along Gwiling-Yabo in Palansa, Bila | Roads | 100,000.00 | 96,510.62 | SRBA General Construction | SB #2 CY 2016 | 0000-00-00 | 0000-00-00 | Completed | |
Bokod | Bila | Improvement of FMR along Gwiling-Yabo in Palansa, Bila | Roads | 100,000.00 | 96,510.62 | SRBA General Construction | SB #2 CY 2016 | 0000-00-00 | 0000-00-00 | Completed | |
Sablan | Banangan | Rehabilitation of Keddeng Tramline | Tramline | 1,000,000.00 | 998,499.98 | Anas Construction | 20% PDF CY 2016 | 2017-02-03 | 2017-04-08 | Completed | |
Sablan | Kamog | Concreting of Lower Tinekey FMR, Kamog, Sablan | Roads | 350,000.00 | 349,525.00 | Guardian Construction | 20% PDF 2016 | 2017-02-02 | 2017-03-02 | Completed | lustered "A" projects a.) concreting of lower tinekey fmr, kamog sablan, benguet b.) const of footpath and installation of hand drills at sitio botot |
Sablan | Bagong | Cluster "S" a.) Riprapping and Installation of Footpath Railings from Sitio Depnac - Cayapes | Road Side | 350,000.00 | 246,481.75 | Guardian Construction | 20% PDF CY 2016 | 2017-06-11 | 2017-07-08 | Completed | CLUSTERED - b) Control No.: 02-16-00138 - Guardian Construction |
Sablan | Bayabas | const of footpath and installation of hand drills at sitio botot | Building | 350,000.00 | 246,481.75 | Guardian Construction | 20% PDF 2016 | 2017-06-11 | 2017-06-27 | Completed | CLUSTERED - a) Control No.: 02-16-00137 - Guardian Construction
clustered "A" projects a.) concreting of lower tinekey fmr, kamog sablan, benguet b.) const of footpath and installation of hand drills at sitio botot |
Sablan | Balluay | Completion of Building: Sablan National High School | Building Repair | 700,000.00 | 698,860.09 | Guardian Construction | 20% PDF CY 2016 | 2017-12-13 | 2018-03-13 | Completed | Completed on February 27, 2018 |
Tuba | Twin Peaks | Construction of Comfort Room, Twin Peaks, Tuba | Building | 700,000.00 | 698,422.32 | Roben Runas Construction | 20% Project Development Fund - 2016 | 2017-08-10 | 2017-11-17 | Completed | |
Tuba | Taloy Sur | Concreting of Extension of Palina Balinsuay FMR, Taloy Sur | Roads | 500,000.00 | 499,134.04 | Roben Runas Construction | 20% PDF CY 2016 | 2016-11-20 | 2017-02-27 | Completed | |
Tuba | Tadiangan | Construction of Flood control at Altaverde | Road Side | 250,000.00 | 248,774.61 | anas construction/ dionisio anas | 20% Project Development Fund - 2016 | 2016-12-20 | 2017-01-27 | Completed | Verify Date |
Tuba | Camp 4 | Construction of Fire Hydrant | Building | 1,000,000.00 | 998,602.54 | Roben Runas Construction | 20% PDF CY 2016 | 2016-11-29 | 2017-01-26 | Completed | |
Tuba | Camp 3 | Construction of Loading Platform | Building | 250,000.00 | 249,316.21 | roben runas construction/roben runas | 20% PDF CY 2016 | 2016-11-28 | 2017-01-29 | Completed | For validation of amount (JC)
contract,construction of loading platform antamok camp 3 located at camp 3 tuba benguet |
Tuba | Tabaan Sur | Construction of Water Works System | | 500,000.00 | | roben runas construction/roben runas | 20% Project Development Fund - 2016 | 2016-12-15 | 2017-01-22 | Completed | |
Tuba | Camp 3 | Opening of Agpay FMR | Roads | 2,000,000.00 | 1,997,961.91 | | 20% PDF CY 2016 | 2017-04-03 | 2017-06-24 | Completed | |
Tublay | Ambassador | Construction of Day Care Center Sto. Nino, Ambassador, Tublay, Benguet | Building | 800,000.00 | 798,719.84 | Aguinsod Construction | 20% PDF CY 2016 | 2016-07-20 | 2018-04-21 | Completed | |
Kibungan | Sagpat | Improvement along Kibungan Junction - Sagpat Provincial Road | Roads | 2,000,000.00 | | | 20% PDF CY 2016 | 2017-02-12 | 2017-06-04 | Completed | Completed on June 4, 2017 |
La Trinidad | Shilan | Improvement along Shilan - Sagpawe Provincial Road | Roads | 1,000,000.00 | 997,649.30 | Drichloui Construction | 20% PDF CY 2016 | 2017-01-19 | 2017-03-26 | Completed | Completed on March 26, 2017 |
La Trinidad | Alno | Construction of PCCP along Alno - Pangablan Provincial Road | Roads | 1,000,000.00 | | Universal De Leon Construction and Aggregates | 20% PDF CY 2016 | 2017-02-05 | 2017-03-06 | Completed | |
Atok | Topdac | Improvement along Mencio Junction - Topdac Provincial Road | Roads | 1,500,000.00 | 1,496,965.37 | Hillstone Builders | 20% PDF CY 2016 | 2017-11-25 | 2017-02-17 | Completed | |
Atok | Cattubo | Improvement along Tulodan - Sayangan Provincial Road | Roads | 1,000,000.00 | | | 20% PDF CY 2016 | 2017-02-12 | 2017-03-13 | Completed | |
Tublay | Tublay Central | Construction of PCCP along Tublay Gate - Tublay Presidencia Provincial Road | Roads | 1,000,000.00 | | bosongan construction/jun-jun wag-e | 20% PDF CY 2016 | 2017-02-12 | 2017-03-14 | Completed | |
Itogon | Poblacion | Improvement of Diversion Road from Batuang - Poblacion Carantes Road (Provincial Road) | Roads | 1,000,000.00 | 995,075.16 | Babecor Builders | 20% PDF CY 2016 | 2017-11-16 | 2017-03-02 | Completed | Completed on March 2, 2017 |
Tuba | Tadiangan | Improvement of Yagyagan - Ampusa Provincial Road | Roads | 1,000,000.00 | 989,412.85 | Balangcod Construction | 20% PDF CY 2016 | 2016-12-02 | 2017-01-28 | Completed | Completed on February 10, 2017 with liquidated damages |
Itogon | Ucab | Improvement of Tram - Ucab Provincial Road | Roads | 1,000,000.00 | | wdg construction and supply/winson galangco | 20% PDF CY 2016 | 2017-08-14 | 2017-10-31 | Completed | Completed on October 27, 2017 |
Mankayan | Tabio | Improvement along Mankayan - Bato Provincial Road | Roads | 1,000,000.00 | 998,000.00 | Donato Sakiwat Construction | 20% PDF CY 2016 | 2017-08-09 | 2017-09-30 | Completed | Completed on September 30, 2017 |
Tuba | Taloy Sur | Improvement of Pugo - Balangbang Vehicular Bridge | Bridge | 1,500,000.00 | 1,494,076.30 | Roben Runas Construction | 20% PDF CY 2016 | 2017-07-11 | 2018-02-17 | Completed | Completed on February 15, 2018 |
Mankayan | Balili | Improvement along Atayan, Balili Provincial Road | Roads | 800,000.00 | 774,066.63 | ZMC General Construction | 20% PDF CY 2016 | 2017-07-11 | 2017-08-26 | Completed | Completed August 15, 2018 |
Kibungan | Sagpat | Improvement along Sagpat - Sapdaan Provincial Road | Roads | 1,000,000.00 | 985,062.20 | Drichloui Construction | 20% PDF CY 2016 | 2017-08-25 | 2017-08-25 | Completed | Completed on August 25, 2017 |
Tuba | Twinpeaks | Construction of PCCP along Camp 1 - Indaoac -Twin Peaks Provincial Road | Roads | 5,000,000.00 | 4,993,468.71 | | 20% PDF CY 2016 | 2016-04-10 | 2016-09-03 | Completed | with Liquidated Damages |
Tublay | Daclan | Construction of PCCP along Bangho - Asin Provincial Road | Roads | 2,000,000.00 | 1,997,729.86 | hillstone builders/ hudson depolio | 20% PDF CY 2016 | 2016-06-27 | 2016-08-05 | Completed | 99.50% completed due to under run and also with liquidated damages. |
Sablan | Poblacion | Improvement along Sablan - Sablan Old Presidencia Provincial Road | Roads | 1,000,000.00 | 999,599.52 | | 20% PDF CY 2016 | 2016-06-27 | 2016-11-19 | Completed | |
La Trinidad | Wangal | Improvement along Wangal - Banengbeng Provincial Road | Roads | 3,500,000.00 | 3,490,046.70 | Cliff Construction and Aggregates, Junifer Bosleng | 20% PDF CY 2016 | 2016-07-04 | 2016-12-21 | Completed | with Liquidated Damages |
Bakun | Dalipey | Improvement along Sipitan - Palidan Provincial Road | Roads | 1,000,000.00 | 999,755.00 | | 20% PDF CY 2016 | 2016-06-27 | 2016-07-20 | Completed | |
La Trinidad | Beckel | Improvement along Beckel - Balangbang Provincial Road | Roads | 1,000,000.00 | 998,506.66 | Sej General Construction and Aggregates, Eric De L | 20% PDF CY 2016 | 2016-07-15 | 2016-10-03 | Completed | |
Bokod | Daclan | Improvement along Daclan - Bonagan - Tickey - Camanggaan Provincial Road | Roads | 1,000,000.00 | 998,455.64 | Almond Engineering and Construction | 20% PDF CY 2016 | 2016-09-28 | 2016-11-18 | Completed | with Liquidated Damages |
La Trinidad | Bahong | Improvement along Camp Dangwa - Bahong - Sadag Provincial Road | Roads | 1,000,000.00 | 998,282.81 | EaJr De Leon Construction, Edwardo De Leon Jr | 20% PDF CY 2016 | 2016-08-19 | 2016-10-12 | Completed | |
Kapangan | Labueg | Improvement of Datakan - Alapang - Camp 66 Provincial Road | Roads | 1,000,000.00 | 998,450.22 | Bolds Engineering and Construction | 20% PDF CY 2016 | 2016-09-20 | 2016-11-16 | Completed | 99.75% completed due to under run |
Sablan | Kamog | Improvement of PCCP along Calot - Kamog - Pappa Provincial Road | Roads | 1,000,000.00 | 873,850.00 | Anas Construction | 20% PDF CY 2016 | 2016-09-28 | 2016-10-24 | Completed | |
Atok | Topdac | Construction of Topdac Elementary School Cottage | Building | 500,000.00 | 499,015.08 | Hillstone Builders | 20% PDF CY 2016 | 2016-11-29 | 2017-02-01 | Completed | |
Bokod | Nawal | Improvement of Danas Footbridge | Bridge | 586,000.00 | | | 20% PDF CY 2016 | 2016-03-23 | 2016-08-23 | Completed | Completed on July 25, 2016 |
Buguias | Catlubong | Improvement of Ponopon-Lusab FMR | Roads | 500,000.00 | | SEJ Construction and Aggregates | 20% PDF CY 2016 | 2016-06-27 | 2016-08-06 | Completed | |
Buguias | Catlubong | Improvement of Wallayan-Abbatan FMR | Roads | 1,000,000.00 | | | 20% PDF CY 2016 | 2016-06-27 | 2016-08-23 | Completed | |
Buguias | Amgaleyguey | Improvement of Polis Kiok Road | Roads | 100,000.00 | | | 20% PDF CY 2016 | 2016-07-07 | 2016-07-17 | Completed | |
Buguias | Baculongan Sur | Improvement of Bad-ayan E/S Ground | | 200,000.00 | | | 20% PDF CY 2016 | 2016-07-07 | 2016-07-25 | Completed | |
Buguias | Natubleng | Construction of Concrete Footpath, Lamut | | 100,000.00 | | | 20% PDF CY 2016 | 2016-07-07 | 2016-07-21 | Completed | |
Kabayan | Ballay | Improvement of Liang FMR, Ballay | Roads | 500,000.00 | | | 20% PDF CY 2016 | 2016-06-24 | 2016-08-07 | Completed | Completed on July 18, 2016 |
Kabayan | Ballay | Improvement along Tamangan FMR, Ballay | Roads | 500,000.00 | | | 20% PDF CY 2016 | 2016-06-24 | 2016-07-27 | Completed | Completed on July 12, 2016 |
Kapangan | Kapangan Central | Improvement of Basketball Court at Kapangan Central School | Building Repair | 350,000.00 | | | 20% PDF CY 2016 | 2016-06-29 | 2016-07-27 | Completed | Completed on July 18, 2016 |
La Trinidad | Puguis | Improvement of Buhaw Road | | 800,000.00 | | Sej General Construction and Aggregates/ Eric De L | 20% PDF CY 2016 | 2016-06-29 | 2016-07-29 | Completed | |
Mankayan | Bulalacao | Improvement of Lower Inga-an - Damoslog FMR | Roads | 500,000.00 | | | 20% PDF CY 2016 | 2016-07-05 | 2016-07-31 | Completed | Completed on June 30, 2016 |
Mankayan | Bulalacao | Construction of Concrete Pavement, Lower Inga-an - Damoslof FMR | Roads | 150,000.00 | | | 20% PDF CY 2016 | 2016-07-07 | 2016-07-26 | Completed | Completed on July 26, 2016 |
Mankayan | Bulalacao | Improvement of Cotcot - Napitkey FMR | Roads | 500,000.00 | | | 20% PDF CY 2016 | 2016-05-07 | 2016-07-27 | Completed | Completed on July 26, 2016 |
Itogon | Tuding | Construction of Vehicular Bridge, Mangga-Luneta | Bridge | 3,000,000.00 | | Ico Construction Services/ Jerico A. Palangdan | 20% PDF CY 2016 | 2016-04-18 | 2016-07-15 | Completed | |
Atok | Topdac | Improvement of Nalseb-Topdac FMR | Roads | 500,000.00 | 499,398.81 | | 20% PDF CY 2016 | 2016-07-06 | 2016-09-29 | Completed | Completed on September 22, 2016 |
Bakun | Dalipey | Riprapping of Sipitan Health Clinic Ground | Road Side | 200,000.00 | 199,909.88 | Apaklo Kin Construction | 20% PDF CY 2016 | 2016-09-07 | 2016-10-02 | Completed | Completed on September 29,2016 |
Bokod | Ekip | Improvement of Whetig-Sacba Foot Trail | Roads | 300,000.00 | 298,808.94 | | 20% PDF CY 2016 | 2016-07-15 | 2016-08-18 | Completed | Completed on September 5, 2016
|
Buguias | Amgaleyguey | Amgaleyguey FMR | Roads | 1,000,000.00 | 998,647.04 | | 20% PDF CY 2016 | 2016-01-07 | 2016-09-26 | Completed | |
Buguias | Abatan | Improvement of Bauknit FMR | Roads | 500,000.00 | 498,920.35 | | 20% PDF CY 2016 | 2016-07-14 | 2016-09-21 | Completed | |
Buguias | Baculongan Sur | Improvement of Balintag - Aligan FMR | Roads | 1,000,000.00 | 997,991.06 | | 20% PDF CY 2016 | 2016-06-27 | 2016-10-09 | Completed | |
Buguias | Sebang | Improvement of Paneg-an FMR | Roads | 1,500,000.00 | 1,496,770.33 | | 20% PDF CY 2016 | 2016-07-20 | 2016-10-15 | Completed | |
Buguias | Baculongan Norte | Improvement of Lagan - Naduguan FMR | Roads | 1,000,000.00 | 997,914.83 | | 20% PDF CY 2016 | 2016-06-29 | 2016-09-24 | Completed | |
Buguias | Loo | Improvement along Loo-Modayan-Kitongan FMR | Roads | 800,000.00 | 798,486.77 | | 20% PDF CY 2016 | 2016-06-29 | 2016-09-30 | Completed | |
Itogon | Tinongdan | Construction of Bleachers at Tinong's Gym | Building Repair | 1,000,000.00 | | WDG Construction and Supply/Winson D. Galangco | 20% PDF CY 2016 | 2016-06-29 | 2016-09-21 | Completed | |
Itogon | Loacan | Road Improvement along Beda FMR | Roads | 1,000,000.00 | 999,271.13 | WDG Construction and Supply/Winson D. Galangco | 20% PDF CY 2016 | 2016-07-21 | 2016-09-22 | Completed | |
Kabayan | Tawangan | Improvement of Proper Nakilo FMR, Tawangan | Roads | 1,000,000.00 | 998,472.27 | | 20% PDF CY 2016 | 2016-07-20 | 2016-09-05 | Completed | Completed on September 9, 2016 |
Kabayan | Anchukey | Improvement of Upper Agat Rice Field Access | Roads | 200,000.00 | 448,589.62 | 4 Brothers Construction | 20% PDF CY 2016 | 2016-09-07 | 2016-10-01 | Completed | Cluster "A" - 4 Brothers Construction |
Kabayan | Anchukey | Construction of Tirepath along Anchukey, Baok | Roads | 150,000.00 | 448,589.62 | 4 Brothers Construction | 20% PDF CY 2016 | 2016-09-07 | 2016-10-01 | Completed | Cluster "A" - 4 Brothers Construction |
La Trinidad | Bahong | Construction of Flood Control at Tomay Creek | Road Side | 1,000,000.00 | 998,651.08 | Illstone Builders, Hudson Depolio | 20% PDF CY 2016 | 2016-06-24 | 2016-09-24 | Completed | Completed on September 19, 2016 |
La Trinidad | Shilan | Improvement of Road in Balukas, Shilan | Roads | 1,000,000.00 | 997,882.63 | Sej Construction & Aggregates, Mr. Eric De Leon | 20% PDF CY 2016 | 2016-06-29 | 2016-09-26 | Completed | Completed on September 26, 2016 |
La Trinidad | Balili | Improvement of Footpath with Steel Railings, Tebteb | Roads | 100,000.00 | 99,698.03 | Almond Engineering and Construction | 20% PDF CY 2016 | 2016-08-29 | 2016-09-22 | Completed | Completed on September 15, 2016 |
La Trinidad | Balili | Construction of Footpath at Botiwtiw, Balili | Roads | 100,000.00 | 98,935.41 | Almond Engineering and Construction | 20% PDF CY 2016 | 2016-08-29 | 2016-09-22 | Completed | Completed on September 22, 2016
payment of contract clustered a)const. foothpath in Botiwtiw, Balili, La Trinidad b)const. of foothpath, Tabangaoen, Balili, La Trinidad |
La Trinidad | Balili | Construction of Footpath at Tabangaoen, Balili | Roads | 200,000.00 | 197,224.79 | Almond Engineering and Construction/ Rogelio L. Al | 20% PDF CY 2016 | 2016-08-29 | 2016-10-02 | Completed | Completed on September 16, 2016
contract due on const. footpath and concrete cover of drainage canal at tabangaoen, balili balili la trinidad |
Tuba | Ansagan | Improvement of Bes-ig FMR, Camp 1 | Roads | 1,000,000.00 | 998,423.70 | | 20% PDF CY 2016 | 2016-06-27 | 2016-09-13 | Completed | Completed on September 4, 2016 |
Tuba | Tadiangan | Improvement of Obbog Footpath | Roads | 150,000.00 | 149,422.24 | | 20% PDF CY 2016 | 2016-07-29 | 2016-08-18 | Completed | Completed on September 10, 2016 |
Tublay | Caponga | Improvement of Kapungan Footbridge | Bridge | 150,000.00 | 148,959.19 | Hillstone Builders | 20% PDF CY 2016 | 2016-09-07 | 2016-09-22 | Completed | Completed on September 22, 2016 |
Bokod | Daclan | Improvement of Landing FMR | Roads | 500,000.00 | 498,825.69 | | 20% PDF CY 2016 | 2016-06-29 | 2016-08-03 | Completed | Completed on August 15, 2016 |
Buguias | Baculongan Sur | Improvement of Nangodey - Baney FMR | Roads | 500,000.00 | 498,539.76 | | 20% PDF CY 2016 | 2016-06-29 | 2016-08-02 | Completed | |
Buguias | Buyacaoan | Improvement of Tablaan - Godogodan FMR at Bekes | Roads | 500,000.00 | 498,953.62 | | 20% PDF CY 2016 | 2016-07-06 | 2016-08-09 | Completed | |
Buguias | Buyacaoan | Improvement of Bayoyo FMR | Roads | 500,000.00 | 498,504.80 | | 20% PDF CY 2016 | 2016-06-30 | 2016-08-10 | Completed | |
Buguias | Abatan | Improvement of Galudan FMR | Roads | 500,000.00 | 494,162.58 | | 20% PDF CY 2016 | 2016-07-04 | 2016-08-12 | Completed | |
Itogon | Tuding | Improvement of Abeo - Duclos Road, Tuding | Roads | 500,000.00 | 497,816.05 | Bemada Construction/ Benny M. Daliling | 20% PDF CY 2016 | 2016-06-29 | 2016-08-12 | Completed | |
Kabayan | Eddet | Improvement of Nanchupit FMR, Eddet | Roads | 1,000,000.00 | 998,420.02 | | 20% PDF CY 2016 | 2016-06-24 | 2016-09-16 | Completed | Completed on August 31, 2016 |
Kabayan | Tawangan | Improvement of Proper Nambangawan FMR | Roads | 500,000.00 | 499,074.95 | | 20% PDF CY 2016 | 2016-07-20 | 2016-08-25 | Completed | Completed on August 11, 2016 |
Kapangan | Gadang | Construction of BeMONC Building, Gadang | Building | 250,000.00 | 249,197.60 | | 20% PDF CY 2016 | 2016-06-29 | 2016-08-02 | Completed | Completed on August 2, 2016 |
Kapangan | Pudong | Improvement of Ambalading Footbridge, Toplac | Bridge | 300,000.00 | 298,893.87 | | 20% PDF CY 2016 | 2016-07-06 | 2016-08-24 | Completed | Completed on August 19,2016 |
La Trinidad | Shilan | Improvement of Road at Besil-Safid | Roads | 700,000.00 | 698,212.52 | Babecor Builders/ Marcos P. Bacoy | 20% PDF CY 2016 | 2016-06-24 | 2016-08-08 | Completed | Completed on August 8, 2016 |
Mankayan | Cabiten | Concreting of Pathway at Baed | Road Side | 300,000.00 | 296,006.08 | | 20% PDF CY 2016 | 2016-07-04 | 2016-08-05 | Completed | Completed on August 5, 2016 |
Mankayan | Balili | Improvement of Solsolatan - Dagadag FMR | Roads | 400,000.00 | 398,411.17 | | 20% PDF CY 2016 | 2016-07-18 | 2016-08-22 | Completed | Completed on August 4, 2016 |
Mankayan | Bulalacao | Improvement of Daycog - Demang FMR | Roads | 500,000.00 | 296,281.11 | | 20% PDF CY 2016 | 2016-07-20 | 2016-08-14 | Completed | Completed on August 13, 2016 |
Sablan | Pappa | Improvement of Balingew - Taya FMR | Roads | 500,000.00 | 498,879.34 | | 20% PDF CY 2016 | 2016-07-07 | 2016-08-19 | Completed | |
Tuba | Tabaan Norte | Improvement of Parasipis - Marconil FMR | Roads | 500,000.00 | 498,773.79 | | 20% PDF CY 2016 | 2016-07-07 | 2016-08-09 | Completed | Completed on August 4, 2016 |
Tuba | Taloy Sur | Improvement of Tawalan - Andil FMR | Roads | 500,000.00 | 498,987.68 | | 20% PDF CY 2016 | 2016-06-30 | 2016-08-09 | Completed | Completed on August 1, 2016 |
Bokod | Ekip | Improvement of Ekip - Naswak Footpath | Roads | 800,000.00 | 798,452.44 | | 20% PDF CY 2016 | 2016-07-15 | 2016-11-17 | Completed | |
Buguias | Baculongan Sur | Improvement of Sinto - Lamagan FMR | Roads | 500,000.00 | 596,453.53 | JYP Construction | 20% PDF CY 2016 | 2016-09-16 | 2016-11-17 | Completed | Cluster "A" - JYP Construction a) Control No. 02-16-00243 b) Control No. 02-16-00234 |
Kapangan | Kapangan Central | Improvement of Padang, Central Foot trail | Roads | 150,000.00 | 148,989.16 | Balangcod Construction | 20% PDF CY 2016 | 2016-11-09 | 2016-11-30 | Completed | Completed on November 22, 2016 |
Kibungan | Madaymen | Improvement of Pakpakitan Elementary School | Building | 600,000.00 | 598,479.56 | Bosongan Construction | 20% PDF CY 2016 | 2016-09-28 | 2016-11-18 | Completed | Completed on November 18, 2016 |
La Trinidad | Bineng | Improvement/Expansion of Bineng Waterworks System | Waterworks System | 1,000,000.00 | 998,179.18 | JCA General Construction and Engineering Services | 20% PDF CY 2016 | 2016-04-11 | 2016-11-06 | Completed | |
La Trinidad | Wangal | Construction of Perimeter Fence at Wangal Nursery | Building Repair | 250,000.00 | 248,847.22 | Anas Construction | General Fund - All Offices CY 2016 | 2016-09-07 | 2016-11-01 | Completed | |
La Trinidad | Puguis | Construction of Drainage Canal at DSWD-Veterans Building | Road Side | 500,000.00 | 499,393.61 | Drichloui Construction | 20% PDF CY 2016 | 2016-09-07 | 2016-11-08 | Completed | |
Sablan | Poblacion | Improvement of Tinekey Waterworks System, Lower Poblacion | Waterworks System | 500,000.00 | 499,478.68 | HGW=3 Engineering & Construction | 20% PDF CY 2016 | 2016-09-18 | 2016-11-10 | Completed | |
Buguias | Bangao | Construction of Labayan Vehicular Bridge | Bridge | 2,000,000.00 | 1,997,489.34 | | 20% PDF CY 2016 | 2016-04-15 | 2016-08-11 | Completed | with liquidated damages |
Buguias | Sebang | Improvement of Guipadan - Pasbol FMR | Roads | 500,000.00 | 495,580.17 | | 20% PDF CY 2016 | 2016-07-18 | 2016-10-05 | Completed | |
Buguias | Sebang | Improvement of Pasbol - Ibisan FMR | Roads | 100,000.00 | 596,453.53 | JYP Construction | 20% PDF CY 2016 | 2016-09-16 | 2016-10-18 | Completed | Cluster "A" - JYP Construction |
Itogon | Tuding | Improvement of Bua-Cemetery Road | Roads | 500,000.00 | 498,482.03 | Gacoscos Construction | 20% PDF CY 2016 | 2016-09-28 | 2016-11-03 | Completed | |
Kabayan | Anchukey | Construction of Tirepath along Anchokey FMR | Roads | 100,000.00 | 448,589.62 | 4 Brothers Construction | 20% PDF CY 2016 | 2016-09-07 | 2016-10-01 | Completed | Cluster "A" - 4 Brothers Construction |
Kabayan | Anchokey | Construction of Tirepath along Anchokey FMR, Baok | Roads | 150,000.00 | 149,533.14 | | 20% PDF CY 2016 | 2016-09-07 | 2016-10-01 | Completed | Completed on September 28, 2016 |
Kabayan | Ballay | Construction of Riprap along Tuidan FMR | Roads | 250,000.00 | 249,082.46 | Jamil Sean Construction | 20% PDF CY 2016 | 2016-09-07 | 2016-10-23 | Completed | Completed on October 4, 2016 |
Kabayan | Pacso | Improvement of Sitio Champeg Waterworks System | Waterworks System | 200,000.00 | 199,128.84 | Solonio Construction | 20% PDF CY 2016 | 2016-09-19 | 2016-10-23 | Completed | Completed on October 18, 2016 |
Kapangan | Datakan | Construction of Foot Bridge at Dassip - Panakbakan - Pongayan | Bridge | 500,000.00 | 495,070.42 | | 20% PDF CY 2016 | 2016-07-06 | 2016-10-04 | Completed | Completed on October 3, 2016 |
La Trinidad | Shilan | Improvement of Roads in Jappa - Shilan | Roads | 700,000.00 | 696,984.80 | Hillstone Builders, Hudson Depolio | 20% PDF CY 2016 | 2016-07-18 | 2016-10-13 | Completed | Completed on October 13, 2016 |
La Trinidad | Alno | Construction of Concrete Fence at the Southwest Portion of the BeNHS Alno Annex | Building Repair | 150,000.00 | 148,985.30 | Hillstone Builders | 20% PDF CY 2016 | 2016-09-07 | 2016-10-13 | Completed | Completed on October 7, 2016 |
Tuba | Camp 4 | Construction of Flood Control, Goldstream, Camp 1 | Road Side | 500,000.00 | 498,987.68 | Roben Runas Construction | 20% PDF CY 2016 | 2016-09-20 | 2016-12-17 | Completed | Completed on October 25, 2016 |
La Trinidad | Balili | Construction of Drainage Canal at Central Balili | Road Side | 500,000.00 | 498,119.14 | Almond Engineering and Construction | 20% PDF CY 2016 | 2016-09-08 | 2016-10-30 | Completed | Completed on October 30, 2016 |
Tuba | Camp 1 | Concreting along Gusaran Pathway, Camp 1 | Roads | 150,000.00 | 149,647.34 | Roben Runas Construction | 20% PDF CY 2016 | 2016-09-08 | 2016-10-16 | Completed | Completed on October 16 , 2016 |
Tuba | Tabaan Norte | Installation of Box Culvert at Tabaan Norte | Road Side | 150,000.00 | 149,647.34 | Roben Runas Construction | 20% PDF CY 2016 | 2016-09-08 | 2016-10-28 | Completed | Completed on October 15, 2016 |
Mankayan | Cabiten | Construction of Lubban Waiting Shed, Camanpaguey, Cabiten | Building | 100,000.00 | 99,797.11 | Baldas Construction | 20% PDF CY 2016 | 2018-02-06 | 2018-02-21 | Completed | Completed on February 21, 2018 |
Buguias | Amlimay | Construction of Barangay Multi-Purpose Hall Comfort Room | Building | 500,000.00 | 498,050.39 | JuricMarc Construction | 20% PDF CY 2016 | 0000-00-00 | 0000-00-00 | Completed | |
Kabayan | Tawangan | Completion of Tawangan Multi-Purpose Building/Hall | Building Repair | 100,000.00 | 99,464.81 | Haight's Construction | 20% PDF CY 2016 | 2018-03-12 | 2018-04-01 | Completed | |
Atok | Paoay | Cluster A: a) Tiling of Wall of the Operating Room / Delivery Room of Atok District Hospital | Building Repair | 544,000.00 | 542,563.24 | Haight's Construction | 20% PDF CY 2016 | 2018-03-12 | 2018-06-08 | Completed | Cluster "A"
b) Improvement of Emergency Room and Shade at Atok District Hospital
c) Improvement / Extension of Stockroom at Atok District Hospital
d) Replacement of Roofing Garage and Ramp Located at Atok District Hospital |
Atok | Paoay | Cluster A: b) Improvement of Emergency Room and Shade at Atok District Hospital | Building Repair | 544,000.00 | 542,563.24 | Haight's Construction | 20% PDF CY 2016 | 2018-03-12 | 2018-06-08 | Completed | Cluster "A"
a) Tiling of Wall of the Operating Room / Delivery Room of Atok District Hospital
c) Improvement / Extension of Stockroom at Atok District Hospital
d) Replacement of Roofing Garage and Ramp Located at Atok District Hospital |
Atok | Paoay | Cluster A: c) Replacement of Roofing Garage and Ramp Located at Atok District Hospital | Building Repair | 544,000.00 | 542,563.24 | Haight's Construction | 20% PDF CY 2016 | 2018-03-12 | 2018-06-08 | Completed | Cluster "A"
a) Tiling of Wall of the Operating Room / Delivery Room of Atok District Hospital
b) Improvement of Emergency Room and Shade at Atok District Hospital
d) Improvement / Extension of Stockroom at Atok District Hospital |
Atok | Paoay | Improvement / Extension of Stockroom at Atok District Hospital | Building Repair | 544,000.00 | 542,563.24 | | 20% PDF CY 2016 | 2018-03-12 | 2018-06-08 | Completed | Cluster "A"
a) Tiling of Wall of the Operating Room / Delivery Room of Atok District Hospital
b) Improvement of Emergency Room and Shade at Atok District Hospital
c) Replacement of Roofing Garage and Ramp Located at Atok District Hospital |
La Trinidad | Beckel | Construction of Centralized Drainage Canal at Beckel | Road Side | 200,000.00 | 199,474.44 | ICO Construction | 20% PDF CY 2016 | 2018-03-09 | 2018-04-03 | Completed | 100% Completed as of April 3, 2018 with 199,474.44 Total Cost Incurred. |
Bakun | Dalipey | Concreting of Masalin Footpath, Dalipey, Bakun | Construction of Foot path | 100,000.00 | 99,314.45 | NAIR Construction & Engineering | 20% PDF CY 2016 | 2018-03-04 | 2018-01-31 | Completed | Completed on February 19, 2018 |
Bakun | Dalipey | Construction of Catwalk Shed, Talbino Elementary School, Dalipey Bakun Benguet | Road Side | 150,000.00 | 149,611.63 | NAIR Construction & Engineering | 20% PDF CY 2016 | 2018-01-17 | 2018-02-15 | Completed | Completed on February 15, 2018 |
Buguias | Baculongan Norte | Construction of Pugo Day Care Center Baculongan Norte | Building | 1,200,000.00 | 1,194,194.84 | HGW=3 Engineering & Construction | 20% PDF CY 2016 | 2018-02-06 | 2018-05-17 | Completed | 1) 2 suspensions
2) 100% Completed
3) Revised target date completion - October 19, 2018 |
Kapangan | Balakbak | Construction of Senior Citizen Building at Balakbak, Kapangan | Building | 1,500,000.00 | 1,480,322.29 | Balangcod Construction | 20% PDF CY 2016 | 2017-11-20 | 2018-04-13 | Completed | 1) This project was previously suspended due to RROW Clearance from the DPWH (Date of Resume: 11/20/2017)
2) Completed with liquidated damage |
Bokod | Poblacion | Cluster | Roads | 400,000.00 | 398,823.43 | Hillbrand Engineering | 20% PDF CY 2016 | 2017-02-06 | 2017-02-26 | Completed | Cluster "C" b) Control No. 02-16-00269 c) Control No. 02-16-00041 d)
Hillbrand Engineering |
Bokod | Ambuklao | Cluster | Roads | 400,000.00 | 398,823.43 | Hillbrand Engineering | 20% PDF CY 2016 | 2017-02-06 | 2017-03-14 | Completed | Cluster "C" a) Control No. 2-16-00268 c) Control No. 02-16-00041 d)
Hillbrand Engineering |
Buguias | Lengaoan | Improvement of Pilando - Igang Footpath | Roads | 150,000.00 | 149,605.67 | | 20% PDF CY 2016 | 2016-11-22 | 2017-03-03 | Completed | Completed with LD |
Itogon | Dalupirip | Improvement of Togi - Ayosip FMR | Roads | 1,000,000.00 | 924,394.95 | babecor builders/ marcos bakoy | 20% PDF CY 2016 | 2017-02-14 | 2017-04-10 | Completed | Completed and usable |
Mankayan | Cabiten | Construction of Multi-Purpose Building (Phase I) located at Gueweng Cabiten | Building | 400,000.00 | 399,085.93 | | 20% PDF CY 2016 | 2018-02-06 | 2018-03-24 | Completed | Completed on March 24, 2018 |
Sablan | Banangan | Construction of Pasalubong Tourist Information Center, Viewdeck Banangan | Building | 500,000.00 | 469,972.82 | Anas Construction | 20% PDF CY 2016 | 2018-02-12 | 2018-04-09 | Completed | 100% Completed - Total Cost Incurred PhP 469,972.82 as of April 30, 2018 |
Tuba | Tadiangan | Construction of Sinco Footpath, Sayapan | Roads | 100,000.00 | 99,346.34 | Anas Construction | 20% PDF CY 2016 | 2018-02-12 | 2018-02-23 | Completed | Completed on February 23, 2018 |
Tuba | Taloy Sur | Construction of Quarantine Checkpoint along Marcos Highway, Tuba Benguet | Building | 400,000.00 | 398,758.63 | Anas Construction | 20% PDF CY 2016 | 2018-02-12 | 2018-03-31 | Completed | |
Tuba | Nangalisan | Improvement of Nangalisan E/S Ground, Nangalisan Tuba Benguet | Building | 300,000.00 | 299,385.96 | Roben Runas Construction | 20% PDF CY 2016 | 2018-02-12 | 2018-03-21 | Completed | Completed on March 19, 2018 |
Kabayan | Ballay | Improvement of Minac-Batuan FMR, Ballay, Kabayan | Roads | 800,000.00 | 784,485.14 | Solonio Construction | 20% PDF CY 2016 | 2018-04-04 | 2018-06-02 | Completed | |
Mankayan | Balili | Construction of Farmers Bodega, Mankengaw, Balili, Mankayan | Building | 250,000.00 | 249,906.65 | Juricmarc Construction | 20% PDF CY 2016 | 2018-04-05 | 2018-05-06 | Completed | Completed on May 5, 2018, with 224,915.99 total cost incurred |
Mankayan | Cabiten | Concreting of Siksiko Road, Cabiten, Mankayan | Roads | 600,000.00 | 585,575.17 | Sharamelle Construction and General Engineering | 20% PDF CY 2016 | 2018-04-02 | 2018-05-06 | Completed | |
Buguias | Buyacaoan | Improvement of Northern Benguet District Hospital Kitchen, Bekes, Buyacaoan, Buguias, Benguet | Improvement works | 300,000.00 | 297,067.56 | AIP Construction | 20% PDF - 2016 | 2018-09-04 | 2018-10-08 | Completed | |
Tuba | Tabaan Sur | Construction of Multi-Purpose Hall, Tabaan Sur, Completion | Building Construction | 500,000.00 | 473,189.08 | Sapdoy Enterprises | 20% PDF 2016 | 2018-11-19 | 2018-12-21 | Completed | Completed and usable. |
Sablan | Banangan | Construction of Banangan Footpath,Ambacuag | Construction of Footpath | 200,000.00 | 199,077.45 | Anas Consruction | 20% PDF-2016 | 2018-10-05 | 2018-11-01 | Completed | |
La Trinidad | for verification | Improvement of School fence and Entrance Gate and Ground Improvement | School Fence and Ground Improvement | 600,000.00 | 597,870.96 | Drichloui Construction | 20% PDF-2016 | 2018-11-15 | 2018-12-13 | Completed | |
Kibungan | Tacadang | Construction of Footbridge - Bileng 1 in Tacadang, Kibungan | Footbridge construction | 350,000.00 | 312,458.03 | Akip Construction & Enterprise | 20% PDF - 2016 | 2018-11-29 | 2019-02-26 | Completed | |
Kabayan | Tawangan | Completion of Multi-Purpose Building (Phase II), Tawangan, Kabayan | Construction of Multi-Purpose CR, Tiling of Multi-Purpose Building | 500,000.00 | 499,139.51 | Akiki Builders | 20% PDF 2016 | 2018-11-29 | 2019-02-09 | Completed | |
Atok | Pasdong | Completion of Banayakew Multi-Purpose Building with Watertank & Ground Improvement at Pasdong, Atok, Benguet | Completion of Building | 800,000.00 | 786,958.74 | Four Brothers Construction | 20% PDF 2016 | 2019-01-31 | 2019-05-09 | Completed | Ongoing with LD; Revised target date= 06/16/2019.
1 suspension |
Kabayan | Ballay | Improvement of Basketball Court in Besocol, Ballay | Basketball Court | 300,000.00 | 298,101.51 | Four Brothers Construction | 20% PDF 2016 | 2019-01-17 | 2019-02-28 | Completed | |
Sablan | Bagong | Concreting of Barangay Clinic Grounds, Depnac, Bagong, Sablan | Building | 150,000.00 | 149,272.97 | Guardian | 20% PDF 2016 | 2019-01-17 | 2019-02-24 | Completed | |
Kabayan | Pacso | Construction of Barangay Multi-Purpose Building/Hall Comfort Room | Construction of comfort room | 500,000.00 | 499,139.51 | Akiki Builders | 20% PDF 2016 | 2018-11-29 | 0000-00-00 | Terminated | 1 suspension.
Suspended on December 10, 2018 due to site problem |
Tublay | Ambongdolan | Construction of Teachers Cottage, Langbis Primary School, Ambongdolan, Tublay, Benguet | Cottage | 800,000.00 | 794,510.75 | Sandstream Construction | 20% PDF 2016 | 2018-11-13 | 2018-01-25 | Terminated | For Termination |
Itogon | Tinongdan | Improvement/Phase III Of X-Ray Completion Of Multi-Purpose Laboratory Complex | Installation of GI roofing | 500,000.00 | 498,011.72 | Reko General Construction | 20% PDF - 2016 | 2019-02-04 | 2019-03-24 | Completed | |
Tuba | Taloy Sur | Re-opening and Improvement along Begis-Poyopoy Provincial Road | Roads | 2,000,000.00 | 1,890,093.30 | Boyet Builders | 20% PDF 2016 | 2019-06-07 | 2019-09-12 | Temporarily suspended | Suspended; Waiting for ECC to be issued by DENR |
Atok | Poblacion | Improvement of Banayakeo-Poblacion Barangay Road | Roads | 500,000.00 | 498,833.25 | | 20% PDF CY 2017 | 2017-11-29 | 2017-12-23 | Completed | |
Atok | Abiang | Improvement of Guiweng-Boy-otan Barangay Road | Roads | 500,000.00 | 498,950.57 | | 20% PDF CY 2017 | 2017-11-29 | 2017-12-11 | Completed | Completed on December 11, 2017 |
Bakun | Kayapa | Improvement of Kayapa FMR | Roads | 500,000.00 | 498,752.60 | SRBA General Construction / Ray Angluben | 20% PDF CY 2017 | 2017-11-24 | 2017-12-24 | Completed | Completed as per plan. |
Bakun | Poblacion | Construction of Catwalk Shed from Bakun National High School to Bakun Central School | Building | 500,000.00 | 498,868.74 | Pulicay Grandsons Construction | 20% PDF CY 2017 | 2017-10-20 | 2017-12-23 | Completed | Completed as per plan with liquidated damages. |
Bakun | Gambang | Improvement of Alam-am Nasayotean FMR | Roads | 500,000.00 | 499,247.99 | NAIR Construction & Engineering | 20% PDF CY 2017 | 2017-12-13 | 2018-01-24 | Completed | 1) Cluster "D" -
2) Completed on January 24, 2018
|
Tuba | Twin Peaks | Improvement / Construction of PCCP along Camp 1 - Indaoac - Twin Peaks Provincial Road | Roads | 5,000,000.00 | 4,989,058.80 | Roben Runas Construction | 20% PDF CY 2017 | 2017-08-08 | 2017-11-14 | Completed | Completed on October 30, 2017 |
Bokod | Nawal | Fencing of Critical Section of Ambagat Foot Trail, Nawal, Bokod | Fence | 200,000.00 | 198,906.60 | AG Chungalan Construction | 20% PDF CY 2017 | 2017-08-10 | 2017-09-12 | Completed | |
Buguias | Poblacion | Improvement of Bolo - Tocdo FMR | Roads | 500,000.00 | 499,257.84 | ICO Construction | 20% PDF CY 2017 | 2017-10-26 | 2017-12-04 | Completed | Completed on December 4, 2017 |
Buguias | Bangao | Improvement of Cotcot - Labayan FMR | Roads | 500,000.00 | 498,230.87 | On Top Construction | 20% PDF CY 2017 | 2017-10-20 | 2017-12-02 | Completed | Completed on December 2, 2017 |
Buguias | Loo | Rehabilitation of JNR Modayan - Kitongan FMR | Roads | 500,000.00 | 498,959.21 | HGW=3 Engineering & Construction | 20% PDF CY 2017 | 2017-10-26 | 2017-11-22 | Completed | Completed on November 22, 2017 with under run |
Buguias | Buyacaoan | Construction of Flood Control at Gusadan (a,b,c,d) | Road Side | 2,400,000.00 | 2,365,832.50 | Kalahan General Construction and Supply | 20% PDF CY 2017 | 2017-08-16 | 2017-12-10 | Completed | Completed on December 10, 2017 |
Buguias | Lengaoan | Improvement of Beling - Paingan FMR | Roads | 500,000.00 | 499,527.98 | | 20% PDF CY 2017 | 2017-11-29 | 2017-12-15 | Completed | Completed on December 15, 2017 |
Buguias | Baculongan Sur | Improvement along Bad-ayan - Cayapas Road at Lamangan Section | Roads | 500,000.00 | 499,198.87 | | 20% PDF CY 2017 | 2017-11-28 | 2017-12-27 | Completed | Completed on November 27, 2017 |
Buguias | Natubleng | Construction of Lamut Flood Control | Road Side | 500,000.00 | 499,151.64 | | 20% PDF CY 2017 | 2017-11-28 | 2017-12-26 | Completed | Completed on December 26, 2017 |
Kapangan | Balakbak | Concreting of Open Canal Along National Road-Sitio Buyot, Balakbak, Kapangan, Benguet | Canal | 300,000.00 | 274,444.94 | Akip Construction and Enterprise | 20% PDF - 2017 | 2018-05-17 | 2018-06-12 | Completed | Completed: 07/19/2018 with LD
Revised Target Date of Completion: 06/21/2018 |
Kabayan | Duacan | Improvement of Bekes - Balangbang FMR | Roads | 500,000.00 | 498,938.88 | Akiki Builders | 20% PDF CY 2017 | 2017-09-20 | 2017-10-16 | Completed | |
Kabayan | Tawangan | Improvement of Nadaklan - Pangaya FMR | Roads | 500,000.00 | 498,791.99 | Jamil Sean Construction | 20% PDF CY 2017 | 2017-09-18 | 2017-10-12 | Completed | |
Kabayan | Gusaran | Concreting of Adereg - Aponan Footpath | Roads | 200,000.00 | 199,582.81 | Jamil Sean Construction | 20% PDF CY 2017 | 2017-09-18 | 2017-11-14 | Completed | |
Kabayan | Kabayan Barrio | Construction of Cauliflower Drying Shed, Balaban | Building | 500,000.00 | 490,331.90 | Solonio Construction | 20% PDF CY 2017 | 2017-12-13 | 2018-02-13 | Completed | Completed on March 20, 2018 with liquidated damages |
Itogon | Loakan | Construction of waiting shed at Dampingan, frontage of Lipma Office | Waiting Shed | 150,000.00 | 146,332.38 | Aljune Builders | 20% PDF CY 2017 | 2017-10-06 | 2017-11-07 | Completed | |
Itogon | Loakan | Construction of waiting shed at Sabkil (in front of UCCP) | Waiting Shed | 150,000.00 | 146,332.38 | Aljune Builders | 20% PDF CY 2017 | 2017-10-06 | 2017-11-07 | Completed | |
Kapangan | Pongayan | Concreting of Footpath, Sagapa-Gaswiling, Pongayan, Kapangan | Roads | 250,000.00 | 245,724.90 | | 20% PDF CY 2017 | 2017-08-16 | 2017-09-20 | Completed | |
Itogon | Ampucao | Improvement of Pasiday-Tocod FMR Ampucao | Roads | 500,000.00 | 496,764.95 | Aljune Builders / alma domagto | 20% PDF CY 2017 | 2017-12-13 | 2018-01-21 | Completed | Completed on January 19, 2018
contract under cluster c: a) imp of pasiday-tocod fmr, ampucao, itogon; b) concreting of road portion and canal along upper mangga road, tuding, itogon |
Itogon | Tuding | Construction of Road Portion and Canal along Upper Mangga Road | Roads | 300,000.00 | 297,044.04 | Aljune Builders / alma domagto | 20% PDF CY 2017 | 2017-12-13 | 2018-01-06 | Completed | Completed on January 6, 2018
contract under cluster c: a) imp of pasiday-tocod fmr, ampucao, itogon; b) concreting of road portion and canal along upper mangga road, tuding, itogon |
Kapangan | Balakbak | Improvement of Balok Barangay Road, Datakan, Kapangan | Roads | 1,500,000.00 | 1,480,322.29 | vanket engineering & construction / frankie diano | 20% PDF CY 2017 | 2017-08-15 | 2017-09-06 | Completed | Needs additional fund so that the road can reach the nearby barangay |
Kapangan | Gadang | Concreting of Sitio Namon-ao, Gadang Foot trail | Roads | 500,000.00 | 499,544.49 | | 20% PDF CY 2017 | 2017-08-15 | 2017-11-22 | Completed | Revised target date completion on November 22, 2017 due to suspension/change order. |
La Trinidad | Puguis | Improvement of Buhao Road in Puguis, La Trinidad, Benguet | Roads | 500,000.00 | 435,095.38 | SEJ Construction and Aggregates | 20% PDF CY 2017 | 2018-04-03 | 2018-04-30 | Completed | 10% completed as of April 15, 2018 with 43,509.54 total cost incurred. (-) 3.95% slippage. Completed as of June 1, 2018 |
Kapangan | Pongayan | Concreting of footpath, Gaswiling, Pongayan | | 500,000.00 | | Ebtitiwa General Engineering & Construction Servic | 20% PDF - 2017 | 2017-08-16 | 2017-09-27 | Completed | Clustered "G" projects - b) concreting of footpath, sagapa-gaswiling, pongayan, kapangan, benguet |
La Trinidad | Puguis | Improvement of Buhaw Road in Puguis, La Trinidad, Benguet | Road | 500,000.00 | 435,095.38 | SEJ Construction and Aggregate | 20% PDF CY 2017 | 2018-03-04 | 2018-04-30 | Completed | Completed on June 10, 2018 with liquidated damages |
Kapangan | Pudong | Construction along Sacdoan FT (Toplac), Pudong, Kapangan, Benguet | | 200,000.00 | 198,901.02 | guardian copnstruction/ruben pacheco jr. | 20% PDF CY 2017 | 2017-12-13 | 2018-01-16 | Completed | Completed on January 16, 2018 |
Kibungan | Palina | Perimeter Fencing of Palina Brgy. Health Station and Multi-Purpose Brgy. Hall, Palina, Kibungan, Benguet | Fence | 500,000.00 | 498,985.83 | Lincee General Construction | 20% PDF CY 2017 | 2017-08-17 | 2017-09-20 | Completed | |
La Trinidad | Wangal | Fencing of School Perimeter with Ground Improvement at Benguet Technical School | Fence | 800,000.00 | 798,430.16 | Drichloui Construction | 20% PDF CY 2017 | 2017-10-11 | 2018-02-11 | Completed | Completed on February 5, 2018. |
La Trinidad | Shilan | Concreting of Shilan - Jappa Barangay Road | Roads | 500,000.00 | 499,021.50 | | 20% PDF CY 2017 | 2017-05-12 | 0000-00-00 | Completed | Completed on January 14, 2018 |
La Trinidad | Poblacion | Improvement of Drainage Canal at Upper Central Buyagan | Road Side | 500,000.00 | 493,504.94 | ICO Construction | 20% PDF CY 2017 | 2017-10-26 | 2017-12-28 | Completed | Completed on January 12, 2018 with liquidated damages. |
La Trinidad | Betag | Construction of Septic Tank Drainage at BeGH | | 1,000,000.00 | 928,127.33 | RNAA Builders | 20% PDF CY 2017 | 2018-05-17 | 2018-07-20 | Completed | |
La Trinidad | Ambiong | Construction of Drainage Canal at Ambiong E/S to Central Ambiong | | | 284,965.33 | JuricMarc Construction | 20% PDF CY 2017 | 2018-05-09 | 2018-06-06 | Completed | |
Kapangan | Taba-ao | Construction of Concrete Footpath at Ubod, Taba-ao, Kapangan | Footpath | 250,000.00 | 249,812.50 | Random Builders | 20% PDF 2017 | 2018-05-17 | 2018-07-04 | Completed | Completed 07/17/2018 |
Mankayan | Bulalacao | Improvement of Cotcot-Ambingan Bulalacao Barangay Road | Roads | 500,000.00 | 499,007.22 | | 20% PDF CY 2017 | 2018-11-10 | 2018-12-10 | Completed | Need additional fund |
Mankayan | Tabio | Construction of Road Protection Wall and Riprapping with Canal along Patpat Barangay Road, Tabio, Mankayan | Road Side | 500,000.00 | 498,474.09 | Sharamelle Construction and General Engineering | 20% PDF CY 2017 | 2017-11-22 | 2018-01-10 | Completed | Completed on February 12, 2018 |
Mankayan | Guinaoang | Improvement of Guinaoang Multi-Purpose Hall, Guinaoang, Mankayan | Building Repair | 500,000.00 | 499,015.00 | Malco Construction | 20% PDF CY 2017 | 2017-11-29 | 2018-01-22 | Completed | Completed on March 7, 2018 |
Mankayan | Cabiten | Improvement of Maduto-Baguyos Barangay Road Cabiten, Mankayan | Roads | 500,000.00 | 499,060.87 | Malco Construction | 20% PDF CY 2017 | 2017-11-29 | 2018-01-04 | Completed | Completed on January 4, 2018 |
Mankayan | Bedbed | Improvement of Daguay-Payeo, Bedbed Barangay Road, Bedbed, Mankayan | Roads | 500,000.00 | 494,535.81 | | 20% PDF CY 2017 | 2017-12-21 | 2018-01-11 | Completed | Completed on February 18, 2018 |
Mankayan | Poblacion | Improvement of Rural Health Unit (RHU) Building, Poblacion, Mankayan | Building Repair | 500,000.00 | 494,433.31 | | 20% PDF CY 2017 | 2017-12-21 | 2018-01-28 | Completed | Completed on January 22, 2018 |
Sablan | Banengbeng | Improvement of Japos-Botot FMR | Roads | 500,000.00 | 498,445.56 | Anas Construction | 20% PDF CY 2017 | 2017-08-16 | 2017-09-26 | Completed | |
Sablan | Kamog | Improvement of Doddo-Kamog FMR | Roads | 500,000.00 | 498,079.52 | Anas Construction | 20% PDF CY 2017 | 2017-12-21 | 2018-01-27 | Completed | Completed on January 18, 2018 |
Sablan | Bayabas | Perimeter Fencing at Agri-Eco Farm (by phase) | Fence | 1,000,000.00 | 998,202.68 | Aguinsod Construction | 20% PDF CY 2017 | 2017-11-29 | 2018-02-06 | Completed | Resumed on August 3, 2018 with a revised target completion date of August 10, 2018 |
Tuba | San Pascual | Improvement of San Pascual - Bokyagan-Talnag Road, San Pascual, Tuba | Roads | 500,000.00 | 498,667.57 | | 20% PDF CY 2017 | 2017-08-10 | 2017-11-13 | Completed | |
Tuba | San Pascual | Construction of Sheep and Goat Sheds, San Pascual, Tuba | Building | 500,000.00 | 499,264.63 | Roben Runas Construction | 20% PDF CY 2017 | 2017-07-31 | 2017-10-25 | Completed | |
Tuba | Tabaan Norte | Road Improvement along Binungbong - Toybongan FMR | Roads | 500,000.00 | 497,168.11 | | 20% PDF CY 2017 | 2017-07-10 | 2017-09-22 | Completed | Completed and usable. |
Tuba | Nangalisan | Improvement of Lasilas Footpath, Nangalisan, Tuba | Roads | 200,000.00 | 199,461.83 | Roben Runas Construction | 20% PDF CY 2017 | 2017-07-31 | 2017-09-25 | Completed | |
Tuba | Tadiangan | Improvement of Sipitan-Tadiangan FMR, Tadiangan Tuba Provincial Road (Concreting) | Roads | 500,000.00 | 497,780.89 | Roben Runas Construction | 20% PDF CY 2017 | 2017-07-31 | 2017-08-13 | Completed | |
Tuba | Camp 4 | Concreting of Liwliw Barangay Road | Roads | 500,000.00 | 491,730.00 | Quieges Builders and Enterprise | 20% PDF CY 2017 | 2017-05-07 | 2017-07-17 | Completed | |
Tublay | Baayan | Improvement of Baayan, Tacarang, Sitio Section, Baayan, Tublay | Roads | 500,000.00 | 495,556.84 | Roben Runas Construction | 20% PDF CY 2017 | 2017-08-31 | 2018-02-19 | Completed | contract under cluster e: a) imp of baayan brgy rd, tacarang, sitio section, baayan, tublay; b) const of ripra/slope protection at moran e/s, tuel, tublay
Completed on February 12, 2018. The project was previously suspended due to road sinking along Sayatan - Tacarang Road an on going project of the Municipality of Tublay. Resume on January 6, 2018 |
Tublay | Tuel | Construction of Riprap/Slope Protection at Moran Elementary School, Tuel, Tublay, Benguet | Road Side | 500,000.00 | 499,085.45 | Roben Runas Construction | 20% PDF CY 2017 | 2017-08-31 | 2018-02-09 | Completed | Completed on February 12, 2018, the project was previously suspended due to the on going project by the DPWH-CAR at the area. Resumed on January 6, 2018 |
Tublay | Basil | Construction of Riprap, Barangay Multi-Purpose Hall, Basil, Tublay, Benguet | Road Side | 500,000.00 | 499,171.75 | Sangin Construction | 20% PDF CY 2017 | 2017-09-03 | 2017-12-27 | Completed | |
Tublay | Ambassador | Improvement of Gongel-Belong Barangay Road, Ambassador, Tublay | Roads | 500,000.00 | 498,982.64 | Sangin Construction | 20% PDF CY 2017 | 2017-11-03 | 2017-12-07 | Completed | |
Tublay | Tublay Central | Construction of shed along the Footpath going to Tublay Elementary School and TSHI, Tublay Central | Road Side | 250,000.00 | 249,501.10 | | 20% PDF CY 2017 | 2017-10-04 | 2017-11-19 | Completed | Completed as programmed and usable |
Tublay | Ambongdolan | Improvement of Betwag-Pachel FMR, Ambongdolan, Tublay | Roads | 500,000.00 | 498,503.45 | roben runas construction/roben runas | 20% PDF CY 2017 | 2017-10-04 | 2017-11-16 | Completed | cluster s: a) imp of betwag-pachel fmr, ambongdolan, tublay |
Tublay | Ambassador | Construction of Footpath at Los-ok Diktewan, Ambassador, Tublay, Benguet | Roads | 200,000.00 | 199,411.29 | roben runas construction/roben runas | 20% PDF CY 2017 | 2017-09-04 | 2017-12-04 | Completed | clustered projects: b) const of shed along footpath going to tublay e/s and c) tshi, const of footpath at los-ok-dictewan, ambassador, tublay |
Mankayan | Bedbed | Improvement / Construction of PCCP along Mankayan - Bedbed Provincial Road | Roads | 5,000,000.00 | 4,980,000.00 | Donato Sakiwat Construction | 20% PDF CY 2017 | 2017-12-02 | 2017-12-04 | Completed | Completed on December 24, 2017 |
Tuba | Taloy Sur | Improvement / Construction of PCCP along Begis - Poyopoy Provincial Road | Roads | 5,000,000.00 | 4,875,363.69 | HDG Construction and Enterprise | 20% PDF CY 2017 | 2017-09-12 | 2017-12-26 | Completed | Completed on December 16, 2017 |
Kabayan | Gusaran | Improvement / Construction of PCCP along National Road Junction - Diboong - Bangao Provincial Road | Roads | 5,000,000.00 | 3,894,790.97 | Kuatako Construction and General Construction | 20% PDF CY 2017 | 2017-07-31 | 2017-09-17 | Completed | Completed on September 17, 2017 with PCCP deficiency |
Bokod | Daclan | Improvement / Construction of PCCP along Daclan - Bonagan - Tikey Camanggaan Provincial Road | Roads | 5,000,000.00 | 4,995,073.69 | Summerlin Construction | 20% PDF CY 2017 | 2017-01-13 | 2017-09-18 | Completed | with PCCP deficiency |
Kapangan | Sagubo | Improvement / Construction of PCCP along Lomon - Sagubo Provincial Road | Roads | 5,000,000.00 | 4,963,666.00 | Sangin General Construction | 20% PDF CY 2017 | 2017-12-01 | 2018-03-30 | Completed | partial accomplishment: imp/const of pccp along lomon-sagubo provincial road, kapangan as of March 30, 2018 |
La Trinidad | Lubas | Fencing of La Trinidad National High School, Lubas | Fence | 500,000.00 | 479,663.72 | SEJ Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-04-13 | Completed | 100%Completed - Total Cost Incurred PhP 479,663.72 as of April 30, 2018 |
La Trinidad | Alapang | Improvement of Bahong Dapiting - Alapang BENECO Road | Roads | 500,000.00 | 494,180.02 | SEJ Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-03-15 | Completed | Completed on October 23, 2018 |
Kibungan | Madaymen | Improvement of Nangayangan - Masala FMR, Masala | Roads | 500,000.00 | 495,410.43 | Pulicay Grandsons Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-03-04 | Terminated | Terminated for change of title and location |
La Trinidad | Tawang | Construction of Footsteps at Upper Boted, Tawang, La Trinidad | | | 423,944.47 | | 20% PDF CY 2017 | 2018-05-09 | 2018-06-03 | Completed | 78.00% completed with 330,676.69 total cash incurred as of May 2018. |
Kibungan | Lubo | Improvement of Lubo - Sayangan Barangay Road, Lubo | Roads | 500,000.00 | 498,621.53 | Balangcod Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-04-22 | Completed | 1) Completed: April 11,2018 - Total Cost Incurred PhP 498,621 as of April 30, 2018
2)Suspended effective February 7, 2018 awaiting action for the submitted realignment of the project to "Improvement for Madaymen - Namul -acan - Masala FMR" of BLGU - Resumed effective March 20, 2018; Revised Target Completion Date on April 22, 2018 |
La Trinidad | Wangal | Improvement of Barangay Road at Upper Gayasi, Wangal | Roads | 500,000.00 | 498,640.07 | Sangin Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-03-04 | Completed | Completed on March 2, 2018 |
Sablan | Banangan | Improvement of Ambacuag, Oring FMR | Roads | 500,000.00 | 494,813.66 | Aguinsod Construction | 20% PDF CY 2017 | 2018-02-08 | 2018-03-16 | Completed | Completed on March 12, 2018 |
Sablan | Bagong | Improvement of Bagong FMR | Roads | 500,000.00 | 498,828.15 | Guardian Construction | 20% PDF CY 2017 | 2018-02-09 | 2018-03-20 | Completed | Completed on April 2, 2018 with Php 498,828.15 total cost incurred |
Mankayan | Taneg | Improvement of Baayasan - Sabean FMR | Roads | 500,000.00 | 498,454.47 | Sharamelle Construction and General Engineering | 20% PDF CY 2017 | 2018-02-09 | 2018-03-30 | Completed | Completed on May 30, 2018, with 498,454.47 total cost incurred |
Kabayan | Ballay | Construction of Concrete Canal and Riprapping along Dimipiyas FMR | Roads | 500,000.00 | 498,621.22 | Jamil Sean Construction | 20% PDF CY 2017 | 2018-02-09 | 2018-03-26 | Completed | Completed on March 23, 2018 |
Kabayan | Lusod | Improvement of Proper Lusod Ba-ayan FMR | Roads | 500,000.00 | 499,412.86 | Jamil Sean Construction | 20% PDF CY 2017 | 2018-02-09 | 2018-03-08 | Completed | Completed on March 21, 2018 - for Post inspection |
Mankayan | Balili | Improvement of Atayan - Macawawa Dasoy Barangay Road | Roads | 5,000,000.00 | 4,981,108.47 | Toclo Construction | 20% PDF CY 2017 | 2018-02-09 | 2018-03-13 | Completed | Completed on March 13, 2018 |
Mankayan | Suyoc | Construction of Pacda FMR, Roadside Riprap, Pacda, Suyoc Palasaan | Road Side | 500,000.00 | 489,838.00 | Toclo Construction | 20% PDF CY 2017 | 2018-02-09 | 2018-03-17 | Completed | Completed on March 17, 2018 |
Mankayan | Sapid | Improvement of Lower Tubo FMR | Roads | 500,000.00 | 489,219.18 | Toclo Construction | 20% PDF CY 2017 | 2018-02-09 | 2018-03-17 | Completed | Completed on February 19, 2018 |
Kapangan | Taba-ao | Construction of Concrete Footpath at Abiang,Taba-ao | Roads | 250,000.00 | 249,226.81 | ADL Construction | 20% PDF CY 2017 | 2018-03-01 | 2018-04-18 | Completed | |
Atok | Naguey | Construction of Tirepath along Sawingan to Bua Barangay Road | Roads | 500,000.00 | 499,312.99 | Haight's Construction | 20% PDF CY 2017 | 2018-03-12 | 2018-05-17 | Terminated | |
Buguias | Catlubong | Improvement of Bot-oan - Ponopon FMR | Roads | 500,000.00 | 494,863.90 | Juricmarc Construction | 20% PDF CY 2017 | 2018-03-22 | 2018-04-27 | Completed | For post inspection |
Itogon | Tuding | Road Protection along Lower Mangga Road, Tuding (Phase II) | Roads | 200,000.00 | 194,588.75 | | 20% PDF CY 2017 | 2018-03-26 | 2018-05-06 | Completed | |
Kibungan | Sagpat | Construction of Slope Protection and Drainage Canal at Akbab, Sagpat, Kibungan, Benguet | Construction of canal and slope protection | 300,000.00 | 289,473.72 | | 20% PDF 2017 | 2018-05-09 | 2018-06-07 | Completed | |
Kabayan | Batan | Construction of Multi-Purpose Building, Bajen (Phase I and Phase II) | Building | 800,000.00 | 798,979.61 | Sangin Construction | 20% PDF CY 2017 | 2018-03-08 | 2018-06-02 | Completed | |
Kapangan | Paykek | Improvement along Lomon Kapangan Provincial Road | Roads | 5,000,000.00 | 4,985,230.94 | BTCJR Construction and Engineering Services | 20% PDF CY 2017 | 2018-03-08 | 2018-09-24 | Completed | 22.80% Completed - Total Cost Incurred PhP 1,159,066.19 as of April 13, 2018 |
Atok | Cattubo | Improvement of Barangay Road at KM. 54 to Tulodan | Roads | 500,000.00 | 498,687,45 | Haight's Construction | 20% PDF CY 2017 | 2018-01-30 | 2018-03-12 | Completed | |
Bakun | Ampusongan | Improvement along Ampusongan to Nakanga Road | Roads | 500,000.00 | 492,754.94 | Reasons Construction | 20% PDF CY 2017 | 2018-01-31 | 2018-03-21 | Completed | |
Bakun | Sinacbat | Improvement of Ba-ey - Cangaw to Dalingoan FMR | Roads | 1,000,000.00 | 983,388.41 | Reasons Construction | 20% PDF CY 2017 | 2018-01-31 | 2018-03-21 | Completed | Completed |
Bakun | Bagu | Improvement of Maliteng - Saddle FMR | Roads | 500,000.00 | 495,476.05 | Pulicay Grandsons Construction | 20% PDF CY 2017 | 2018-01-31 | 2018-03-04 | Completed | Completed(97.19%) on March 4, 2018 with underrun. |
Buguias | Sebang | Improvement of Mankaet-Pasbol FMR (Extension) | Roads | 500,000.00 | 498,591.92 | Random Builders | 20% PDF CY 2017 | 2018-01-31 | 2018-03-10 | Completed | Completed on February 26, 2018 |
Kapangan | Labueg | Concreting of Longboy - Tacal - Busoc FMR | Roads | 500,000.00 | 499,276.82 | guardian copnstruction/ruben pacheco jr. | 20% PDF CY 2017 | 2018-01-03 | 2018-01-30 | Completed | Completed on January 29, 2018 |
La Trinidad | Betag | Improvement of Barangay Road (near Depayso's Residence) | Roads | 500,000.00 | 491,345.36 | ICO Construction | 20% PDF CY 2017 | 2017-10-26 | 2018-02-03 | Completed | Completed on January 25, 2018 |
Itogon | Gumatdang | Rehabilitation of Besil - Narba Footbridge, Gumatdang | Bridge | 500,000.00 | 484,842.32 | Aljune Builders | 20% PDF CY 2017 | 2017-10-06 | 2017-11-24 | Completed | Completed and usable
cluster h contracts at itogon : a) rehab of besil-narba footbridge, b)const of waiting shed @ dampingan, c) const of waithing shed @ sakbil |
Bokod | Daclan | Improvement of the Linen and Laundry Section, DMMH | Building Repair | 340,000.00 | 335,868.75 | DMCD Engineering and Construction | 20% PDF CY 2017 | 2018-02-03 | 2018-03-30 | Completed | |
Kapangan | Paykek | Completion of Ricemill Facility Housing and Accessories at Cadtay Kapangan | Building Repair | 500,000.00 | 493,595.29 | Vanket Engineering and Construction | 20% PDF CY 2017 | 2018-02-12 | 2018-04-12 | Completed | 100% Completed - Total Cost Incurred PhP 493,595.29 as of April 30, 2018 |
Kibungan | Badeo | Construction of Mocgao Day Care Center Building, Badeo, Kibungan | Building | 1,000,000.00 | 999,787.16 | Remnant Builders | 20% PDF CY 2017 | 2018-02-18 | 2018-06-22 | Completed | Completed
Revised Target Date of Completion: August 6, 2018 |
Kibungan | Madaymen | Construction of Concrete Pavement along Tagapaya-Salong FMR | Roads | 1,000,000.00 | 998,966.63 | Hillbrand Engineering | 20% PDF CY 2017 | 2018-02-12 | 2018-03-26 | Completed | COMPLETED: Reported and recommended for no payment since the project was completed prior to the release of the NTP; for termination |
La Trinidad | Alno | Construction of Footpath with Railings from Elementary to National High School, Alno | Roads | 586,000.00 | 585,557.48 | DMCD Engineering and Construction | 20% PDF CY 2017 | 2018-02-14 | 2018-04-23 | Completed | Completed with slippage on April 23, 2018 |
La Trinidad | Tawang | Concreting of Purok 4, Tawang Barangay Road Towards Tawang - Lubas - Ambiong National Road | Roads | 300,000.00 | 298,984.34 | Sangin Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-03-08 | Completed | Completed on February 28, 2018 |
La Trinidad | Cruz | Construction of Slope Protection at Sitio Kangas, Cruz | Road Side | 500,000.00 | 445,918.76 | Guardian Construction | 20% PDF CY 2017 | 2018-02-07 | 2018-03-10 | Completed | Completed on March 30, 2018 |
Sablan | Bayabas | Construction of Waiting Shed, Pidawan, Bayabas | Building | 330,000.00 | 313,084.25 | Anas Construction | 20% PDF CY 2017 | 2018-02-12 | 2018-04-09 | Completed | |
Sablan | Palali | Construction of Septic Tank and Site Improvement of a Quarantine Checkpoint along Naguilian Road | Building | 150,000.00 | 149,718.23 | Anas Construction | 20% PDF CY 2017 | 2018-01-17 | 2018-02-04 | Completed | Completed on February 4, 2018 |
Tublay | Tublay Central | Improvement of School Ground at TSHI Extension, Tublay Central , Tublay Benguet | Building Repair | 250,000.00 | 249,139.56 | Sangin Construction | 20% PDF CY 2017 | 2018-03-26 | 2018-04-29 | Completed | |
Buguias | Buyacaoan | Construction of flood control, Gusadan | Flood Control | 500,000.00 | 495,506.34 | MacGat Construction | 2017 20% PDF | 2018-04-13 | 2018-05-24 | Completed | Completed: 07/18/2018 with 1 suspension
Revised target date of completion: 07/24/2018 |
Kabayan | Eddet | Improvement of Balang-Sokong-Pinanchay-Talukip-Cable FMR, Eddet, Kabayan | | 500,000.00 | 498,398.53 | | 2017 20% PDF | 0000-00-00 | 0000-00-00 | Completed | |
Kibungan | Sagpat | Improvement along Sagpat - Sapdaan Provincial Road | Roads | 5,000,000.00 | 4,449,389.20 | Sangin General Construction | 20% PDF CY 2017 | 2018-02-03 | 2018-07-10 | Completed | 18.44% Completed with 11.51% Slippage - Total Cost Incurred PhP 308,342.67 as of April 13, 2018. |
Bokod | Daclan | Construction of Stage for Bokod National High School, Ambangeg Campus, Daclan | Building | 400,000.00 | 398,844.35 | Sangin Construction | 20% PDF CY 2017 | 2018-03-23 | 2018-05-21 | Completed | Completed |
Sablan | Bayabas | Construction of Barn House, OPAG, Bulala | Building | 1,000,000.00 | 914,594.00 | Anas Construction | 20% PDF - 2017 | 2018-04-25 | 2018-07-25 | Completed | |
Atok | Cattubo | Improvement/ Construction of PCCP along Tuludan - Sayangan Provincial Road | PCCP; Grouted Riprap | 5,000,000.00 | 4,994,705.06 | Buganheirs Eng'g and Construction | 20% PDF - 2017 | 2018-04-24 | 2018-09-12 | Completed | 88.55% completed with a revised target date of completion = 09/27/2018 |
Kapangan | Kapangan Central | Construction of Grouted Riprap,Central,Kapangan (below Barangay Hall),Central,Kapangan,Benguet | PCCP,Grouted Riprap | 500,000.00 | 401,893.04 | Pulicay Grandsons Construction | 20% PDF - 2017 | 2018-07-04 | 2018-08-22 | Completed | |
Buguias | Bangao | Improvement of Loading Platform-Quarantine Checkpoint Located at Cotcot, Bangao, Buguias, Benguet | | 300,000.00 | 299,476.87 | On Top Construction | 20% PDF - 2017 | 2018-10-17 | 2018-11-26 | Completed | |
Sablan | Bagong | Construction of waiting shed, Cayapes | Building Completion of waiting Shed | 250,000.00 | 249,040.00 | Guardian Construction | SB #1, CY 2017 | 2018-10-03 | 2018-10-28 | Completed | |
La Trinidad | Puguis | Construction of Irrigation Tank at CTS, Puguis | Waterworks System | 200,000.00 | 194,102.52 | JURICMARC CONSTRUCTION | 20% PDF 2017 | 2018-10-22 | 2018-11-16 | Completed | |
La Trinidad | Bineng | Improvement of Sitio Kagiskis Barangay Road at Bineng, La Trinidad, Benguet | Road Pavement | 500,000.00 | 494,416.30 | On Top Construction | 20% PDF 2017 | 2018-10-19 | 2108-12-15 | Completed | |
Itogon | Loacan | Construction of Public Toilet at Geweng,Loacan,Itogon,Benguet | Construction of CR | 200,000.00 | 199,412.95 | Aljune Builders | 20% PDF CY 2017 | 2018-11-26 | 2018-12-31 | Completed | |
Buguias | Baculongan Sur | Completion of Obanga CDC Building | Building Construction | 700,000.00 | 694,553.19 | MACGAT Construction | 20% PDF 2017 | 0000-00-00 | 2019-01-15 | Completed | Completed, Rough Phase. |
Tuba | Taloy Sur | Construction of Additional Watertank | Water System | 200,000.00 | 199,076.72 | Roben Runas Construction | 20% PDF | 0000-00-00 | 0000-00-00 | Completed | Completed on November 5, 2018 |
Kapangan | Pudong | Concreting Along Alimuyos Foot-trail (Bacatey - Toplac | Foo-trail Concreting | 300,000.00 | 297,754.40 | Juricmarc Construction | 20% PDF 2017 | 2018-11-13 | 2019-02-08 | Completed | Completed and usable. |
Tublay | Daclan | Construction of Footbridge at Meril, Daclan, Tublay, Benguet | Footbridge construction | 500,000.00 | 460,452.12 | Hillstone Builders | 20% PDF-2017 | 2018-12-12 | 2019-01-28 | Completed | |
Kapangan | Cayapes | Construction of Grouted Riprap in School Boundaries, Cayapes | Grouted Riprap | 500,000.00 | 470,338.76 | E.B Titiwa General Eng'g & Construction | 20% PDF 2017 | 2018-11-06 | 2019-01-02 | Completed | |
Bokod | Ekip | Improvement of Multi-Purpose Building | Comfort Room | 500,000.00 | 482,779.80 | Hillbrand Engineering | 20% PDF 2017 | 2018-12-12 | 2019-02-07 | Completed | |
La Trinidad | Wangal | Construction of 3rd Floor Roofing and Improvement of Buildings, Benguet Technical School, Wangal, La Trinidad | Construction of Roofing | 2,500,000.00 | 2,213,501.43 | On Top Construction | 20% PDF 2017 | 2018-11-29 | 2019-05-18 | Completed | Ongoing with 45.90% completion as of January 2019 |
Tuba | Camp 6 | Construction of quarantine Checkpoint along Kennon Road, Tuba, Benguet | Quarantine Checkpoint Construction | 400,000.00 | 398,231.09 | Ruben B. Runas Construction | 20% PDF 2017 | 2018-10-05 | 2019-02-15 | Completed | Completed and usable |
Buguias | Amlimay | Completion of Dagway Box Culvert | Box Culvert | 500,000.00 | 490,000.00 | SEJ Construction | 20% PDF 2017 | 2019-01-22 | 2019-03-01 | Completed | |
Kabayan | Anchokey | Construction of Tirepath Along Anchokey FMR, Abat, Anchokey | Tirepath | 500,000.00 | 498,409.70 | Four Brothers | 20% PDF 2017 | 2019-01-17 | 2019-02-17 | Completed | |
Kabayan | Pacso | Improvement of Apanberang-Washington Acess Road, Pacso, Kabayan | Road Improvement | 500,000.00 | 497,478.98 | Four Brothers Construction | 20% PDF 2017 | 2019-01-07 | 2019-02-01 | Completed | |
Kabayan | Gusaran | Improvement of Farm to Market Road at Maebat | Cross drainage, Retaining wall, PCCP | 600,000.00 | 594,802.60 | Jamil Sean Construction | 20% PDF 2017 | 2018-11-29 | 0000-00-00 | Completed | Suspended effective November 29, 2018 due to closed access road caused uncleared slides on various sections
1 suspension |
Sablan | Balluay | Improvement of Balluay - Perrel FMR | Construction of Slope Protection | 500,000.00 | 497,785.20 | Guardian Construction | 20% PDF 2017 | 2018-11-29 | 2019-01-20 | Completed | 1 Suspension
Revised Target Date=3/4/2019
|
La Trinidad | Wangal | Fencing of School Perimeter with Ground Improvement | Fence | 500,000.00 | 497,168.11 | Drich Loui Construction | 20% PDF 2017 | 2017-10-11 | 2018-02-11 | Completed | Completed February 5, 2018 |
Buguias | Calamagan | Construction of Camanbeey - Calamagan Road Pavement/Tirepath | FMR Pavement | 500,000.00 | 494,411.96 | JYP Construction | 20% PDF - 2017 | 2018-09-27 | 2018-10-26 | Completed | |
Kapangan | Boklaoan | Improvement of Barangay Road, Boklaoan, Kapangan, Benguet | PCCP | 500,000.00 | 498,943.20 | Drich Loui Construction | 20% PDF 2017 | 2018-04-25 | 2018-05-16 | Completed | Completed with Under run |
La Trinidad | Tawang | Construction of Handrail of Footsteps at Upper Boted, Tawang, La Trinidad | Handrails | 200,000.00 | 199,703.74 | ICO Construction | 20% PDF 2017 | 2018-05-09 | 2018-06-03 | Completed | Completed on June 28, 2018 with liquidated damages |
Kabayan | Pacso | Road Opening Pacso, Kabayan | Road opening | 500,000.00 | 498,779.64 | Akiki Builders | 20% PDF 2017 | 2018-08-31 | 0000-00-00 | Terminated | |
Kibungan | Madaymen | Construction of Concrete Pavement along Tagpaya - Salong | Concreting of Existing Road | 1,000,000.00 | 998,966.63 | Hillbrand Engineering | 20% PDF 2017 | 2018-02-12 | 2018-03-26 | Terminated | Reported and recommended for no payment and for termination since the project was already completed |
La Trinidad | Balili | Completion of Shed From BSU Horticulture Along CHED, Ogas Store UCCP Church Balili, La Trinidad, Benguet | Construction of Pathway Shed | 500,000.00 | 499,521.04 | Haight's Construction | 20% PDF 2017 | 2018-12-05 | 2018-01-21 | Terminated | Mutually terminated
Recommended for reprogramming |
Kibungan | Madaymen | Improvement of Madaymen - Namul-acan - Masala FMR, Kibungan | Road Improvement | 500,000.00 | 499,975.83 | NAIR Construction and Engineering | 20% PDF 2017 | 2019-03-04 | 2019-04-11 | Completed | |
Kibungan | Madaymen | Construction of Enrique Jose Elementary School Waterworks System, Madaymen | Waterworks system | 800,000.00 | 780,345.86 | Four Brothers | 20% PDF - 2017 | 2019-01-17 | 0000-00-00 | Completed | |
Bakun | Dalipey | Construction of Conacon Footbridge | Bridge | 200,000.00 | 199,501.75 | NAIR Construction & Engineering | 20% PDF CY 2017 20% PDF CY 2016 | 2018-01-31 | 2018-02-26 | Completed | 1) Construction of Conacon Footbridge (additional) - 20% PDF CY 2017 (Php 150,000.00)
2) Construction of Conacon Footbridge - 20% PDF CY 2016 (PhP 50,000.00)
3) Completed on February 19, 2018. |
Bakun | Kayapa | Improvement of Kayapa to Bulisay FMR | Roads | 2,000,000.00 | 1,989,002.44 | SRBA General Construction /Ray Angluben | 20% PDF 2018 | 2018-05-09 | 2018-07-18 | Completed | 98.92% accomplishment; completed with underrun |
Bakun | Poblacion | Tirepathing of Limosan-Tenging FMR | Roads | 500,000.00 | 491,624.18 | Pulicay Grandsons Construction | 20% PDF 2018 | 2018-05-09 | 2018-06-15 | Completed | 96.04% completed with underrun and liquidated damages. |
Tuba | Twin Peaks | Improvement of Bacaog-Bayating to Bawek FMR, Twin Peaks | Road | 750,000.00 | 737,823.64 | Sapdoy Enterprises | 20% PDF CY 2018 | 2018-07-09 | 2018-08-31 | Completed | Completed = 09/20/2018 Revised Target Date of Completion = 10/01/2018
1 suspension |
Mankayan | Tabio | Improvement of Baguingey to Piled Panad Road,Tabio,Mankayan,Benguet | Improvement of Road | 300,000.00 | 299,506.14 | Dipas Builders | 20% PDF - 2018 | 2018-09-28 | 2018-10-24 | Completed |
Completed on 10-23-18
|
Buguias | Abatan | Improvement of Halsema - Upper Nakiangan FMR,Abatan,Buguias,Benguet | | 500,000.00 | 487,603.27 | NAIR Construction | 20% PDF - 2018 | 2018-09-28 | 2018-11-04 | Completed | Completed with LD |
Buguias | Loo | Improvement of Loo-Panayaoan FMR, Loo, Buguias | Road improvement | 250,000.00 | 247,436.43 | MACGAT Construction | 20% PDF - 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Tuba | Camp 6 | Improvement of Pathway with Shed Leading to Lower Green Valley to Millsite,Camp 6,Tuba,Benguet | Improvement of pathway | 1,000,000.00 | 997,132.86 | Roben B. Runas Construction | 20% PDF - 2018 | 2018-08-28 | 2018-10-27 | Completed | 1 suspension |
Tuba | Poblacion | Rehabilitation of Badiwan Road | Const. of PCCP | 500,000.00 | 467,539.15 | Sapdoy Enterprises | 20% PDF - 2018 | 2018-07-09 | 2018-08-31 | Completed | Completed = 09/04/2018, Revised Target Date of Completion = 09/17/2018
2 Suspensions |
Kapangan | Taba-ao | Concreting of Cotocot-Abiang Foot Trail, Abiang, Taba-ao, Kapangan,Benguet | Concreting of Footpath | 250,000.00 | 238,270.67 | EBTITIWA General engineering and Construction Services | 20% PDF - 2018 | 2018-08-16 | 2018-09-07 | Completed | Completed on November 14, 2018 |
Bokod | Bila | Construction of Grouted Riprap along the area of rural Health Center (RHC) Bila,Bokod,Benguet | Grouted Riprap | 300,000.00 | 275,054.88 | SRBA General Construction | 20% PDF - 2018 | 2018-09-25 | 2018-10-27 | Completed | update as of January 2019 |
Buguias | Baculongan Sur | Improvement along Nakagang-Sayangan-Beleng-Paing,Baculungan Sur | Construction of PCCP | 1,000,000.00 | 989,354.11 | MACGAT Construction | 20% PDF - 2018 | 2018-07-06 | 2018-09-06 | Completed | Revised Target Date=08/12/2018. 1 Suspension
|
Kabayan | Ballay | Improvement of Ballay liang to taaw FMR | Retaining Wall,PCCP | 2,000,000.00 | 1,995,573.59 | Jamil Sean Construction | 20% PDF 2018 | 2018-10-15 | 2019-01-02 | Completed | |
La Trinidad | Puguis | Improvement of Access road at Buhaw, Puguis, La Trinidad | Construction of road | 1,000,000.00 | 969,628.96 | Akip Contruction | 20% PDF 2018 | 2018-10-22 | 2019-01-25 | Completed | 100% completed. |
Kabayan | Ballay | Improvement of Barangay Road at Tinaleb, Ballay, Kabayan, Benguet | Riprap road side | 500,000.00 | 498,901.56 | | 20% PDF | 0000-00-00 | 0000-00-00 | Completed | |
Mankayan | Balili | Rehabilitation of Water Works System, Balili E/S, Balili, Mankayan | Waterworks | 500,000.00 | 498,000.00 | Donato-Sakiwat Construction | 20% PDF - 2018 | 2018-10-10 | 2018-10-12 | Completed | Completed as programmed and usable. |
Bakun | Ampusongan | Improvement of Ampusongan to Nakanga Road | Road improvement | 1,000,000.00 | 975,251.70 | Pulicay Grandson's Construction | 20% PDF - 2018 | 2018-11-26 | 2019-01-09 | Completed | |
Buguias | Loo | Improvement of Nabellang (Nagutikan Section) | FMR Improvement | 1,500,000.00 | 975,000.00 | | 20% PDF 2018 | 2018-10-29 | 0000-00-00 | Completed | |
Bokod | Pito | Construction of Tire path | Construction of Tire Path | 500,000.00 | 499,315.21 | BLDY Engineering & Construction | 20% PDF 2018 | 2018-10-15 | 2019-01-02 | Completed | 1) 1 suspension
2) on going with 15% completion as of January 2019 |
Atok | Caliking | Construction of Barangay Health Station, Km. 24, Caliking | Building | 2,500,000.00 | 2,494,029.72 | Drichloui Construction | 20% PDF 2018 | 2019-12-17 | 2019-07-01 | Completed | |
Bakun | Gambang | Improvement of Liwang - Bolbolo FMR, Gambang | Roads | 1,000,000.00 | 998,842.86 | Drichloui Construction | 20% PDF 2018 | 2019-12-17 | 2019-03-12 | Completed | |
Kapangan | Cuba | Concreting of Bocao Foot Trail | Foot trail | 300,000.00 | 246,449.43 | CJ OLIVIA Construction | 20% PDF CY 2018 | 2019-01-07 | 2019-02-01 | Completed | Completed and usable, final inspection, March 8, 2019. |
La Trinidad | Wangal | Improvement of Access Road and Site Development of Bahay Pag-asa Center Wangal | Roads | 5,000,000.00 | 4,840,141.38 | SEJ Construction & Aggregate | 20% PDF 2018 | 2019-01-22 | 2019-09-12 | Completed | |
Tuba | Ansagan | Construction of Terterem Flood Control, Ansagan, Proper | Flood control | 1,200,000.00 | 1,197,007.12 | Reasons Construction | 20% PDF 2018 | 2019-01-17 | 2019-04-15 | Completed | |
Tuba | Tadiangan | Improvement of Gymnasium at Tadiangan, Tuba | Construction of Gym | 500,000.00 | 456,152.44 | Four Brothers Construction | 20% PDF 2018 | 2019-01-17 | 2019-02-27 | Completed | Completed and usable |
Buguias | Baculungan Sur | Construction of Obanga Drainage Canal (Bad-ayan - Obanga - Paing FMR) | Construction of Drainage Canal | 1,000,000.00 | 997,990.64 | JYP Construction | 20% PDF 2018 | 2018-09-27 | 2018-11-27 | Completed | |
Bokod | Pito | Construction Of Tirepath At Simbonan, Pito, Bokod, Benguet | Tirepath | 500,000.00 | 499,315.21 | BLDY Eng'g & Construction | 20% PDF 2018 | 2018-10-15 | 2018-11-20 | Completed | |
Buguias | Abatan | Improvement of Hospital Building and Annexes:Construction of Dental Room with Annexes,Construction of Gen. Expert Room,Abatan,Buguias | Building improvement | 1,800,000.00 | 1,796,551.23 | AIP Construction | 20% PDF-2018 | 2019-03-25 | 2019-05-14 | Completed | |
Itogon | Ampucao | Construction of footbridge at Sitio Limingaling | Footbridge | 2,000,000.00 | 1,995,102.84 | HGW=3 Eng'g & Construction | 20% PDF 2018 | 2019-03-01 | 2019-07-01 | Completed | Completed with underrun.
|
La Trinidad | Wangal | Construction of PCCP with Drainage Canal at Provincial Housing Project,Phase II,Wangal | PCCP Construction | 2,000,000.00 | 1,977,778.29 | Pulicay Grandson's Construction | 20% PDF-2018 | 2019-03-25 | 2019-07-12 | Completed | |
Mankayan | Guinaoang | Completion of Guinaoang Multi-purpose Hall,Guinaoang,Mankayan,Benguet | Building Completion | 1,000,000.00 | 997,631.54 | Malco Construction | 20% PDF - 2018 | 2019-03-26 | 2019-07-28 | Completed | |
La Trinidad | Ambiong | Construction of Concrete Perimeter Fence (Phase II) to Enclose the Ambiong Elementary School | Fence | 200,000.00 | | | 20% PDF CY 2017 | 2017-12-02 | 0000-00-00 | Completed | On-going with 85.08% accomplishment as of January 8, 2018 with liquidated damages. |
Tuba | Camp 6 | Improvement of pathway with shed leading to lower Green Valley to Millsite, Tuba Camp 6 | Pathway | 1,000,000.00 | 997,132.86 | Ruben Runas Construction | 20% PDF 2018 | 2018-08-28 | 2018-12-13 | Completed | Project Completed revised target date - 12/13/18 |
Sablan | Kamog | Improvement of Multi-Purpose Hall at Central Kamog, Sablan | Building Improvement | 1,200,000.00 | 1,198,899.34 | Guardian Construction | 20% PDF - 2018 | 2019-02-26 | 2019-06-22 | Completed | |
Kibungan | Madaymen | Construction of PCCP along Tagpaya-Matikid FMR, Madaymen, Kibungan | Road Pavement | 1,500,000.00 | 1,491,631.22 | Pulicay Grandson Construction | 20% PDF 2018 | 2018-11-26 | 2019-01-09 | Completed | Completed with LD & Under run |
Buguias | Amgaleyguey | Completion of Km. 73 Multi-Purpose Hall, Amgaleyguey | Building | 1,500,000.00 | 1,445,578.04 | Drichloui Construction | 20% PDF 2018 | 2019-06-07 | 2019-10-12 | Completed | |
Buguias | Baculungan Sur | Improvement along Bad-ayan - Manhuyuhuy Provincial Road | Roads | 5,000,000.00 | 4,996,085.79 | Drichloui Construction | 20% PDF - 2018 | 2019-01-17 | 2019-05-06 | Completed | Completed on June 24, 2019 with liquidated damages
|
Mankayan | Suyoc | Rehabilitation of Gueday Waterworks System, Suyoc, Mankayan | Waterworks | 800,000.00 | 797,192.20 | MALCO Construction | 20% PDF - 2018 | 2019-01-29 | 2019-03-19 | Completed | |
Tublay | Ambassador | Construction of Barangay Health Station at Ambassador, Tublay, Benguet | Construction of Building | | 2,232,705.96 | Elfer Construction and Enterprise | 20% PDF - 2018 | 2019-07-12 | 2019-10-31 | Completed | |
La Trinidad | Bineng | Improvement along La Trinidad - Capitol - Bineng Provincial road | Road | 5,000,000.00 | 4,612,561.80 | Sangin Gen. Construction | 20% PDF 2018 | 2019-03-27 | 2019-08-25 | Completed | - Completed as of October 4, 2019.
- 6 sections |
Kabayan | Gusaran | Construction of PCCP Along National Road JCT - Diboong - Bangao Provincial Road at Kabayan | Road | | 4,369,493.26 | Solonio Construction (Ritchie Solonio) | 20% PDF 2018 | 2019-01-31 | 2019-05-23 | Terminated | Terminated due to site problem.
Contract terminated as of June 28, 2019
|
Mankayan | Guinaoang | Slope Protection at Ambabag - Poy-oc FMR, Guinaoang, Mankayan, Benguet | Slope Protection | 1,000,000.00 | 997,631.54 | | 20% PDF 2018 | 0000-00-00 | 0000-00-00 | Completed | |
Buguias | Baculungan sur | Rehabilitation of Nakagang-Sayangan-Beleng-Paing-Obanga FMR | FMR rehabilitation | 600,000.00 | 594,854.19 | Macgat Construction | 20% PDF-2019 | 2019-01-27 | 2019-05-01 | Completed | |
Bakun | Gambang | Improvement of Sookan-Gambang Barangay Road, Gambang | Roads | 1,000,000.00 | 998,412.58 | Drichloui Construction | 20% PDF 2019 | 2019-06-07 | 2019-07-21 | Completed | Images taken on June 18, 2019 |
Buguias | Loo | Slope Protection and Improvement of Panayaoan - Loo Barangay Road | Roads | 1,000,000.00 | 996,764.96 | HGW=3 Engineering and Construction | 20% PDF 2019 | 2019-06-07 | 2019-07-15 | Completed | |
Buguias | Buyacaoan | Improvement of Bekes - Bayoyo FMR, Buyacaoan | Roads | 500,000.00 | 498,537.66 | Macgat Construction | 20% PDF 2019 | 2019-06-07 | 2019-07-05 | Completed | |
Buguias | Poblacion | Improvement of Posel-Demang FMR, Poblacion, Buguias | Roads | 500,000.00 | 498,916.90 | Macgat Construction | 20% PDF 2019 | 2019-06-07 | 2019-07-07 | Completed | |
Buguias | Poblacion | Improvement of Insalong-Padongay FMR | Roads | 1,000,000.00 | 989,597.04 | BTCJR Construction and Eng'g Services | 20% PDF 2019 | 0000-00-00 | 0000-00-00 | Completed | |
Buguias | Poblacion | Improvement of Sidel Balakbak-Nilawitan FMR | Roads | 500,000.00 | 489,262.33 | On Top Construction | 20% PDF 2019 | 2019-06-07 | 2019-07-04 | Completed | |
Bokod | Bobok-Bisal | Construction of Multi-purpose Gym at Bobok-Bisal,Bokod,Benguet | Gym Construction | 4,000,000.00 | 3,995,637.15 | Hillbrand Engineering | 20% PDF - 2019 | 2019-11-06 | 2019-09-26 | Completed | |
Itogon | Ampucao | Concreting of Lumbag Road,Ampucao,Itogon,Benguet | PCP | 500,000.00 | 448,738.09 | Queges Builders & Enterprise | 20% PDF - 2019 | 2019-06-11 | 2019-07-16 | Completed | |
Tuba | Camp 4 | Construction of Flood Control Along Bued Riverside,Camp 6,Tuba,Benguet | Flood Control | 2,400,000.00 | | 2,227,206.94 | 20% PDF - 2019 | 2019-06-27 | 2019-08-17 | Completed | |
Tublay | Ambassador | Construction of PCCP,Coroz-Tabeo-Sto. Nino E/S Extension,Ambassador,Tublay,Bengeut | Construction of PCCP | 2,000,000.00 | 1,994,961.86 | Tagel Construction | 20% PDF - 2019 | 2019-06-07 | 2019-08-14 | Completed | completed |
La Trinidad | Bahong | Rehabilitation along Bahong-Sadag Provincial Road | Roads | 1,000,000.00 | 873,983.67 | SEJ Construction | 20% PDF 2019 | 2019-06-07 | 2019-07-16 | Completed | |
La Trinidad | Shilan | Improvement along Km. 12 (Shilan) - Sagpawe Provincial Road | Road | 5,000,000.00 | 4,395,522.13 | SEJ Construction | 20% PDF 2019 | 2019-07-06 | 2019-09-12 | Completed | |
La Trinidad | Beckel | Improvement along Beckel - Balangbang Provincial Road | Road | 5,000,000.00 | 4,981,598.22 | Drichloui Construction (Roy M. Balay-odao) | 20% PDF 2019 | 2019-06-11 | 2019-11-09 | Completed | |
Atok | Cattubo | Improvement along Tulodan - Sayangan Provincial Road | Road | 5,000,000.00 | 4,974,491.08 | Efler Construction and Enterprise | 20% PDF 2019 | 2019-06-27 | 2020-10-15 | Completed | 1.) Suspension recommended effective June 27, 2019 pending the issuance of ECC;
2.) Actual date of completion: November 16, 2020.
|
Bakun | Kayapa | Construction of Box Culvert at Kayapa-Bulisay FMR, Kayapa, Bakun | | 1,200,000.00 | 1,189,781.43 | SRBA General Construction | 20% PDF 2019 | 2019-07-05 | 2019-08-21 | Completed | |
La Trinidad | Wangal | Ground Improvement and Completion of Indigenous Building | Building | 500,000.00 | 496,075.33 | On Top Construction | SB # 2 2020 | 2020-01-02 | 2020-02-12 | Completed | Project Engineer: Ceasar Wacay
Geotagged by: J G. C |
La Trinidad | Wangal | Repair of PEO Building, Wangal, La Trinidad, Benguet | Building Repair | 1,000,000.00 | 997,587.97 | LBJ Construction | 2018 20% PDF | 2020-01-10 | 2020-02-14 | Completed | Project Engineer: Porter B. Camsol
Geotagged by: Jeffrey G. Cabato |
La Trinidad | Wangal | Improvement of PEO Building/Extension Phase II (Planning ROW, Survey Section & Motor-pool Division | Building | 6,500,000.00 | 6,446,093.50 | LBJ Construction | GSO-2019 | 2020-01-10 | 2020-02-14 | Completed | Project Engineer: Porter B. Camsol
Geotagged by: JC |
Tublay | Caponga | Construction of Perimeter Fence at Palew ES | Perimeter Fence | | 500,000.00 | James Palangdan | 20% PDF 2017 | 2020-12-01 | 2020-10-10 | Completed | |
Tublay | Basil | Rehabilitation of Danis Water Works System, Basil Tublay | Water Works | 800,000.00 | 798,440.00 | FMCwarriors Construction | SB-No.1-2019 | 2020-01-09 | 2020-02-28 | Completed | |
La Trinidad | Wangal | Construction of Multi-purpose Building at Wangal | Building | 2,000,000.00 | 1,939,644.41 | JCA Construction anfd Engineering Services | 20% PDF CY 2016 General Fund CY 2015 | 2017-07-18 | 0000-00-00 | Temporarily suspended | Suspended effective July 18, 2017 due to site problem.
1 suspension.
Mutual Termination on process.
|
Kabayan | Eddet | a) Consruction of Daket-Oguban Footbridge, Eddet, Kabayan; b) Construction of Daket-Oguban Footbridge, Eddet (Additional) | Excavation, Structure Excavation, Reinforcing Steel, Structural Concrete | 1,764,000.00 | 1,743,340.17 | Random Builders | 20% PDF-2014 & SB # 02 - 2016 | 2018-03-08 | 2018-08-18 | Completed | |
La Trinidad | Tawang | Construction of Senior Citizen's Building at Barangay Tawang | Building | 1,600,000.00 | 1,589,777.37 | Leo Heirs Construction | 20% PDF CY 2015 , SB No. 2 CY 2015 CCO - 20% PDF | 2016-11-28 | 2017-04-17 | Completed | Based from the picture taken on May 18, 2018, the building is not yet physically completed. |
La Trinidad | Ambiong | Improvement of Gulon Road at Ambiong | Roads | 1,800,000.00 | 1,699,101.63 | Drichloui Construction | 20% PDF CY 2015, SB No. 5 CY 2015 | 2017-01-12 | 2017-04-10 | Completed | |
Tuba | Tadiangan | Concreting of Hydro 2-Absay Footpath at Tadiangan | | 460,000.00 | 458,565.68 | Roben Runas Construction | SB No. 05 & GF 2015 | 2017-01-24 | 2017-03-10 | Completed | Cluster "H" a) Control No. 08-16-00013 - Roben Runas Construction |
Bakun | Ampusongan | Construction of Multi-purpose Building (Additional) | Building | 4,500,000.00 | 4,496,765.54 | Reasons Construction | SB No. 5 CY 2015 & 20% PDF CY 2016 | 2017-02-15 | 2017-09-15 | Completed | Completed as per plan. |
Kabayan | Ballay | Improvement of Inuman WWS, Ballay | Waterworks system | 150,000.00 | 149,420.46 | Four Brothers | SB #2 - 2015 & 20%PDF-2016 | 2019-01-17 | 2019-02-08 | Completed | |
Kabayan | Pacso | Construction of Mangoto Day Care Center (Phase 1 and Phase 2) | Building | 1,050,000.00 | 1,047,897.62 | Bosongan Construction | 20% PDF CY 2015 SB No. 2 CY 2016 | 2017-08-31 | 2018-02-04 | Completed | Completed on February 25, 2018 |
Tuba | Tabaan Norte | a.) Construction of Parasipis Health Station (Phase II); b.)Construction of Barangay Health Station (Additional) Parasipis Tabaan Norte, Tuba | Building | 939,000.00 | 937,348.97 | Roben Runas Construction | 20% Project Development Fund - 2015 & SB #2 GF-2016 | 2017-01-26 | 2017-10-07 | Completed | |
Tublay | Ambongdolan | Construction of Sante Footbridge at Payay,Ambongdolan (Additional),Tublay,Benguet | construction of footbridge | 400,000.00 | 378,930.11 | Sandstream Construction | 20% PDF - 2017 | 2018-07-23 | 2018-09-03 | Completed | |
Itogon | Virac | Improvement along Provincial Road Construction of Diversion Road - Batuang Provincial Road | Roads | 873,000.00 | | ICO Construction | 20% PDF CY 2016, SB No. 2. CY 2016 GF | 2017-04-20 | 2017-05-22 | Completed | Completed on May 22, 2017
clustered
a) improvement along baguio - balatoc - itogon provincial road; b) const of diversion road - batuang prov'l road @ virac, itogon |
Bakun | Poblacion | Construction of Beyeng Barrio School | Building | 1,110,000.00 | 1,108,766.89 | Reasons Construction | 20% PDF CY 2016 SB No. 1 2017 | 2017-11-24 | 2018-02-21 | Completed | 1)Completed on February 20, 2018
2) 20% PDF CY 2016 (PhP 1,000,000.00) SB No. 1 CY, GF (PhP 110,000.00) |
Tuba | San Pascual | Establishment of Provincial organic swine and poultry farm, San Pascual, Tuba (Construction of Phase I-Storage Building for feeds, supplies and tools for organic / native swine demo farm) | Building | 400,000.00 | 399,750.85 | Ruben Runas Construction | 20% PDF 2016 & SB # 1 2017 | 2019-01-17 | 2019-03-17 | Completed | Completed (rough finishing) |
Kapangan | Balakbak | a) Fencing of Heritage Park Balakbak Elementary School, Kapangan; b) Fencing of Heritage Park Balakbak Elementary School, Kapangan - Additional | Fencing | 312,000.00 | 301,400.17 | Four Brothers Construction | 20% PDF 2017 & SB# 1 2017 | 2019-01-17 | 2019-02-05 | Completed | |
La Trinidad | Betag | Improvement of Benguet General Hospital Annex B Building | Improvement | 150,000.00 | 138,379.49 | ADL Construction | SB # 01 - 2017, 20% PDF | 2018-05-17 | 2018-05-23 | Completed | |
Buguias | Lengaoan | Construction of Gymnasium at Lengaoan - Waking Elementary School | Building | 5,000,000.00 | 4,996,492.54 | Almond Engineering and Construction | 20% PDF CY 2016 PSBF CY 2016 | 2016-09-13 | 2017-06-09 | Completed | Completed on June 9, 2017 |
Mankayan | Bulalacao | a) Construction of Sr. Citizen Building and b.) Construction of Sr. Citizen building additional, Bulalacao, Mankayan | Building | 900,000.00 | 894,627.07 | | SB No. 6 2015 and 20% PDF CY 2015 | 2017-12-01 | 2017-02-24 | Completed | Need additional funding for full completion |
Sablan | Bayabas | Construction of Multi-Purpose Building at Agri-Eco farm | Building | 2,000,000.00 | 1,996,397.92 | | SB No. 5 CY 2012 and SB No. 5 CY 2013 | 2017-04-24 | 2017-07-18 | Completed | Completed and usable |
Buguias | Loo | Construction of Taba-ao Waterworks System at Patpat | Waterworks System | 100,000.00 | 99,638.81 | | SB No. 2 CY 2014 | 2017-11-22 | 2017-12-18 | Completed | For post inspection |
Buguias | Abatan | Improvement of Buguias Federated Senior Citizen's Building Located at Abatan | Building Repair | 100,000.00 | 75,656.52 | Juricmarc Construction | SB No. 2 CY 2014 | 2018-03-22 | 2018-03-31 | Completed | |
Tuba | San Pascual | Construction of Piggery Building | Building | 1,600,000.00 | 1,460,043.43 | Queges Builders and Enterprise | 20% PDF 2014 | 2019-06-07 | 2019-10-01 | Terminated | Suspended due to site problem.
Terminated as of February 03, 2020.
|
Bakun | Sinacbat | Construction of Sinacbat Public Toilet with Shower Room | Building | 500,000.00 | 499,131.17 | FMC Warriors Construction | SB No. 4 CY 2015 | 2016-11-09 | 2017-01-26 | Completed | Completed as per plan. |
Buguias | Loo | Improvement of Lanas - Taba-ao - Nagutikan FMR | Roads | 150,000.00 | 149,663.94 | | SB No. 2 CY 2016 GF | 2017-11-22 | 2017-12-21 | Completed | Completed on December 21, 2017 |
Buguias | Catlubong | Construction of Bekes-Palakad Tirepath at Bekes-Palakad | Roads | 500,000.00 | 499,298.45 | Mel-Soc Construction | SB No. 5 CY 2015 | 2017-02-15 | 2017-04-14 | Completed | Revised target completion date on April 16, 2017. Deducted PhP 500.00 due to substandard billboard. |
Buguias | Buyacaoan | Cementing of Tirepath at Duntog | Roads | 300,000.00 | 298,864.29 | | SB No. 5 CY 2015 | 2017-11-22 | 2017-12-12 | Completed | Completed on December 12, 2017 |
Buguias | Amgaleyguey | Concrete Tirepathing of Dangwa FMR at Guiwe | Roads | 300,000.00 | 298,819.22 | | SB No. 5 CY 2015 GF | 2017-11-22 | 2017-12-15 | Completed | Completed on December 15, 2017 |
Bokod | Ekip | Improvement of Multi-Purpose Hall Pethal, Ekip, Bokod | Building Repair | 1,700,000.00 | 1,693,780.68 | Aroboan Construction | SB No. 5 CY 2015 | 2017-08-03 | 2017-12-26 | Completed | CLUSTERED b) Control No.: 01-15-00052 - Aroboan Construction
85.21% completed with LD |
Kabayan | Ballay | Construction of Multi-Purpose Building at Tinaleb | Building | 1,000,000.00 | 987,812.83 | | SB No. 5 CY 2015 | 2017-02-14 | 2017-06-19 | Completed | Completed and usable with liquidated damages |
Kabayan | Eddet | Construction of Eddet Waterworks System | Waterworks System | 1,000,000.00 | 971,114.35 | | SB No. 5 CY 2015 | 2017-02-03 | 2017-06-09 | Completed | Completed and usable with underrun and liquidated damages. |
Kabayan | Batan | Improvement of Batan FMR | Roads | 150,000.00 | 148,665.42 | 4 Brothers Construction | SB No. 5 CY 2015 | 2017-02-07 | 2017-03-04 | Completed | |
Kabayan | Poblacion | Improvement of Poblacion Barangay Hall | Building Repair | 1,000,000.00 | 998,467.63 | Akiki Builders | SB No. 5 CY 2015 | 2017-08-31 | 2018-02-06 | Completed | 90.00% Completed with liquidated damages - Total Cost Incurred PhP 898,621.05 as of March 2018; post-inspected on January 15, 2018 |
Kabayan | Bashoy | Improvement of Day Care Center, Pulag, Bashoy | Building Repair | 800,000.00 | 793,116.38 | Aroboan Construction | SB No. 5 CY 2015 | 2017-11-02 | 2017-11-24 | Completed | Completed on February 22, 2018 |
Kibungan | Madaymen | Construction of Masala Day Care Center, Madaymen, Kibungan | Building | 800,000.00 | 769,760.80 | | SB #2 CY 2015 | 2016-12-12 | 2017-02-24 | Completed | |
Kibungan | Tacadang | Construction of Litalit Footrail, Tacadang, Kibungan | Roads | 300,000.00 | 299,894.51 | | SB No. 5 CY 2015 | 2017-01-27 | 2017-06-19 | Completed | |
Itogon | Dalupirip | Improvement of Footrail at Sitio Tivang Pigingan, Dalupirip | Roads | 75,000.00 | 74,500.00 | jessie construction and services/ jessie palangdan | SB No.1 CY 2015 | 2016-12-14 | 2017-01-15 | Completed | Clausters
project construction of waiting shed at tenedy, itogon, benguet and improvement of foottrail at sitio tivang to mt. pigingan at dalupirip, itogon, benguet. |
Itogon | Ampucao | Establishment of Botanical Garden at Ampucao | Garden | 150,000.00 | 149,553.31 | MK Construction | SB No. 2 CY 2015 | 2017-07-06 | 2017-07-20 | Completed | cluster c: a) concreting of bito-pasiday fmr (phase II) in apmucao, itogon; b) establishment of botanical garden at ampucao, itogon |
Kapangan | Kapangan Central | Construction of Garage and Warehouse, KMCH, Kapangan, Benguet | Building | 1,000,000.00 | 958,435.44 | Balangcod Construction | SB No. 1 CY 2015 | 2017-12-05 | 2017-01-31 | Completed | |
Kapangan | Cuba | Construction of Multi-Purpose Building, Cuba, Kapangang, Benguet | Building | 500,000.00 | 499,330.024 | Balangcod Construction | SB No. 5 CY 2015 | 2017-10-31 | 2017-12-08 | Completed | |
La Trinidad | Poblacion | Improvement of Benguet Museum Building | Building improvement | 1,000,000.00 | 996,883.81 | Haight's Construction | SB No. 03 CY 2015 GF | 2017-12-01 | 2018-04-19 | Completed | 1) Completed March 21, 2018
2) This project was suspended on December 1, 2017 to January 17, 2018 |
Tublay | Ambongdolan | Construction of Footpath at Payay, Ambongdolan | Roads | 150,000.00 | 148,762.75 | Sangin Construction | SB No. 6 CY 2015 | 2018-03-26 | 2018-04-29 | Completed | |
La Trinidad | Beckel | Improvement of Barangay Road at Pagal | Roads | 150,000.00 | 149,457.32 | SEJ Construction | SB No. 5 CY 2015 GF | 2017-08-31 | 2017-09-15 | Completed | 75.43% Completed with under run. |
La Trinidad | Poblacion | Construction of MRF at Buyagan | Building | 200,000.00 | 199,443.75 | SEJ Construction | SB No. 5 CY 2015 GF | 2017-08-18 | 2017-09-27 | Completed | Input the accurate coordinates of the project |
La Trinidad | Betag | Improvement of Walkway at Benguet General Hospital | Building Repair | 500,000.00 | 499,797.53 | Balangcod Construction | SB No. 1 CY 2015 | 2017-10-06 | 2017-11-21 | Completed | |
La Trinidad | Betag | Improvement of Benguet General Hospital Building | Building Repair | 265,000.00 | 264,706.34 | Balangcod Construction | SB No. 1 CY 2015 | 2017-10-06 | 2017-11-16 | Completed | |
Mankayan | Bulalacao | Const'n of Ambingan-Cotcot Footpath, Bulalacao | Roads | 4,000,000.00 | 398,143.67 | | SB No. 5 CY 2015 | 2016-11-25 | 2017-01-04 | Completed | Need additional fund for fully completion |
Mankayan | Cabiten | Construction of Waiting Shed at Poked Las-igan, Cabiten, Mankayan | Building | 350,000.00 | 348.476.08 | Baldas Construction | SB No. 05 CY 2015 | 2017-01-23 | 2017-02-26 | Completed | Cluster "G" b) Control No. 03-15-00028 c) 02-16-000122 - Baldas Construction |
Mankayan | Guinaoang | Tirepathing (Phase I) at Lower Dowag, Guinaoang, Mankayan | Roads | 350,000.00 | 348,476.08 | Baldas Construction | SB No. 5 CY 2015 | 2017-01-23 | 2017-02-10 | Completed | Cluster "G" a) Control No. 03-15-00027 c) 02-16-000122 - Baldas Construction |
Sablan | Bagong | Cluster 'HH' Construction of Duban-Tufil Footpath at Bagong Sablan | Roads | 600,000.00 | 597,016.47 | Anas Construction | SB No. 5 CY 2015 | 2017-06-04 | 2017-06-27 | Completed | |
Sablan | Bayabas | Construction of Multi-Purpose Building at Bayabas | Building | 1,200,000.00 | 1,187,446.89 | Anas Construction | SB No. 5 CY 2015 | 2017-08-15 | 2017-12-29 | Completed | |
Sablan | Bayabas | Cluster "Q" a) Construction of Deepwell with Jet matic at Sitio Matal-og | Waterworks System | 217,798.41 | 212,122.54 | Sangin Construction | SB No. 3 CY 2015 | 2017-10-06 | 2017-11-08 | Completed | |
Bokod | Poblacion | Improvement of Mangagew FMR | Roads | 299,000.00 | | | SB No. 5 CY 2015 | 2016-06-24 | 2016-07-15 | Completed | |
Buguias | Catlubong | Wallayan-Abbatan Road Construction | | 1,000,000.00 | | | SB No. 5 CY 2015 | 2016-05-16 | 2016-07-12 | Completed | |
Sablan | Bayabas | Riprapping along Bekes - Talete FMR | Roadside | 300,000.00 | | | SB No. 5 CY 2015 GF | 2016-06-27 | 2016-07-26 | Completed | |
Sablan | Poblacion | Construction of Deepwell with Jetmatic (Phase I) Exploration at Matal-og | | 81,100.00 | | | SB No. 4 CY 2015 | 2016-07-06 | 2016-08-05 | Completed | |
Kabayan | Tawangan | Riprap of Lusod - Tawangan NHS Grounds at Tawangan | | 1,000,000.00 | | | SB No. 5 CY 2015 GF | 2016-04-12 | 2016-08-02 | Completed | Completed on July 18, 2016 |
Kapangan | Gaswiling | Completion of Barangay Health Station | Building | 200,000.00 (Initial appropriation) | | family circle construction/marcos luma-ang | SB No. 5 CY 2015, SB No. 5 CY 2015 General Fund | 2016-06-29 | 2016-07-28 | Completed | |
Mankayan | Balili | Construction of Road at Bila - Cabacab | Roads | 1,000,000.00 | | | SB No. 5 CY 2015 GF | 2016-06-27 | 2016-07-30 | Completed | Completed on June 30, 2016 |
Itogon | Tuding | Construction of Day Care Center (Phase II), Lucnab | Building | 990,000.00 | | Ico Construction Services/ Jerico A. Palangdan | SB No. 5 CY 2015 | 2016-03-28 | 2016-07-15 | Completed | |
Buguias | Abatan | Construction of Concrete Riprap along Gal-udan - Abatan Access Road | Road Side | 150,000.00 | 149,154.47 | Mel-Soc Construction | SB No. 5 CY 2015 | 2016-08-29 | 2016-09-15 | Completed | |
Tuba | Taloy Sur | Improvement of Poyopoy Elementary School Ground | Building | 1,000,000.00 | 998,513.80 | | SB No. 5 CY 2015 | 2016-06-30 | 2016-09-12 | Completed | Completed - September 3, 2016 |
Tublay | Ambassador | Installation of PVC Pipes for Sewerage System | Waterworks System | 230,000.00 | 228,665.67 | Hillstone Builders | SB No. 5 CY 2015 | 2016-09-07 | 2016-10-04 | Completed | Completed on September 29, 2016 |
Buguias | Loo | Puputak - Beka Road Construction | | 1,000,000.00 | 997,839.84 | | SB No. 5 CY 2015 | 2016-06-27 | 2016-08-04 | Completed | |
Kapangan | Labueg | Construction of Barangay Hall (Additional), Labueg | Building | 400,000.00 | 498,484.43 | Bolos Construction Engr. Edgar Baclawad | SB No. 5 CY 2015 | 2016-06-29 | 2016-08-18 | Completed | Completed on August 16, 2016 |
Kapangan | Labueg | Concreting of Canal along Longboy - Tacal FMR | Roads | 300,000.00 | 298,961.72 | Guardian Construction, Ruben Pacheco Jr. | SB No. 5 CY 2015 | 2016-07-06 | 2016-08-09 | Completed | Completed on August 9, 2016 |
Kapangan | Taba-ao | Concreting and Installation of handrails along Carel - Balete - Debeng Foot Trail at Daclan, Taba-ao | | 200,000.00 | 198,418.11 | Balangcod Construction/Fermin D. Balangcod | SB No. 5 CY 2015 | 2016-07-06 | 2016-08-06 | Completed | Completed on August 6, 2016 |
Mankayan | Sapid | Construction of Nursery Bridge at Sapid | | 1,500,000.00 | 1,497,965.32 | | SB No. 5 CY 2015 | 2016-04-18 | 2016-08-30 | Completed | Completed - August 15, 2016 |
Kapangan | Gadang | Cementing of Mangingeb to Bial Residence Footpath Trail, Namat-ican Gadang | Roads | 300,000.00 | 299,131.56 | Balangcod Construction | SB No. 5 CY 2015 | 2016-11-09 | 2016-12-13 | Completed | Completed on November 25, 2016 |
Kibungan | Poblacion | Construction of Kibungan Municipal Guest House Annex (Phase I) | Building | 1,000,000.00 | 999,317.17 | | SB No. 4 CY 2015 | 2016-02-22 | 2016-11-25 | Completed | Completed on November 14, 2016 |
Kabayan | Batan | Construction of Bajeng Waterworks System, Batan | Waterworks system | 200,000.00 | 199,203.85 | Four Brothers | SB #5 - 2015 | 2019-01-17 | 2019-02-22 | Completed | |
Bakun | Bagu | Improvement of Benggekan Road, Bagu | Roads | 500,000.00 | 498,656.58 | FMC Warriors Construction | SB No. 5 CY 2015 | 2016-08-26 | 2016-10-10 | Completed | Completed on October 10, 2016 |
Bokod | Ambuklao | Improvement of Ambuklao Elementary Stage | Building Repair | 200,000.00 | 199,822.92 | 4 Brothers Construction | SB No. 5 CY 2015 | 2016-09-07 | 2016-10-11 | Completed | Completed on October 6, 2016 (Backstage only) |
Kibungan | Sagpat | Construction of Flood Control at Sagpat | Road Side | 500,000.00 | 494,062.73 | Pulicay Grandsons Construction | SB No. 5 CY 2015 | 2018-02-09 | 2018-03-21 | Completed | Completed on March 21, 2018 |
Itogon | Ampucao | Construction of Basketball Court (Phase II) at Cruz | Building | 500,000.00 | 498,477.13 | Aljune Builders | SB No. 5 CY 2015, General Fund (Non Office) | 2018-02-01 | 2018-03-06 | Completed | Completed on March 6, 2018 |
Kapangan | Cayapes | Widening and Improvement of FMR from Barangay Central (Sagubo Junction) to Cayapes | Improvement of road | 900,000.00 | 889,477.12 | Family Circle Construction | SB # 5 2015 | 2019-01-31 | 2019-04-03 | Completed | |
Tuba | Tadiangan | Construction of Marville Daycare Center, Tadiangan, Tuba | Construction of Building | 1,000,000.00 | 998,356.35 | ANAS Construction | SB # 05 - 2015 | 2019-03-01 | 2019-06-13 | Completed | |
Tuba | Camp 6 | a.)Construction of Footbridge at Riverside, Camp 6, Tuba; b.)Construction of Footbridge at Riverside, Camp 6, Tuba (additional), Camp6, Tuba, Benguet | Footbridge | | 364,073.42 | Juricmarc Construction | a.)SB#05CY2015 b.)SB#012017 | 2018-09-24 | 2018-11-11 | Temporarily suspended | Suspended as of September 24, 2018.
1 suspension |
Atok | Abiang | Improvement of Banangan-Lower Abiang FMR | Roads | 750,000.00 | 747,848.77 | RNAA Builders | SB No. 2 CY 2016 | 2017-05-30 | 2017-07-14 | Completed | |
Bakun | Sinacbat | Construction of Footpath at Sinacbat to Bolibo | Roads | 150,000.00 | 149,678.48 | NAIR Construction & Engineering | SB No. 2 CY 2016 | 2017-07-13 | 2017-08-01 | Completed | Completed as per plan. |
Bakun | Sinacbat | Construction of Galvanized Water Tank at Bakun National High School - Extension | Waterworks System | 50,000.00 | 49,475.73 | Sandstream Construction | SB No. 2 CY 2016 | 2017-06-07 | 2017-06-20 | Completed | Completed as per plan. |
Itogon | Loakan | Construction of waterworks system of purok II, Barangay Loakan | Waterworks System | 500,000.00 | 469,564.76 | | SB No. 2 CY 2016 | 2017-01-20 | 2017-03-07 | Completed | |
Bakun | Poblacion | Construction of School Gymnasium | Building | 5,000,000.00 | 4,994,877.86 | Reasons Construction | SB No. 2 CY 2016 | 2016-12-04 | 2017-06-25 | Completed | Completed as per plan. |
Bakun | Gambang | Construction of Kil-ingan Communal Forrest Nursery at Yago | Building | 200,000.00 | 199,830.67 | Sandstream Construction | SB No. 2 CY 2016 | 2017-11-03 | 2017-11-30 | Completed | Completed with underrun. |
Bakun | Gambang | Improvement of Waterworks System at Cagam-is | Waterworks System | 300,000.00 | 299,618.13 | Sandstream Construction | SB No. 2 CY 2016 | 2017-10-10 | 2017-11-09 | Terminated | |
Buguias | Sebang | Repair of Alapang - Lengaoan Footbridge | Bridge | 300,000.00 | 298,961.49 | On Top Construction | SB No. 2 CY 2016 GF | 2017-01-27 | 2017-03-06 | Completed | Completed on March 6, 2017 |
Mankayan | Sapid | Improvement of Sapid - Pacda FMR | Roads | 2,000,000.00 | 1,950,000.00 | | SB No. 2 CY 2016 & 20% PDF CY 2016 | 2017-01-12 | 2017-05-03 | Completed | Need additional fund |
Mankayan | Taneg | Taneg Road Opening, Baayan, Sabian, Mankayan | Roads | 500,000.00 | 498,379.76 | Eugao Construction | SB No. 2 CY 2016 GF | 2017-07-13 | 2017-08-19 | Completed | |
Buguias | Sebang | Improvement of Pasbol - Ibisan in Sebang | Roads | 300,000.00 | 298,492.57 | SEJ Construction | SB No. 2 CY 2016 | 2017-02-21 | 2017-03-07 | Completed | Completed on March 7, 2017 |
Buguias | Catlubong | Improvement of Ponopon - Lusab FMR (Additional) | Roads | 500,000.00 | 498,422.34 | SEJ Construction | SB No. 2 CY 2016 | 2017-02-20 | 2017-03-20 | Completed | Completed on March 20, 2017 |
Buguias | Poblacion | Improvement of Padang - Naytoyab FMR | Roads | 2,000,000.00 | 1,996,610.78 | | SB No. 2 CY 2016 | 2017-02-06 | 2017-03-18 | Completed | Completed on March 18, 2017 |
Buguias | Baculongan Norte | Road Improvement at Pugo - Yuko-an Section | Roads | 800,000.00 | 797,766.47 | On Top Construction | SB No. 2 CY 2016 | 2017-02-22 | 2017-03-28 | Completed | Completed on March 28, 2017 |
Buguias | Poblacion | Construction of Pavement at Bolo - Tocdo - FMR at Poblacion | Roads | 1,000,000.00 | 998,367.80 | | SB No. 2 CY 2016 | 2017-02-06 | 2017-03-15 | Completed | |
Buguias | Catlubong | Improvement of Mansoysoy - Ambanglo FMR | Roads | 1,000,000.00 | 983,659.40 | | SB No. 2 CY 2016 | 2017-02-08 | 2017-05-05 | Completed | Project Completed with underrun and Liquidated Damages |
Buguias | Baculongan Norte | Improvement along Puo - Apunan - Ketang FMR | Roads | 500,000.00 | 498,409.27 | On Top Construction | SB No. 2 CY 2016 | 2017-08-15 | 2017-09-22 | Completed | Completed on September 22, 2017 |
Buguias | Amgaleyguey | Construction of Tirepath Junction Polis - Akiki FMR | Roads | 500,000.00 | 498,356.70 | On Top Construction | SB No. 2 CY 2016 | 2017-07-13 | 2017-08-07 | Completed | Completed on August 7, 2017 |
Buguias | Amgaleyguey | Construction of Basketball Court at Sagandoy Elementary School (Phase 2) | Building | 250,000.00 | 249,375.79 | On Top Construction | SB No. 2 CY 2016 | 2017-07-13 | 2017-08-16 | Completed | Completed on August 16, 2017 with liquidated damages |
Buguias | Loo | Construction of Balakbak - Magubgubang Flood Control at Pusong | Road Side | 500,000.00 | 497,261.70 | | SB No. 2 CY 2016 | 2017-08-15 | 2017-09-22 | Completed | Completed on September 22, 2017 |
Buguias | Bangao | Road Improvement at Macascasa | Roads | 500,000.00 | 498,779.85 | | SB No. 2 CY 2016 | 2017-08-15 | 2017-09-26 | Completed | Completed on September 26, 2017. |
Buguias | Bangao | Construction of Pavement at Amdodon FMR, Tinapan Section | Roads | 300,000.00 | 298,871.62 | | SB No. 2 CY 2016 | 2017-08-15 | 2017-09-26 | Completed | Completed on September 26, 2017. |
Buguias | Calamagan | Tirepathing at Palonsay | Roads | 400,000.00 | 398,762.11 | | SB No. 2 CY 2016 | 2017-08-16 | 2017-09-12 | Completed | Completed on September 12, 2017 |
Buguias | Calamagan | Construction of Comfort Room for Calamagan Elementary School | Building | 400,000.00 | 398,656.11 | | SB No. 2 CY 2016 | 2017-08-16 | 2017-09-25 | Completed | Revised project completion date to September 25, 2017 |
Buguias | Sebang | Improvement of Panig-an - Butiki - Tamangan FMR | Roads | 500,000.00 | 497,738.63 | On Top Construction | SB No. 2 CY 2016 | 2017-08-15 | 2017-09-09 | Completed | Completed on September 9, 2017
Clustered E1 Project, a)imp of panig-an - butiki - tamangan FMR, Buguis (Add'l) @ Sebang, Buguias, Benguet |
Buguias | Amlimay | Improvement of Dagway - Toplac Waterworks System | Waterworks System | 300,000.00 | 298,846.30 | On Top Construction | SB No. 2 CY 2016 | 2017-11-22 | 2017-12-30 | Completed | Completed on December 30, 2017 |
Buguias | Poblacion | Construction of Kiosk at Poblacion | Building | 50,000.00 | 49,895.65 | On Top Construction | SB No. 2 CY 2016 | 2017-11-22 | 2017-12-13 | Completed | Completed on December 13, 2017 |
Buguias | Poblacion | Improvement of Sabyatan - Tocdo - Nilawitan FMR | Roads | 1,000,000.00 | 998,880.18 | ICO Construction | SB No. 2 CY 2016 | 2017-11-22 | 2018-02-21 | Completed | Completed on January 21, 2018 |
Buguias | Bangao | Road Improvement at Camanggaan, Natugtugan | Roads | 500,000.00 | 994,871.00 | ICO Construction | SB No. 2 CY 2016 GF | 2017-11-22 | 2018-03-05 | Completed | Completed on February 26, 2018 |
Buguias | Baculongan Norte | Ground Improvement of Bano-oy Elementary School | School Grounds | 500,000.00 | 499,681.84 | | SB No. 2 CY 2016 | 2017-11-22 | 2017-12-30 | Completed | Completed - December 30, 2017 For post inspection |
Buguias | Buyacaoan | Improvement of Day Care Center at Magmagaling | Improvement of Daycare Center | 450,000.00 | 447,602.69 | On Top Construction | SB # 2 - 2016 | 2018-04-13 | 2018-07-18 | Completed | |
Buguias | Poblacion | Construction of 2 Classroom Building for Enggay - Willie Primary School | Building | 1,900,000.00 | 1,897,574.88 | HGW=3 Engineering & Construction | SB No. 2 CY 2016 PSBF | 2017-10-26 | 2018-04-12 | Completed | 1) Revised target completion date April 12, 2018 |
Buguias | Buyacaoan | Improvement of Day Care Center at Magmagaling | Improvement of Daycare Center | 450,000.00 | 447,602.69 | On Top Construction | SB # 2 - 2016 | 2019-04-13 | 2019-07-18 | Completed | |
Buguias | Catlubong | Construction of Waiting shed at Padang - Palakad | Construction of waiting shed | 450,000.00 | 447,602.69 | On Top Construction | SB # 2 - 2016 | 2018-04-13 | 2018-07-18 | Completed | |
Kabayan | Ballay | Improvement of Unnoy - Taaw FMR | Roads | 1,000,000.00 | 998,412.97 | | SB No. 2 CY 2016 | 2017-02-08 | 2017-04-19 | Completed | |
Kabayan | Tawangan | Improvement of Lusod - Tawangan National High School Road at Tawangan | Roads | 400,000.00 | 398,896.13 | Jamil Sean Construction | SB No. 2 CY 2016 | 2017-03-01 | 2017-03-23 | Completed | |
Kabayan | Batan | Rehabilitation of Penged Waterworks System | Waterworks System | 500,000.00 | 498,463.25 | Sangin General Construction | SB No. 2 CY 2016 | 2017-02-01 | 2017-03-09 | Completed | Completed and usable with liquidated damages |
Kabayan | Ballay | Improvement of Bagto - Akikian FMR at Ballay | Roads | 300,000.00 | 299,755.22 | Jamil Sean Construction | SB No. 2 CY 2016 | 2017-06-29 | 2017-07-24 | Completed | |
Kabayan | Ballay | Construction of Riprap along Taaw FMR at Ballay | Road Side | 200,000.00 | 199,272.27 | Jamil Sean Construction | SB No. 2 CY 2016 | 2017-06-29 | 2017-07-24 | Completed | |
Kabayan | Ballay | Construction of Riprap along Tinaleb FMR at Ballay | Road Side | 500,000.00 | 498,925.57 | Jamil Sean Construction | SB No. 2 CY 2016 | 2017-06-29 | 2017-07-24 | Completed | |
Kabayan | Gusaran | Improvement of Road at Bangao - Gusaran | Roads | 500,000.00 | 498,012.50 | Solonio Construction | SB No. 2 CY 2016 | 2017-01-24 | 2017-02-15 | Completed | |
Kabayan | Gusaran | Construction of Footpath at Tekeng - Mogaben, Gusaran, Kabayan | Roads | 250,000.00 | 249,293.80 | Akiki Builders | SB No. 2 CY 2016 | 2017-10-17 | 2017-11-23 | Completed | 95.00% Completed with liquidated damages - Total Cost Incurred PhP 236,829.11 as of March 2018; Post-inspected on January 5, 2018 |
Kabayan | Gusaran | Construction of Footpath at Naysuyoc | Roads | 250,000.00 | 248,894.33 | Akiki Builders | SB No. 2 CY 2016 | 2017-10-17 | 2017-11-26 | Completed | |
Kabayan | Adaoay | Concreting of Pathway along Adaoay National High School, Binado | Road Side | 300,000.00 | 299,277.47 | Akiki Builders | SB No. 2 CY 2016 | 2017-10-17 | 2017-11-24 | Completed | |
Kabayan | Lusod | Construction of Community Public Comfort Rooms at Proper Lusod | Building | 300,000.00 | 299,001.44 | | SB No. 2 CY 2016 | 2017-08-18 | 2017-10-15 | Completed | |
Kabayan | Tawangan | Improvement of Lubban - Hahagod FMR | Roads | 200,000.00 | 195,916.00 | | SB No. 3 CY 2016 | 2017-11-22 | 2017-12-09 | Completed | |
Kabayan | Adaoay | Extension of COMPAC at Adaoay | Building Repair | 500,000.00 | 490,331.90 | | SB No. 4 CY 2016 | 2017-11-22 | 2018-02-10 | Completed | |
Kapangan | Beling-Belis | Completion of Day Care Center Beling-Belis | Building | 500,000.00 | 496,905.80 | Balangcod Construction, Fermin Balangcod | SB No. 2 CY 2016 | 2016-12-05 | 2017-02-17 | Completed | Completed as planned |
Kapangan | Labueg | Improvement of Longboy-Tacal Road in Labueg, Kapangan, Benguet | Roads | 700,000.00 | 683,463.85 | RNAA Builders | SB No. 2 CY 2016 | 2017-05-30 | 2017-07-19 | Completed | |
Kapangan | Cayapes | Construction of Footbridge, Pilo, Cayapes | Bridge | 300,000.00 | 299,270.77 | Balangcod Construction | SB No. 2 CY 2016 | 2017-10-31 | 2017-12-05 | Completed | Contract under cluster e: a) const of footbridge at pilo, cayapes, kapangan; b) const of multi-purpose building at cuba kapangan (add'l) |
Kibungan | Sagpat | Construction of Senior Citizen Building, Sagpat, Kibungan | Building | 1,200,000.00 | 1,157,715.09 | RNAA Builders | SB No. 2 CY 2016 | 2017-12-01 | 2018-05-09 | Completed | 1) Duration-158.20 Calendar Days
2) 100.00% Completed - Total Cost Incurred PhP 1,157,715.09 as of May 2018 |
Kibungan | Tacadang | Rehabilitation of Pingew Footbridge | Bridge | 350,000.00 | 348,997.60 | Akip Construction and Enterprise | SB No. 2 CY 2016 | 2017-02-07 | 2017-04-28 | Completed | |
Itogon | Ampucao | Slope protection-Sinco, Ampucao | Road Side | 1,000,000.00 | 995,765.87 | MK Construction | SB No. 2 CY 2016 | 2017-08-10 | 2017-10-06 | Completed | |
Itogon | Ampucao | Concreting of Bito-Pasiday FMR (Phase II) | Roads | 250,000.00 | 248,984.80 | MK Construction | SB No. 2 CY 2016 | 2017-07-06 | 2017-07-16 | Completed | contract under cluster c: a) concreting of bito-pasiday fmr (phase II) in apmucao, itogon; b) establishment of botanical garden at ampucao, itogon |
Itogon | Loacan | Construction of footpath with railings at Anteg-in | Road Side | 200,000.00 | 198,042.52 | BEMADA Construction | SB No. 2 CY GF | 2017-11-30 | 2018-01-07 | Completed | Completed on January 5, 2018
contract under cluster c: c) const of footpath with railings at anteg-in, loacan, itogon |
La Trinidad | Puguis | Improvement of Bato - Longlong FMR | Roads | 1,000,000.00 | 998,407.36 | RNAA builders Roy K. Kepes | SB No. 2 CY 2016 | 2017-02-07 | 2017-04-10 | Completed | |
La Trinidad | Tawang | Improvement of Tawang Viewdeck | Building Repair | 300,000.00 | 298,685.78 | Universal De Leon Construction and Aggregates | SB No. 2 CY 2016 | 2017-02-14 | 2017-04-14 | Completed | Writing were found on the viewdeck |
La Trinidad | Wangal | Improvement of Cosaran Barangay Road | Roads | 300,000.00 | 298,985.83 | Universal De Leon Construction and Aggregates | SB No. 2 CY 2016 | 2017-02-14 | 2017-03-15 | Completed | |
La Trinidad | Puguis | Improvement of Guadayan Road | Roads | 1,200,000.00 | 1,197,228.88 | RNAA Builders | SB No. 2 CY 2016 | 2017-08-24 | 2017-10-24 | Completed | |
La Trinidad | Ambiong | Construction of Perimeter Fence of Ambiong Elementary School | Fence | 200,000.00 | 194,660.84 | Universal De Leon Construction and Aggregates | SB No. 2 CY 2016 | 2017-07-10 | 2017-08-14 | Completed | Completed with liquidated damages |
La Trinidad | Tawang | Improvement of Cruz - Tawang Road | Roads | 500,000.00 | 498,997.47 | Universal De Leon Construction and Aggregates | SB No. 2 CY 2016 | 2017-08-26 | 2017-09-18 | Completed | |
La Trinidad | Poblacion | Concreting of Road at Upper Buyagan (Additional) | Roads | 500,000.00 | 498,946.39 | Universal De Leon Construction and Aggregates | SB No. 2 CY 2016 | 2017-07-10 | 2017-08-30 | Completed | |
La Trinidad | Tawang | Improvement of Road from Barangay Hall to Cemetery | Roads | 500,000.00 | 498,200.82 | | SB No. 2 CY 2016 | 2017-01-24 | 2017-05-04 | Completed | |
La Trinidad | Balili | Construction of Flood Control and Pathway Railings at Bell Church Creek | | 1,200,000.00 | | Leo Heirs Construction, Emmanuel Leo | SB No. 2 CY 2016 | 2017-02-06 | 2017-04-30 | Completed | Completed as planned |
La Trinidad | Balili | Construction of Sidewalk - Central Balili - PAGASA | Road Side | 500,000.00 | 497,039.51 | Leo Heirs Construction, Emmanuel Leo | SB No. 2 CY 2016 | 2017-02-08 | 2017-03-12 | Completed | Input the accurate coordinates of the project |
La Trinidad | Beckel | Construction of Senior Citizen's Building (Phase II) | Building | 800,000.00 | 798,088.41 | ICO Construction | SB No. 5 CY 2015, GF | 2017-11-22 | 2018-02-13 | Completed | 1) Completed
2) Suspended January 31, 2018 - March 21, 2018
3) Revised target date of completion = April 2, 2018 |
La Trinidad | Poblacion | Completion of Fencing Jail Perimeter at PGO Jail | Fence | 200,000.00 | 198,259.06 | | SB No. 2 CY 2016 | 2017-01-24 | 2017-03-30 | Completed | |
La Trinidad | Poblacion | Improvement of School Ground at La Trinidad Central School | School Grounds | 400,000.00 | 397,079.36 | RNAA builders, Roy k. Kepes | SB No. 2 CY 2016 | 2017-01-20 | 2017-02-16 | Completed | |
La Trinidad | Poblacion | Construction of Concrete Pavement at Bato, Puguis | Roads | 200,000.00 | 198,870.15 | RNAA builders, Roy k. Kepes | SB No. 2 CY 2016 | 2017-01-30 | 2017-02-13 | Completed | Clusters: a)imp of school ground, La Trinidad Central School, Pob, LTB; b)const of concrete pavement @ Bato, Puguis, LTB |
Mankayan | Suyoc | Construction of Grouted Riprap along Pacda Barangay Road, Suyoc | Road Side | 200,000.00 | 198,429.25 | Eugao Construction | SB No. 2 CY 2016 GF | 2017-07-13 | 2017-08-13 | Completed | |
Sablan | Bagong | Cluster "HH" a.) Construction of Footpath at Cayapes, Bagong, Sablan | Roads | 600,000.00 | 597,016.47 | Anas Construction | SB No. 2 CY 2016 | 2017-06-04 | 2017-07-20 | Completed | |
Sablan | Kamog | Cluster 'HH' b.) Riprapping and Construction of Pavement Along Lower Tenekey FMR in Kamog, Sablan | Roads | 600,000.00 | 597,016.47 | Anas Construction | SB No. 2 CY 2016 | 2017-06-04 | 2017-07-03 | Completed | |
Sablan | Kamog | Construction of Walkway Shade in Sablan NHS | Road Side | 100,000.00 | 99,320.61 | Sangin Construction | SB No. 2 CY 2016 | 2018-01-12 | 2018-02-01 | Completed | |
La Trinidad | Betag | Improvement of CT Scan Building (Electrical Cabling) | Building Repair | 1,200,000.00 | 1,067,000.00 | | SB No. 1 CY 2016 | 2016-07-22 | 2016-10-23 | Completed | |
La Trinidad | Shilan | Construction of FMR Connet Shilan | FMR Pavement | 500,000.00 | 446,044.31 | SEJ Construction and Aggregate | SB # 2 - 2016, GF | 2018-02-07 | 2018-03-13 | Completed | |
Bakun | Poblacion | Construction of Senior Citizen's Multi-Purpose Building, Poblacion Bakun | Building | 1,000,000.00 | 979,019.15 | Pulicay Grandsons Construction | SB No. 2 CY 2016 | 2018-01-17 | 2018-04-23 | Completed | |
La Trinidad | Puguis | Improvement of Access Road in Puguis La Trinidad (DSWD Lingap Center to Veterans Building Area) | Roads | 500,000.00 | 442,703.38 | RNAA Builders | SB No. 2, CY 2016, GF-Non Office | 2018-03-07 | 2018-04-09 | Completed | Completed on March 30, 2018 |
Buguias | Abatan | Improvement of Halsema - Nakiangan Barangay Road, Abatan, Buguias, Benguet | Roads | 500,000.00 | 499,508.65 | Cliff Construction | 20% PDF CY 2017 | 2018-03-22 | 2018-04-26 | Completed | |
Bakun | Poblacion | Improvement of Bagiw Foottrail Phase I | Roads | 300,000.00 | 294,988.55 | Pulicay Grandsons Construction | SB No. 2 CY 2016 | 2018-01-31 | 2018-03-17 | Completed | Completed on March 17, 2018 with underrun |
Buguias | Poblacion | Improvement of the School Ground of Buguias Central School in Poblacion, Buguias, Benguet | Building Repair | 500,000.00 | 498,469.92 | SEJ Construction | SB No. 3 CY 2016 | 2017-02-13 | 2017-04-10 | Completed | |
Buguias | Abatan | Improvement of Hospital Building, NBDH Bekes | Improvement of hospital | 800,000.00 | 798,801.50 | AIP Construction | SB No. 2 CY 2016 | 2018-01-15 | 2018-03-18 | Completed | 1) 1 Suspension
2) Revised Target Date of Completion is on November 11, 2018
3) Completed, 2nd Revised Target Date of Completion = 11/11/2018
|
Buguias | Baculongan Sur | Construction of Tirepath at Kelong Section along Balintag-Palintaang FMR | Roads | 200,000.00 | 193,245.90 | Macgat Construction | SB No. 2 CY 2016 GF | 2018-02-01 | 2018-02-24 | Completed | Completed on February 20, 2018 |
Kabayan | Tawangan | a) Improvement of Kapalan FMR at Tawangan b) Improvement of Nanhabitan - Kapalan Extension FMR | Roads | 1,000,000.00 | 984,315.96 | Jamil Sean Construction | SB No. 2 CY 2016 | 2018-05-29 | 2018-07-24 | Completed | Completed: 07/08/2018
Revised target date of completion: per suspension order no. 1 is on 07/24/2018 |
Kapangan | Kapangan Central | Construction of Barangay Hall, Central Kapangan | Building | 1,500,000.00 | 1,391,622.12 | Balangcod Construction | SB No. 2 CY 2016 | 2018-01-18 | 2018-05-04 | Completed | |
La Trinidad | Beckel | Road Improvement - Sapsing and Beckel (Phase II) | Construction of PCCP and drainage canal | 500,000.00 | 498,933.68 | SEJ Construction and Aggregates | SB No. 2 CY 2016 | 2017-08-18 | 0000-00-00 | Temporarily suspended | 1) Suspended Aug. 18, 2017; The Barangay officials and end users had requested for the mutual termination of this project to pave way for the preparation of a new program of work.
2) Update as of June 2018 |
Mankayan | Bulalacao | Construction of Flood Control at Lower Demang, Bulalacao | Road Side | 100,000.00 | 99,443.71 | Sharamelle Construction and General Engineering | SB No. 2 CY 2016 | 2018-02-12 | 2018-02-27 | Completed | Completed on February 26, 2018 |
Mankayan | Bulalacao | Improvement along Gawaan - Akmet Road, Bulalacao | Roads | 500,000.00 | 497,429.26 | Eugao Construction | SB No. 2 CY 2016 | 2018-02-07 | 2018-03-20 | Completed | Completed on March 20, 2018 |
Mankayan | Colalo | Concreting of Busan Pathway, Busan, Colalo | Roads | 200,000.00 | 199,401.88 | Dipas Builders | SB No. 2 CY 2016 | 2018-02-16 | 2018-03-20 | Completed | Completed on March 20, 2018 |
Tuba | Camp 4 | Road Opening and Construction of Grouted Riprap Retaining Wall at Lalab, Camp 4, Tuba,Benguet | Road Opening and Construction of Grouted Riprap Retaining Wall | 700,000.00 | 663,590.25 | Sapdoy Enterprise | SB # 3 - 2016 | 2018-11-19 | 2019-04-11 | Completed | 1 suspension |
Sablan | Balluay | Improvement of Talwan - Peril FMR | Roads | 800,000.00 | 799,495.18 | Guardian Construction | 20% PDF CY 2016 | 2019-03-13 | 2019-04-28 | Completed | Ongoing, 70% completed |
Bakun | Poblacion | Improvement of Bagiw Footbridge | Bridge | 280,000.00 | 279,601.60 | Pulicay Grandsons Construction | SB No. 1 CY 2017 | 2017-11-29 | 2018-02-22 | Completed | 1) Cluster "G" Pulicay Grandsons Construction
2) Completed on February 22, 2018. |
Bakun | Poblacion | Improvement of Bagiw Foottrail | Roads | 500,000.00 | 466,458.38 | Pulicay Grandsons Construction | SB No. 1 CY 2017 | 2017-11-29 | 2018-02-22 | Completed | 1) Cluster "G" Pulicay Grandsons Construction
2) Completed on February 6, 2018 |
La Trinidad | Betag | Improvement of Betag Road (Passing by INC Church) | Roads | 2,000,000.00 | 1,997,181.97 | Buganheirs Engineering Construction | SB No.1 CY 2017 GF | 2017-12-01 | 0000-00-00 | Completed | Completed on June 26, 2018 |
Sablan | Banangan | Completion of Oriyao Footpath | Roads | 700,000.00 | 698,695.80 | Anas Construction | SB No. 1 CY 2017 | 2017-12-01 | 2018-02-03 | Completed | Completed on February 2, 2018 |
La Trinidad | Wangal | Construction of Corridor and Upper Bleachers for the Multi-Purpose Gym at Benguet Sports Center | Building Repair | 416,000.00 | 414, 225.50 | RNAA Builders | SB No. 1 CY 2017 | 2018-02-09 | 2018-03-03 | Completed | Completed on February 23, 2018 |
La Trinidad | Wangal | Construction of Guard House (Benguet PAG-ASA Center) | Building | 500,000.00 | 498,869.28 | Random Builders | SB No. 1 CY 2017 | 2018-02-20 | 2018-05-01 | Completed | 16.55% Completed - Total Cost Incurred PhP 82,562.87as of February 2018 |
Bokod | Karao | Improvement of Poblacion to Karao FMR Located at Karao | Roads | 1,500,000.00 | 1,444,887.92 | Summerlin Construction | SB No. 1 CY 2017 | 2018-03-06 | 2018-05-05 | Completed | Completed with revised target completion date of May 20, 2018 |
Bokod | Karao | Improvement of Boligueng Turning Point, Karao Road | PCCP & Slope Protection | 1,500,000.00 | 1,444,394.44 | Summerlin Construction | SB No. 1 CY 2017 | 2018-03-06 | 2018-05-08 | Completed | 1) Suspended as of March 6, 2018 and resumed on April 18, 2018;
2) Suspended again on July 16, 2018;
3) Resumed on November 7 ;
4) Completed w/ LD;
|
Mankayan | Colalo | Construction of Quarantine Checkpoint at Colalo, Mankayan, Benguet | Building | 550,000.00 | 544,195.35 | EUGAO Construction | SB No. 2 2017 | 2018-05-17 | 2018-07-21 | Completed | |
Kabayan | Ballay | Ground Levelling and Construction of Retaining Wall at Ballay Elementary School Coumpound | construction of retaining wall | 1,000,000.00 | 947,269.92 | Jamil Sean Construction | SB # 1 2017 | 2019-01-17 | 2019-02-28 | Completed | |
Bokod | Ekip | Construction of Comfort Rooms, Bokod National High School, Poodan, Ekip, Bokod | Building | 1,000,000.00 | 997,519.22 | Hillbrand Engineering | SB No. 1 CY 2017 | 2018-03-07 | 2018-07-28 | Temporarily suspended | 2 suspensions
Suspended as of March 6, 2018;
Resumed on September 5, 2018.
Revised Target Date of Completion January 8, 2019
Awaiting for the endorsement of the Mayor of Bokod for resumption. |
Atok | Paoay | Construction of Kochi-Benguet Sisterhood Park Waterworks System | Waterworks System | 509,000.00 | 508,651.11 | Haight's Construction | SB No.1 CY 2017 | 2018-01-17 | 2018-03-13 | Completed | |
Atok | Caliking | Improvement of Sayet-Ammey Farm to Market Road | Roads | 500,000.00 | 498,930.13 | Sangin General Construction | SB No.1 CY 2017 | 2018-02-07 | 2018-03-16 | Completed | |
Buguias | Baculongan Sur | Construction of Box Culvert at Kandapig Creek | Road Side | 500,000.00 | 498,093.66 | Macgat Construction | SB No. 1 CY 2017 | 2018-02-01 | 2018-03-14 | Completed | 1) 98.23% Completed - Total Cost Incurred PhP 498,093.66 as of April 30, 2018 - For post inspection
2) Revised Target Completion Date April 19, 2018 |
Buguias | Bangao | Construction of Vegetable Processing Center | Building | 3,200,000.00 | 3,197,341.64 | AIP Construction | SB No. 1 CY 2017 | 2017-12-11 | 2018-03-31 | Completed | Revised target date of completion: 07/09/2018
2 suspensions |
Buguias | Baculongan Sur | Improvement along Balintag - Teguing - Palintaang FMR | Roads | 500,000.00 | 497,216.36 | Macgat Construction | SB No. 2 CY 2016 | 2018-02-09 | 2018-05-02 | Completed | 1) 100% Completed - Total Cost Incurred PhP 497,216.36 as of April 30, 2018
2) Revised Target Completion Date May 2, 2018
3) For post inspection |
Kapangan | Gaswiling | Construction of Riprap Retaining Wall for Gaswiling BeMONC | Road Side | | 509,451.36 | Pulicay Grandsons Construction | SB No. 1 CY 2017, GF | 2018-01-18 | 2018-03-05 | Completed | Completed on March 5, 2018 |
La Trinidad | Wangal | Rehabilitation of Provincial Housing Project Road Section | Roads | 2,700,000.00 | 2,667,976.02 | SEJ Construction | SB No. 1 CY 2017 | 2018-01-11 | 2018-05-20 | Completed | 100.00% completed with 2,667,976.02.
Completed May 19, 2018 |
Mankayan | Paco | Rehabilitation of Concrete Canal at Pukitan | Road Side | 150,000.00 | 149,590.49 | Dipas Builders | SB No. 1 CY 2017 | 2018-01-18 | 2018-02-14 | Completed | Completed on February 5, 2018 |
Sablan | Bagong | Repair and Painting of Gonzales Elementary School Library | Building Repair | 490,000.00 | 481,966.07 | Guardian Construction | SB No. 1 CY 2017 | 2018-01-17 | 2018-04-20 | Completed | |
Bokod | Pito | Rehabilitation of Akbot Waterworks System | Waterworks System | 500,000.00 | 475,518.90 | DMCD Engineering and Construction | SB No. 1 CY 2017 | 2018-02-15 | 2018-04-09 | Completed | Revised Start Date (Orig. February 1, 2018) and Target Completion Date (Orig. March 26, 2018) |
Bokod | Ekip | Concreting of Ekip FMR/Barangay Road | Roads | 200,000.00 | 188,780.83 | Vanket Engineering and Construction | SB No. 1 CY 2017 | 2018-02-26 | 2018-03-19 | Completed | Completed on March 19, 2018 |
Bokod | Ekip | Construction of Pangis Footbridge in Ekip, Bokod | Bridge | 495,000.00 | 491,886.32 | Vanket Engineering and Construction | SB No. 1 CY 2017 | 2018-02-01 | 2018-03-22 | Completed | Completed |
Tuba | Tadiangan | Improvement / Construction of PCCP along Yagyagan - Ampusa Provincial Road | Roads | 2,000,000.00 | 1,991,925.62 | Anas Construction | SB No. 1 CY 2017 | 2018-02-09 | 2018-06-13 | Completed | 80.76% Completed - Total Cost Incurred PhP 1,608,679.13 as of April 13, 2018 |
Mankayan | Suyoc | Construction of FMR Riprap, Suyoc, Mankayan | Riprap | 500,000.00 | 459,828.97 | A.L Sagandoy Construction | SB No. 1 2017 | 2018-08-20 | 2018-10-10 | Completed | |
Buguias | Amlimay | Completion of Barangay Health Station (Clinic) Amlimay,Buguias,Benguet | | 1,000,000.00 | 964,710.56 | Pulicay Grandsons Construction | SB # 01-2017 | 2018-05-11 | 2018-08-16 | Completed | |
Kabayan | Lusod | Consruction of Lusod Proper Footbridge, Lusod, Kabayan | Footbridge | 1,000,000.00 | 998,190.77 | Haight's Construction | SB # 01 - 2017 | 2018-05-09 | 2018-07-11 | Completed | Completed with 1 suspension and 1 extension
Revised Target Date =11/21/2018 |
Buguias | Buyacaoan | Construction of Salingao to Ikip Flood Control (Batbatoan Section) | Flood Control Construction | 1,000,000.00 | 984,989.21 | Juricmarc Construction | SB no. 2-2017 | 2018-11-13 | 2019-01-20 | Completed | |
Kapangan | Balakbak | Construction of Comfort Room at the Heritage Park, Balakbak, Kapangan | Construction of Comfort Room | 500,000.00 | 496,141.26 | Precious Gold Builders | SB # 1 - 2017 | 2018-12-12 | 2019-02-05 | Completed | Completed, final inspection, March 8, 2019. |
La Trinidad | Wangal | Construction of Four Bathrooms (2 Male Bathrooms, 2 Female Bathrooms) and Laundry Area with Water Tank at Benguet Bahay Pag-asa Center La Trinidad, Benguet | Construction of Bathroom | 1,000,000.00 | 980,600.88 | NAIR Construction & Engineering | SB # 1-2017 | 2018-11-14 | 2019-01-25 | Completed | Completed and usable. |
Buguias | Natubleng | Construction of Police Substation and Tourism Information and assistance Center at Natubleng (Additional) | Completion of Substation | 450,000.00 | 447,602.69 | On Top Construction | SB # 1 - 2017 | 2018-04-13 | 2018-07-18 | Completed | |
Itogon | Tinongdan | Construction of Ambowet Footbridge at Sitio Domolpos | Footbridge | 300,000.00 | 278,837.14 | YKJ - LHAT General Construction | SB #1 2017 | 0000-00-00 | 0000-00-00 | Completed | Completed and usable. |
Tublay | Daclan | Improvement of Alukip Barangay Road | Roads | 500,000.00 | 469,127.16 | Hillstone Builders | 20% PDF 2017 | 0000-00-00 | 2019-11-04 | Completed | Completed |
La Trinidad | Betag | Improvement of Sewage Treatment Plant (Phase II), BeGH, Betag, La Trinidad, Benguet | Improvement of Sewage | 1,000,000.00 | 926,479.29 | AKIP Construction and Enterprise | 20% PDF 2017 | 2018-08-08 | 2019-03-06 | Completed | 1 suspension |
Itogon | Loacan | Completion of Perimeter Fence at Loacan National High School | Perimeter Fence | 150,000.00 | 149,829.00 | YKJ-LHAT General Construction | SB #1 2017 | 2019-03-28 | 2019-04-29 | Completed | Completed |
Atok | Paoay | Installation of Electricity of Senior Citizens Building, KM 46, Paoay, Atok | Electrical | | 51,129.74 | Four Brothers | Sb # 1-2018, PEO | 2019-01-17 | 2019-01-22 | Completed | |
Bokod | Ambuklao | Development of Historical Sites and Prospective Tourist Destinations of Barangay Ambuklao, Bokod, Benguet | Marker | 500,000.00 | 499,369.64 | | 20% PDF 2018 | 2018-10-15 | 2018-11-15 | Completed | |
Kibungan | Madaymen | Construction of concrete pavement along Tagpaya-Salong FMR | Roads | 2,500,000.00 | 2,487,572.46 | HGH=3 Eng'g & Construction | SB#02 2018 | 2019-02-06 | 2019-05-09 | Completed | |
Itogon | Tinongdan | Improvement of the Hospital Building and Cottages at Itogon District Hospital at Itogon,Benguet | Building improvement | 2,500,000.00 | 2,315,652.47 | Tepanlu Construction and Supply | SB # 01-2019 | 2019-06-11 | 2019-09-29 | Completed | |
Mankayan | Bulalacao | Construction of Concrete Pavement along Halsema Junction-CotCot-Bulalacao FMR, Bulalacao, Mankayan | Concrete Pavement | 600,000.00 | 564,070.49 | Nair Construction & Engineering | SB #1 CY 2017 GF | 2018-08-10 | 2018-09-18 | Completed | |
Itogon | Tinongdan | A) Construction of Garage and Morgue and OPD CR; B) Construction of Hospital Morgue Garage, Outside Male and Female CR; C) Upgrading of Facility, IDH | Construction of Building | 1,800,000.00 | 1,777,685.59 | WDG Construction | SB # 2 - 2014 / 20% PDF-2015 | 2018-09-06 | 2018-06-09 | Completed | Completed and usable.
|
Itogon | Tinongdan | A)Construction of Garage and Morgue and OPD CR ; B) Const.of Hospital Morgue Garage, Outside Male and Female CR; C) Upgrading of the Facility, IDH. | Construction of Building | 1,800,000.00 | 1,777,685.59 | WDG Construction | SB # 02 - 2014 / 20% PDF-2015 | 2018-09-06 | 2018-06-09 | Completed | Completed .Revised Target Date=26/10/2018
|
Itogon | Tinongdan | Construction of Guardhouse Itogon Hospital ; Construction of Guardhouse at Itogon Hospital (Add'l.) | Construction of Guardhouse | 180,000.00 | 179,358.73 | Bemada Construction | SB # 02 - 2015 & 20% PDF-2014 | 2018-07-26 | 2018-08-29 | Completed | |
Kibungan | Poblacion | Construction of Senior Citizen Building (Phase II), Poblacion Kibungan | Building | 2,000,000.00 | 1,999,671.60 | Efler Construction | SB No. 2 CY 2016 20% PDF CY 2016 | 2018-01-24 | 2018-07-03 | Completed | 100.00% Completed - Total Cost Incurred PhP 1,999,671.60 as of April 30, 2018 |
Buguias | Natubleng | Construction of Natubleng E/S Open Gym (Phase 1), Construction of Gym (Additional) Natubleng E/S, Construction of Gymnasium at Natubleng E/S | Building | 5,000,000.00 | 4,996,971.65 | | SB No. 4 CY 2015 GF, 20% PDF CY 2016, SEF CY 2016 | 2016-07-08 | 2017-03-24 | Completed | Completed on March 27, 2017 |
La Trinidad | Poblacion | Improvement/ Installation of Roofing for the Third Floor of the Warehouse (DILG Office) | Improvement of Building | 300,000.00 | 268,914.28 | Hillstone Builders | LDRRMF Trust fund | 2019-01-31 | 2019-02-20 | Completed | |
Buguias | Amgaleyguey | Construction of Divsersion Canal and Open Tank Protected by Gabion | | 835,000.00 | | | LDRRMF CY 2013 | 2017-11-22 | 2017-12-30 | Completed | For Post Inspection |
Bakun | Gambang | Construction of Slope Protection as Batanes Primary School | Road Side | 900,000.00 | 897,860.48 | Drichloui Construction | LDRRMF CY 2015 | 2017-08-04 | 2017-12-10 | Completed | Completed as per plan |
Buguias | Bangao | Rehabilitation of Bailey Bridge, Lapalap | Bridge | 330,000.00 | 328,640.98 | On Top Construction | LDRRMF CY 2015 | 2017-01-27 | 2017-02-24 | Completed | |
La Trinidad | Wangal | Construction of Additional RC Retaining Wall | Road Side | 1,130,000.00 | 1,128,244.97 | | LDRRMF CY 2015 Trust Fund | 2016-01-26 | 2017-03-02 | Completed | Input the accurate coordinates of the project |
Bakun | Poblacion | Rehabilitation/Improvement of Poblacion Canal System | | 2,903,000.00 | | | LDRRMF CY 2015 Trust Fund | 2016-04-11 | 2016-07-02 | Completed | Completed on July 18, 2016 with liquidated damages |
La Trinidad | Bineng | Improvement / Fencing of Day Care Center | Fence | 500,000.00 | 499,160.20 | | LDRRMF CY 2015 Trust Fund | 2016-06-28 | 2016-10-14 | Completed | Completed on September 20, 2016 |
Bakun | Poblacion | Construction of Concrete Drainage Canal & Footpath at Wagangan, Poblacion, Bakun | | 350,000.00 | 347,319.86 | NAIR Construction and Engineering | LDRRMF CY 2016-Trust Fund | 2018-06-26 | 2018-08-11 | Completed | |
Buguias | Loo | Construction of Retaining Wall and Restoration of Concrete Pavement along Lanas- Taba-ao Farm to Market Road | Road | 700,000.00 | 673,225.02 | Drich Loui Construction | LDRRMF 2016 | 2018-07-25 | 2018-09-16 | Completed | |
Bokod | Daclan | Construction of Slope Protection at the Dennis Molintas Memorial Hospital Daclan, Bokod, Benguet | Semi-permanent Structure | 350,000.00 | 334,467.39 | Pulicay Grandsons Construction | LDRRMF-2016,Trust Fund | 2018-07-04 | 2018-08-07 | Completed | |
Itogon | Virac | Rehabilitation along Baguio - Balatoc Provincial Road | Roads | 8,016,454.94 | | Compass Rose Builders/ Daniel T. Sibelius | LDRRMF Trust Fund | 2016-07-21 | 2017-05-13 | Completed | Completed on June 6, 2017 with liquidated damages |
Itogon | Virac | Improvement along Baguio - Balatoc Provincial Road | Roads | 2,000,000.00 | 1,997,915.47 | ICO Construction | LDRRMF CY 2016 | 2016-09-20 | 2017-01-02 | Completed | Completed on January 2, 2017 |
Kapangan | Pudong | Improvement of Cadtay - Pudong Provincial Road | Roads | 1,000,000.00 | 996,861.13 | Balangcod Construction, Fermin D. Balangcod | LDRRMF CY 2016 | 2016-04-06 | 2016-07-19 | Completed | with under run and Liquidated Damages |
Kabayan | Gusaran | Improvement along National Road Junction - Diboong - Bangao Provincial Road | Roads | 2,000,000.00 | 1,997,826.95 | | LDRRMF CY 2016 | 2016-04-18 | 2016-07-18 | Completed | |
Mankayan | Balili | Improvement along Mankayan - Balili Provincial Road | Roads | 2,000,000.00 | 1,997,675.29 | | LDRRMF CY 2016 | 2016-04-12 | 2016-08-12 | Completed | With Liquidated Damages |
Kapangan | Sagubo | Improvement along Lomon - Sagubo Provincial Road | Roads | 3,000,000.00 | 2,996,978.82 | Bolos Engineering & Construction, Edgar B. Baclawa | LDRRMF CY 2016 | 2016-04-26 | 2016-08-05 | Completed | With under run and liquidated damages |
Kapangan | Paykek | Improvement along Lomon - Paykek Provincial Road | Roads | 2,000,000.00 | 1,989,500.32 | Balangcod Construction, Fermin D. Balangcod | LDRRMF CY 2016 | 2016-04-06 | 2016-09-05 | Completed | 99.047% completed due to under run |
Tublay | Ambassador | Improvement along Labey - Lacamen Provincial Road | Roads | 2,000,000.00 | 1,997,799.27 | Leo Heirs Construction/ Emmanuel S. Leo | LDRRMF CY 2016 | 2016-04-18 | 2016-09-26 | Completed | with Liquidated Damages |
Itogon | Virac | Diversion of Batuang Road (Rehabilitation along Baguio - Balatoc Provincial Road) | Roads | 3,000,000.00 | 2,996,947.56 | ico construction services/jerico palangdan | LDRRMF CY 2016 | 2016-07-21 | 2016-12-06 | Completed | |
Kabayan | Gusaran | Rehabilitation of Diboong Provincial Road | Roads | 1,000,000.00 | 998,483.80 | | LDRRMF Trust Fund | 2016-07-21 | 0000-00-00 | Completed | For updating of actual Completion |
Buguias | Baculungan Sur | Rehabilitation along Bad-ayan-Manhuyohoy Provincial Road | Roads | 1,500,000.00 | 1,496,835.28 | | LDRRMF 2016 | 2016-09-20 | 2016-11-29 | Completed | |
Sablan | Provincial Road Sablan (for updating) | Rehabilitation along Sablan -Sabalan old Presidential Provincial Road | Roads | 1,000,000.00 | 999,403.00 | | LDRRMF 2016 | 2016-06-27 | 2016-08-13 | Completed | For updating |
Bakun | Ampusongan | Improvement along Tongey Farm to Market Road | Roads | 5,000,000.00 | 4,997,563.22 | | LDRRMF CY 2016 | 2016-04-11 | 2016-10-13 | Completed | |
Kabayan | Ballay | Construction of Retaining Wall along Liang-Taaw FMR, Ballay, Kabayan | Road Side | 350,000.00 | 348,762.14 | Jamil Sean Construction | LDRRMF CY 2016 - TRUST FUND | 2018-03-12 | 2018-04-12 | Completed | |
Mankayan | Guinaoang | Construction of Retaining Wall at Guinaoang | Road Side | 767,000.00 | 748,224.05 | Sharamelle Construction and General Engineering | LDRRMF CY 2016 Trust Fund | 2018-03-28 | 2018-05-24 | Completed | Completed on May 19, 2018, with 748,224.05 total cost incurred. |
Buguias | Catlubong | Construction of Drainage Canal along Padang - Mankilet FMR | Roads | 350,000.00 | 340,717.06 | Macgat Construction | LDRRMF CY 2016 | 2018-03-22 | 2018-04-12 | Completed | Revised target completion date (May 2, 2018).
Completed with 340,717.06 total cost incurred.
For post inspection |
Bakun | Poblacion | Construction of Drainage Canal and Riprap at Bacung | Roadside | 350,000.00 | 346,675.11 | SRBA General Construction | LDRRMF 2016 | 2018-06-29 | 2018-09-03 | Completed | |
Tublay | Ambassador | Rehabilitation of Langgay Bajating Barangay Road, Ambassador, Tublay, Benguet | PCCP with curb and gutter and cross drain | 350,000.00 | 343,011.92 | Sangin General Construction | LDRRMF - 2016, Trust fund | 2018-05-09 | 2018-06-17 | Completed | |
Sablan | Bayabas | Construction of Slope Protection at Agri-Eco Farm, Bulala, Bayabas, Sablan | Construction of Slope Protection | 1,300,000.00 | 1,294,620.75 | HGW = 3 Eng'g & Construction | LDRRMF 2016 Trust Fund | 2019-01-29 | 2019-04-20 | Completed | |
Atok | Naguey | Rehabilitation of Naguey Vehicular Bridge (Abutment Foundation) | Bridge | 3,200,000.00 | 3,179,395.26 | BTCRJ Construction and Engineering | LDRRMF CY 2017 | 2017-07-18 | 2018-09-25 | Completed | 1) Target Completion Date to be determined upon issuance of Resume Order.
2) 85% Completed - Total Cost Incurred PhP 2,702,485.97 as of April 30, 2018
3. For post-inspection |
La Trinidad | Wangal | Construction of Grouted Riprap at the Site of Benguet Training Center | Road Side | 320,000.00 | 320,000.00 | | LDRRMF CY 2017 | 2017-10-16 | 2017-11-05 | Completed | Input the accurate coordinates of the project |
La Trinidad | Bineng | Improvement along Capitol - Bineng Provincial Road | Roads | 1,500,000.00 | 1,498,460.84 | SEJ Construction | LDRRMF CY 2017 | 2017-12-20 | 2018-03-10 | Completed | 82.09% Completed - Total Cost Incurred PhP 1,230,086.50 as of March 2018 |
Mankayan | Taneg | Construction of Vehicular Bridge at Sitio Kil-ingan | Bridge | 9,265,000.00 | 9,171,622.06 | Compass Rose Builders | LDRRMF CY 2017 | 2017-12-01 | 2018-05-17 | Completed | Suspended on March 5, 2018 due to change order (inclusion of pedestrian lane). Resumed on April 30, 2018. And Actual Date of Completion is May 16, 2018. |
Itogon | Virac | Improvement of Kias - Padcal - Philex Provincial Road | Roads | 1,500,000.00 | 1,497,811.06 | ICO Construction | LDRRMF CY 2017 | 2018-02-09 | 2018-04-23 | Completed | 36.42% Completed with 8.51% slippage- Total Cost Incurred PhP 545,502.79 as of April 13, 2018 |
La Trinidad | Wangal | Improvement/ Upgrading of PDRRM Equipment Shed Multi-purpose warehouse | Improvement of Building | | 523,653.80 | Hillstone Builders | LDRRMF CY 2017 | 2019-01-31 | 2019-03-19 | Completed | |
Itogon | Ampucao | Rehabilitation of Manganese Elementary School Building | Building Repair | 400,000.00 | 388,622.94 | Aljune Builders | LDRRMF Trustfund | 2018-03-12 | 2018-04-22 | Completed | completed on April 18, 2018 |
La Trinidad | Puguis | Construction of Drainage Canal and Concrete Pathway at Palmaville Subdivision, La Trinidad, Benguet | Roadside | 500,000.00 | 423,944.47 | Akip Construction | Trust Fund - LDRRMF 2018 | 2018-05-17 | 2018-07-13 | Completed | |
Tuba | Twin Peaks | Improvement along Camp1, Indaoac, Twin Peaks Provincial Road | Road Side Improvement | 1,000,000.00 | 944,702.23 | Sapdoy Enterprise / William W. Sapdoy | LDRRMF | 2018-07-18 | 2018-11-20 | Completed | Completed as Planned. |
Buguias | Abatan | Construction of Drainage Canal System and Concrete Retaining Wall Along the Sinking Section of the Central Business District Area, Buguias | Construction of Drainage canal | 1,500,000.00 | 1,495,745.00 | Wacaden Construction | LDRRMF 2018 | 2019-01-28 | 2019-05-07 | Completed | |
Tublay | Ambongdolan | Construction of Riprap at Pungayan - Betwag FMR | Riprap | 830,000.00 | 795,230.04 | Akip Construction and Enterprise | LDRRMF-2018 | 2019-06-07 | 2019-07-25 | Completed | |
Kibungan | Sagpat | A.) Improvement along Kibungan Junction - Sagpat Provincial Road; B.)Rehabilitation along JNR Sagpat-Sapdaan Provincial Road | Roads | 3,000,000.00 | 2,467,119.09 | Balangcod Construction | LDRRMF 2018 and 2019 | 2019-06-07 | 2019-08-21 | Completed | |
Kapangan | Datakan, Labueg, and Lomon | Rehabilitation along Datakan-Labueg-Lomon Provincial Road | Roads | 4,000,000.00 | 3,971,017.91 | Balangcod Construction | LDRRMF | 2019-06-07 | 2019-10-19 | Completed | Brief description of project: Road concreting, removed and replaced PCCP, grouted riprap, gabion, and retaining wall;
- 1 suspension (August 7-29, 2019);
- Date completed: September 27, 2019
|
Mankayan | Guinaoang, Suyoc, and Taneg | Construction of Two Terraced Retaining Wall along Guinaoang-Suyoc-Taneg Provincial Road | Retaining Wall | 1,600,000.00 | 1,466,826.83 | Dicay Construction Supply and Services | LDRRMF, Trust Fund | 2019-04-02 | 0000-00-00 | Completed | |
La Trinidad | Pico | Construction of Drainage Canal at Lower Capjaran - Obudan, Km. 4 | Canal | 700,000.00 | 685,168.88 | Hillstone Builders | LDRRMF, Trust Fund | 2019-06-07 | 2019-08-03 | Completed | completed |
Atok | Caliking | Rehabilitation along Jose Mencio Provincial Road (section not covered by PRDP) | Road | 6,000,000.00 | 5,838,541.52 | Almond Engineering and Construction (Rogelio D. Alimondo) | LDRRMF TF 2019 | 2019-06-27 | 2020-02-14 | Completed | Completed as of February 26, 2020. |
Itogon | Balatoc | Rehabilitation along Baguio - Balatoc - Itogon Provincial Road | Road | 500,000,000.00 | 4,180,653.53 | A.L. Sagandoy Construction (Agapito L. Sagandoy) | LDRRMF TF 2019 | 2019-06-27 | 2019-09-13 | Completed | by JC |
Buguias | Baculongan Norte | Improvement of Bano-oy Elementary School of Baculongan Norte, Buguias | | 780,000.00 | 778,462.79 | | PSB No. 9 CY 2015 | 2016-02-04 | 0000-00-00 | Completed | |
Buguias | Poblacion | Completion of Gymnasium for Stage and Bleachers of Buguias Central School in Central Buguias (Additional) | Building | 780,000.00 | 778,176.94 | Random Builders | PSBF CY 2015 | 2017-05-30 | 2017-09-08 | Completed | Revised target completion date to October 1, 2017. |
Kibungan | Lubo | Construction of Cottage in Lubo, Kibungan, Benguet (additional) | Building | 1,000,000.00 | 983,075.85 | Cabuguisan Builders | PSBF CY 2015 | 2017-01-27 | 2017-05-23 | Completed | |
Mankayan | Tabio | Construction of Building Phase II for Lepanto National High School, Palatong Annex in Palatong Mankayan (additional) | Building | 1,200,000.00 | 1,185,000.00 | Donato Sakiwat Construction | PSBF CY 2015 | 2017-03-22 | 2017-07-13 | Completed | Need additional fund |
Mankayan | Bedbed | Construction of Payew Primary School Building in Bedbed | | 800,000.00 | | | PSBF CY 2015 | 2016-04-06 | 2016-07-22 | Completed | |
Bokod | Ekip | Reconstruction of Naswak Elementary School Teacher's Cottage | Building Repair | 1,000,000.00 | 998,383.49 | | PSBF CY 2015 | 2016-06-29 | 2016-10-07 | Completed | Suspended on August 12, 2016 to September 5, 2016 |
Sablan | Bayabas | Construction of Multi-Purpose Building (Phase II), Agri-Eco Farm | Building | 1,000,000.00 | 935,010.68 | Anas Construction | 20% PDF CY 2015 | 2018-09-03 | 2018-12-08 | Completed | |
Buguias | Abatan | Completion of School Building for Abatan Elementary School | Building | 500,000.00 | 497,530.17 | On Top Construction | PSBF CY 2016 | 2017-11-22 | 2017-12-31 | Completed | For post inspection |
Kapangan | Sagubo | Rehabilitation of Tadayan Elementary School in Pudong, Kapangan, Benguet | | 500,000.00 | | Balangcod Construction, Fermin Balangcod | PSBF-2016 | 2017-02-16 | 2017-06-13 | Completed | Repair of tadayan elem school in pudong, kapangan |
Kapangan | Pudong | Repair of Tadayan Elementary School in Pudong, Kapangan, Benguet | Building Repair | 900,000.00 | 897,070.68 | Balangcod Construction | PSBF CY 2016 | 2017-01-27 | 2017-08-01 | Completed | |
Kapangan | Paykek | Construction of Sabagit Footpath, Cadtay, Paykek, Kapangan | Roads | 200,000.00 | 198,553.86 | Balangcod Construction | SB No. 2 CY 2016 | 2017-10-07 | 2017-12-03 | Completed | Contract under cluster l: a) construction of sabagit footpath, cadtay, paykek, kapangan |
La Trinidad | Beckel | Rehabilitation of Lamut Elementary School | Building Repair | 500,000.00 | 498,659.31 | ICO Construction | PSBF CY 2016 | 2017-02-08 | 2017-03-30 | Completed | 99.84% Completed with under run.
|
Sablan | Pappa | Completion of Senior Citizen's Building, Pappa | Building | 500,000.00 | 491,390.94 | Anas Construction | PSBF CY 2016 | 2017-07-31 | 2017-09-24 | Completed | |
Bakun | Gambang | Completion of School Building for Tingbaoen - Galisen Elementary School at Gambang, Bakun | Completion of Building | 500,000.00 | 495,289.88 | SRBA Gen. Construction | PSBF CY 2016 | 2019-01-30 | 2019-04-12 | Completed | Completed with LD |
Tublay | Ambassador | Repair of Dorencio Elementary School (Coroz Elementary School) Building in Ambassador, Tublay | Building Repair | 700,000.00 | 698,956.09 | Leo Heirs Construction | PSBF CY 2016 | 2017-01-28 | 0000-00-00 | Completed | |
Kabayan | Gusaran | Ground Development at Kamora NHS | | 500,000.00 | | | PSBF CY 2016 | 2016-06-29 | 2016-07-29 | Completed | |
Mankayan | Bulalacao | Completion of Caew Elementary School Building | Building | 611,000.00 | 603,251.03 | | PSBF CY 2016 | 2016-07-20 | 2016-10-28 | Completed | |
Mankayan | Guinaoang | Improvement of Ambabag FMR | Roads | 500,000.00 | 488,554.05 | Malco Construction | PSBF CY 2016 | 2016-09-19 | 2016-11-02 | Completed | |
Bakun | Bagu | Improvement of Barbarit Primary School Building | Building Repair | 400,000.00 | 399,293.84 | Apaklo Construction | PSBF CY 2016 | 2018-02-27 | 2018-05-27 | Terminated | |
Bokod | Bila | Improvement of FMR along Gwiling-Yabo in Palansa, Bila | Roads | 100,000.00 | 96,510.62 | SRBA General Construction | SB #2 CY 2016 | 0000-00-00 | 0000-00-00 | Completed | |
Itogon | Dalupirip | Rehabilitation of Fianza Memorial National High School Waterworks System | Waterworks System | 285,000.00 | 284,070.62 | SFF Enterprise | PSBF CY 2017 | 2018-01-24 | 2018-03-04 | Completed | Completed on March 2, 2018 |
Itogon | Dalupirip | Construction of Stage at Lawigen Elementary School | Stage | 500,000.00 | 497,126.57 | Compass Rose Builders | PSBF 2017 | 2019-02-07 | 2019-04-10 | Completed | Completed and Usable
|
Sablan | Poblacion | Repair of Damaged HE and Industrial Arts Building, Walk Shed and Flag Pole of Palali Elementary School in Palali, Sablan | Building Repair | 800,000.00 | 739,910.16 | HGW=3 Engineering & Construction | SB No. 1 CY 2017-PSB, SB No. 1 CY 2017- GF PEO | 2018-01-17 | 2018-04-01 | Completed | Completed on March 28, 2018 |
La Trinidad | Wangal | Construction of Multi-Purpose Gymnasium at the Benguet Sports Center (Phase VII), Wangal, La Trinidad | | 4,993,676.18 | | Anitos construction / marty manayos | Trust Fund 2015 DILG Pamana | 2016-03-22 | 0000-00-00 | Completed | Partial accomplishment (86.67..%)of his contract due on const. of multi-purpose gymnasium at benguet sports center (phase IV),wangal,la trinidad |
Buguias | Loo | Loo Farm to Market Road | Roads | 1,000,000.00 | 994,514.26 | | 2015 SP Res. No. 15-377 Trust Fund | 2017-02-08 | 2017-03-15 | Completed | |
Bakun | Dalipey | Opening/Improvement of Dagadangan-Copcopit Road | Roads | 32,000,000.00 | 31,982,382.30 | MAKJAY Construction and Bakun Construction | PAMANA 2015 | 2015-10-08 | 2018-07-17 | Terminated | 1) 85.94% completed - Total Cost Incurred PhP 27,587,513.54
2) Project terminated for default as of December 2018
3) Length - 4312 meters |
Kibungan | Madaymen | Tokbo Bailey Bridge | Bridge | 5,000,000.00 | 4,944,971.54 | Universal De Leon Construction and Aggregates | Pamana 2015 | 2015-09-15 | 2016-10-02 | Completed | 1) Completed with underrun
2) 99.84% completion which is equivalent to Php 4,937,236.67 |
Kabayan | Tawangan | Improvement of Talabing - Tinoc Road, Tawangan | Roads | 12,000,000.00 | 9,439,087.18 | Cabuguisan Builders | PAMANA 2016 | 2017-01-24 | 2017-05-17 | Terminated | 1) 44.6821% completion which is equivalent to Php 4,202,384.37
2) Project terminated for default |
Kibungan | Sagpat | Opening from Bokes-Saddle to Lasilas, Tawang towards Badeo, Kibungan, Benguet | Roads | 10,000,000.00 | 6,999,999.99 | Cabuguisan Builders | PAMANA 2016 | 2017-02-15 | 2018-04-21 | Terminated | 1) Ongoing; Original Target Completion date: April 21, 2018
2) Suspension Order No. 1 Effective February 15, 2017 due to procurement of ECC and Tree Cutting Permit; Resumer Order No. 1: March 30, 2017.
3) Suspension Order No. 2 effective March 30, 2017 due to on-going project implemented by MLGU.
4) Suspension Oder No. 3 effective August 31, 2017 awaiting for the relocation of BENECO POST and for the action of the concerned office regarding the query of the contractor regarding the COA-AOM.
5) Resume order No. 3 issued and received on April 23, 2018
6) Completed 16.4% w/ -2.34% slippage - Total Cost Incurred PhP 1,148,036.40 - as of May 2018
7) for termination as directed by DILG |
Mankayan | Bulalacao | Construction of Manpey-as Concrete Canal and Flood Control | Road Side | 3,000,000.00 | 2,950,000.22 | Donato Sakiwat Construction | PAMANA 2016 | 2017-01-24 | 2017-05-13 | Completed | 1) Completed with underrun.
2) 98.91% completion which is equivalent to Php 2,917,950.33 |
Mankayan | Cabiten | Concreting of Cabiten - Kamantaki Road at Cabiten, Mankayan | Roads | 20,000,000.00 | 19,979,773.81 | Rocky 5G | PAMANA 2016 | 2017-01-23 | 2018-09-02 | Terminated | 1) 58.19% completed - Total Cost Incurred PhP 11,626,938.36
2) Project terminated for default |
Mankayan | Cabiten | Concreting of Cabiten - Kamantaki Road at Cabiten, Mankayan | Roads | 8,333,637.00 | 8,276,530.77 | JYP Construction | PAMANA 2016 | 2017-12-08 | 2018-01-31 | Completed | Completed on February 23, 2018 |
Kabayan | Tawangan | Leveling and Improvement of Tawangan Elementary School Ground, Tawangan Kabayan | School Improvement, Ground Leveling and Riprap | 300,000.00 | 299,375.02 | Akiki Builders | SB No. 2, 2016 | 2018-07-03 | 2018-08-04 | Completed | |
Tublay | Tublay Central | Construction of Gymnasium at Tublay School of Home Industries in Tublay Central, TUBLAY | Building | 2,000,000.00 | | Hillstone Builders/ Hudson W. Depolio | PSB CY 2015 | 2016-03-21 | 2017-02-13 | Completed | payment of projects. a)cons.of tublay central gymnasium @ tublay central.b)cons,of gymnasium @ TSHI in tublay central,tublay benguet. |
Kapangan | Sagubo | Rehabilitation of Amponget Barrio School in Sagubo, Kapangan (additional) | Building Repair | 500,000.00 | 496,736.13 | Bolos Engineering and Construction | SEF CY 2016 MOOE | 2017-02-16 | 2017-06-13 | Completed | For additional Funding |
Itogon | Gumatdang | Rehabilitation of Gumatdang Elementary School Building in Gumatdang, Itogon | Building Repair | 800,000.00 | 797,762.30 | Compass Rose Builders | Special Education Fund 2016 MOOE | 2018-01-17 | 2018-05-21 | Completed | Completed as of May 23, 2018 |
Bakun | Kayapa | Construction of Water Works System for Cadsi-Amoy Elementary School in Kayapa, Bakun | Waterworks System | 400,000.00 | 399,369.29 | SRBA General Construction | SEF CY 2016 CO | 2018-02-01 | 2018-03-10 | Completed | Completed on March 5, 2018 |
La Trinidad | Beckel | Construction of Gymnasium for Beckel Elementary School in Beckel, La Trinidad (additional) | Building | 1,000,000.00 | 998,433.41 | | SEF CY 2016 | 2016-03-22 | 0000-00-00 | Completed | |
Mankayan | Bulalacao | Completion of Ca-ew Elementary School Building in Bulalacao, Mankayan | Building | 611,000.00 | 603,251.03 | | SEF CY 2016 | 2016-07-06 | 0000-00-00 | Completed | |
Tuba | Tadiangan | Improvement of Kiwas Elementary School in Tadiangan, Tuba | Building Repair | 460,000.00 | 458,565.68 | Roben Runas Construction | SEF CY 2016 | 2017-01-03 | 0000-00-00 | Completed | Cluster "H" b) Control No. 0203-15-00028 - Roben Runas Construction |
Atok | Topdac | Construction of School Building for Ja'pa Elementary School in Topdac, Atok | Building | 800,000.00 | 794,982.99 | Sangin General Construction | SEF CY 2016 | 2017-01-17 | 0000-00-00 | Completed | |
Atok | Cattubo | Construction of two-storey building for Calasipan Elementary School at Calasipan | School Building | 3,293,218.00 | 3,277,624.12 | Camrock construction | SEF 2018 SB #1 | 2019-02-08 | 2019-10-05 | Completed | Completed and Geo-tagged on October 17, 2019. |
Tublay | Ambassador | Construction of Gymnasium for Pontino Elementary School in Ambassador, Tublay (additional) | Building | 2,600,000.00 | 2,533,797.22 | Pecdasen Builders | Special Education Fund SB #1 CY 2018 | 2020-03-03 | 2021-01-15 | Completed | |
Bokod | Pito | Construction of Basketball Court for Pilpiok Elementary School in Pito, Bokod | Building | 500,000.00 | 498,681.86 | | SEF CY 2016 | 2016-06-22 | 2016-08-24 | Completed | |
Kabayan | Kabayan Barrio | Ground Improvement of Kamora National High School | Building Repair | 500,000.00 | 499,012.86 | | SEF CY 2016 | 2016-06-22 | 0000-00-00 | Completed | |
Mankayan | Poblacion | Construction of Shed for Lepanto National High School in Mankayan (additional) | Building | 1,000,000.00 | 998,253.80 | | SEF CY 2016 | 2016-06-20 | 0000-00-00 | Completed | |
Kapangan | Sagubo | Construction of Gymnasium for Kapangan National High School (additional) | Building | 2,000,000.00 | 1,997,536.35 | Balangcod Construction, Fermin Balangcod | SEF CY 2016 | 2016-06-13 | 0000-00-00 | Completed | |
Atok | Abiang | Opening of Kisset - Moding FMR, Abiang | Roads | 500,000.00 | 497,456.46 | SANGIN Gen. Construction | 20% PDF CY 2016 | 2018-05-09 | 2018-06-16 | Temporarily suspended | Temporarily suspended pending issuance of CNC by DENR |
Atok | Abiang | Completion of Sub-Clinic, Bocao, Abiang | Building | 300,000.00 | 299,344.47 | Drichloui Construction | 20% PDF CY 2016 | 2018-05-09 | 2018-06-19 | Completed | |
Itogon | Dalupirip | Bantic Water Works Systems | Waterworks system | | 830,223.32 | Compass Rose Builders | 20% PDF 2016 | 0000-00-00 | 2019-08-04 | Completed | |
Kapangan | Datakan | Repair of Datakan Elementary School Building in Datakan, Kapangan, Benguet | Building | 600,000.00 | 598,836.96 | Vanket Engineering and Construction | SEF CY 2017 | 2017-10-20 | 2018-01-13 | Completed | Completed on January 12, 2018 |
La Trinidad | Poblacion | Repair of Benguet National High School Slope Protection and Drainage | Road Side | 500,000.00 | 499,282.24 | ICO Construction | SEF CY 2017 | 2017-11-22 | 2018-01-08 | Completed | Completed on January 26, 2018 with liquidated damages |
La Trinidad | Poblacion | Repair of Buyagan Elementary School Building | Building Repair | 150,000.00 | 149,414.85 | Ico Construction Services, Jerico Palangdan | SEF CY 2017 | 2017-11-22 | 2017-12-05 | Completed | contract under cluster h: a) repair of benhs slope protection and drainage, wangal; b) repair of buyagan e/s building , poblacion, la trinidad |
Tublay | Baayan | Repair of Baayan Elementary School Annex Building | Building Repair | 600,000.00 | 598,868.65 | Sangin General Construction | SEF CY 2017 | 2018-03-08 | 2018-04-14 | Completed | Completed on May 8, 2018, with 598,868.65 total cost incurred. |
La Trinidad | Wangal | Repair of SPED Center Slope Protection in Wangal | Road Side | 500,000.00 | 447,067.71 | Guardian Construction | SEF CY 2017 | 2018-01-17 | 2018-03-02 | Completed | 1) Completed
2) Suspended effective February 27, 2018 pending preparation and approval of Change Order No. 01 |
La Trinidad | Wangal | Construction of Covered Court for Regional Science High School, Wangal, La Trinidad Benguet | Building | 1,500,000.00 | 1,498,400.95 | SEJ Construction | SEF CY 2017 | 2018-02-27 | 2018-06-04 | Completed | |
Atok | Pasdong | Improvement of Dituan Barangay Road | Roads | 500,000.00 | 498,373.24 | Drichloui Construction | 20% PDF 2017 | 2018-05-09 | 2018-06-09 | Completed | |
Tuba | Ansagan | Construction of Fence at Ansagan E/S | Construction of Fence | 300,000.00 | 293,987.62 | FMC Warriors | SEF-2017 | 2018-11-29 | 2018-12-31 | Completed | |
Kabayan | Ballay | Construction of Fence at Ballay Elementary School, Ballay, Kabayan | Fence | 500,000.00 | 478,538.53 | Haight's Construction | SEF 2017 | 2018-09-05 | 2018-07-06 | Terminated | |
Kabayan | Ballay | Construction of Fence at Pallay Elementary School,Ballay,Kabayan,Benguet | Grouted Riprap/Masonry Fence | 500,000.00 | 499,434.38 | YKJ-LHAT General Construction | SEF-2017 | 2019-03-27 | 2019-05-13 | Completed | |
La Trinidad | Shilan | Repair of Pagal Elementary School, La Trinidad, 3 Classrooms | School Building | 8000,000.00 | 760,127.37 | On Top Construction | SEF | 2018-11-14 | 2019-02-17 | Completed | Completed and usable. |
Bokod | Pito | Repair of Galsa Elementary School, Bokod - 3 Classrooms at Pito, Bokod, Benguet | Building Repair | 900,000.00 | 895,000.00 | | SEF - 2018 | 2019-04-12 | 2019-07-08 | Completed | |
Itogon | Ampucao | Construction of Walk with Shed for Manganese E/S Ampucao, Itogon, Benguet | Walk Shed | 250,000.00 | 249,379.50 | ICO Construction | SEF 2016, SB #3 | 0000-00-00 | 2018-09-13 | Completed | |
Itogon | Virac | Rehabilitation of Drainage Canal along Baguio - Balatoc - Itogon Provincial Road | Road Side | 980,000.00 | 914,851.61 | ICO Construction | SLRF CY 2015 | 2017-04-20 | 2017-06-28 | Completed | |
Sablan | Kamog | Rehabilitation of Drainage Canal along Calot - Kamog - Pappa Provincial Road | Roads | 1,960,000.00 | 1,630,161.50 | Anas Construction | SLRF CY 2015 | 2017-04-01 | 2017-07-14 | Completed | |
La Trinidad | Shilan | Rehabilitation of Drainage Canal along Shilan - Sagpawe Provincial Road | Road Side | 1,960,000.00 | 1,939,172.69 | ICO Construction | SLRF CY 2015 | 2017-09-05 | 2017-11-05 | Completed | with liquidated damages |
La Trinidad | Wangal | Rehabilitation of Drainage Canal along Buyagan - Wangal Banengbeng Provincial Road | Road Side | 2,438,073.40 | 2,433,059.07 | Cliff Construction | SLRF CY 2015 | 2017-04-20 | 2017-07-23 | Completed | with liquidated damages |
Tuba | Twin Peaks | Rehabilitation of Drainage Canal along Camp 1 - Indaoac Twin Peaks Provincial Road | Road Side | 1,960,000.00 | 1,944,471.91 | Bosongan Construction | SLRF CY 2015 | 2017-04-10 | 2017-06-28 | Completed | |
La Trinidad | Bahong | Rehabilitation along Bahong - Sadag Provincial Road | Roads | 2,340,000.00 | 2,336,209.07 | EaJr De Leon Construction/ Edwardo De Leon Jr | 5% Calamity Fund 2015 and LDRRMF 2015 | 2016-01-26 | 2016-07-08 | Completed | Completed with Liquidated damages equivalent to 6,429.48 |
La Trinidad | Alapang | Improvement along Alapang - Alno Provincial Road | Roads | 2,000,000.00 | 1,998,017.35 | Sangin General Construction | PDRRMF CY 2015 CO | 2017-12-06 | 2018-02-25 | Completed | Completed on February 25, 2018 |
La Trinidad | Ambiong | Construction of of Open Gymnasium Phase II Ambiong Elementary School | Gym | 4,000,000.00 | 3,985,900.38 | NORBANO BUILDERS | GF 2017 | 2019-03-07 | 2019-12-11 | Completed | By J G. C |
La Trinidad | Wangal | Construction of Comfort Rooms With Lavatory (Cold Chain) | Building | 1,500,000.00 | 1,544,829.13 | Four Brothers Construction | GF 2018 | 2019-02-03 | 0000-00-00 | Completed | by JC |
Kibungan | Madaymen | Concrete Pavement Along Madaymen-Daopyongo-Sagangasang FMR | Road Pavement and Riprap | 500,000.00 | 499,825.34 | Akip Construction and Enterprise | SB 2019 | 2019-12-11 | 2019-02-12 | Completed | Geotagged by J G. C |
Itogon | LabilAB | Construction of one-room kinder School Building Labilab | School Building | 1,200,000.00 | 1,122,566.12 | Reko General Konstruct | GF 2018 | 2019-12-10 | 2019-09-12 | Completed | Completed, Geotagged by JG. C |
Itogon | Tuding | Construction of Covered Court Phase II AMPHS Bua, Tuding, Itogon, Benguet | Gymnasium | 3,000,000.00 | 2,831,065.49 | AMSLEO Construction | GF 2018 | 0000-00-00 | 2019-12-12 | Completed | Geottagged by J G. C |
Bokod | Bobok-Bisal | Rehabilitation of Yapas Potable Waterworks System-Extention | Waterworks System | 300,000.00 | 298,693.57 | Sangin General Construction | CHARMP 2 Trust Fund | 2017-01-31 | 2017-03-22 | Completed | |
Kibungan | Madaymen | Road Upgrading and Improvement of Halsema - Madaymen Provincial Road Phase II | Roads | 45,244,985.00 | 45,209,140.69 | KVC Construction | CMGP DILG | 2018-01-23 | 2018-12-01 | Completed | |
Kapangan | Boklaoan | Road Upgrading and Improvement of Amburayan Boneng Provincial Road | Roads | 43,839,963.53 | 43,839,963.53 | JOMARCANN General Construction | CMGP DILG | 2017-11-21 | 2019-01-12 | Completed | Completed on April 17, 2019 with liquidated damages and underrun |
Kapangan | Sagubo | Rehabilitation along Landing Waterworks System | | 2,930,046.44 | 292,974.94 | bolos engineering & construction/edgar baclawad | DOE-ER | 2016-07-06 | 2016-08-09 | Completed | |
La Trinidad | Wangal | Construction of Multi-Purpose Gymnasium at the Benguet Sports Center (Phase VIII) | Building | 4,000,000.00 | 3,996,782.34 | | SNAPB 2015 Trust Fund | 2016-06-27 | 2016-10-24 | Completed | |
Mankayan | Colalo | Construction of Compac at Baguyos | Building | 1,100,000.00 | 1,076,597.69 | | LS | 2016-03-26 | 2017-07-02 | Completed | |
Mankayan | Guinaoang | Improvement and Upgrading of Guinaoang - Suyoc Gambang Provincial Roads | Roads | 56,838,685.91 | 56,800,660.75 | Anitos Construction / STAY Construction JV | KALSADA - DILG 2016 | 2016-04-09 | 2017-07-27 | Completed | 79.43% Completed - Total Cost Incurred PhP 45,116,764.83 as of April 13, 2018 |
La Trinidad | Wangal | Construction of Coffee Trading Center | Building | 2,672,000.00 | 2,658,551.92 | ICO Construction | PRDP Trust Fund | 0000-00-00 | 0000-00-00 | Completed | On going, resumed on June 22, 2020.
|
La Trinidad | Beckel | Construction of Slope Protection at Beckel | Road Side | 8,013,000.00 | 6,884,529.85 | APB Construction | PRDP 2016 | 2017-06-07 | 2017-12-01 | Completed | Completed on March 23, 2018 with liquidated damages and under run |
La Trinidad | Alno | Construction of Slope Protection at Alno | Slope Protection | 1,763,000.00 | 1,750,578.83 | Rocky 5G Builders | PRDP 2016 | 2017-05-22 | 2017-07-22 | Completed | 1) Completed June 30, 2018 with liquidated damages
2) Suspended on December 1, 2017 due to Variation Change Order No. 2. |
La Trinidad | Alapang | Construction of Slope Protection at Alapang | Slope Protection | 4,086,000.00 | 4,075,139.89 | Rocky 5G Builders | PRDP 2016 | 2017-05-22 | 2017-11-16 | Completed | Completed September 6, 2017 |
Atok | Caliking | Improvement of Jose Mencio FMR | Roads | 202,336,809.93 | 202,336,809.93 | Northern Builders/ Jomarcann Gen. Construction (JV) | PRDP | 2017-04-05 | 2019-02-17 | Completed | Ongoing with -9.793% Slippage as of 06/21/2019.(Slippage might change due to revised s-curve due to time extension # 03.).Revised Target Date = 08/31/2019 #
Actual completion date: August 14, 2020.
|
Bakun | Bagu | Construction of Slope Protection, Bagu, Bakun, Benguet | Slope Protection | 15,500,000.00 | 15,469,306.39 | FB Bantales Engineering Construction | PRDP | 2017-10-11 | 2018-02-23 | Completed | Completed on February 21, 2018 with 2 suspensions |
Kabayan | Batan | Improvement of KM 49 - Ambakian FMR | Roads | 203,655,000.00 | 198,182,697.03 | FIAT CONSTRUCTION SERVICES | PRDP | 2017-05-10 | 2018-11-30 | Terminated | 1) On-going with 15.29% accomplishment - Total Cost Incurred PhP 30,302,134.38 as of March 2018 with 9.35% slippage
2) Suspended as of November 15, 2017 for the preparation of Variation Order.
3) Still suspended as of October 2018 |
Bakun | Ampusongan | Construction of Consolidation Facility | Building | 3,222,000.00 | 3,217,564.23 | Reasons Construction and Supplies | GOP,PLGU,DA-PRDP-TRUST FUND | 2017-12-26 | 2018-07-13 | Completed | Completed and usable |
Mankayan | Guinaoang-Suyoc | Improvement and road upgrading of Guinaoang-Suyoc-Gambang Provincial road | Road | 11,500,000.00 | 11,491,647.77 | Buganheirs Eng'g & Construction (Allan Fuchigami) | PRDP | 2019-03-25 | 2019-06-07 | Temporarily suspended | Suspended as of June 7, 2019 |
La Trinidad | Puguis | Improvement along Pico - Stockfarm Provincial Road | Roads | 6,994,870.60 | | jca general construction and engineering services | PCF DILG 2015 | 2016-07-21 | 2017-04-06 | Completed | with under run |
La Trinidad | Wangal | Construction of PDRRMF Office Building Located at Wangal | Building | 4,000,000.00 | 3,994,112.23 | Remnant Builders | Performance Challenge Fund (PCF) 2016 | 2017-12-05 | 2018-04-04 | Completed | Completed on May 24, 2018 with 3,994,112.23 total cost incurred |
Kibungan | Madaymen | Improvement and Upgrading of Halsema - Madaymen Provincial Road | Roads | 53,390,374.20 | | Stay Construction | PNRDP 2016 Trust Fund | 2016-04-09 | 2017-06-13 | Completed | with under run and liquidated damages |
Itogon | Ampucao | Construction of of Multi-Purpose Open Gym at Simpa, Ampucao (Phase II), Itogon | GYM | 4,000,000.00 | 3,674,744.90 | Jessie Construction Services | 20% PDF 2018 | 2019-03-04 | 2019-11-28 | Completed | with suspensions |
Kapangan | Lomon | Construction of Slope Protection at the Municipal Road | Road Improvement | 1,000,000.00 | 996,600.76 | Family Circle Construction | LDRRMF 2019 | 2019-09-30 | 2020-02-20 | Completed | Project Engineer: Dianne Joy B. Sangiao
Geotag by: JC |
Mankayan | Suyoc | Construction of Retaining Wall Along Suyoc-Gambang Road, Mankayan, Bengeut | construction of retaining wall | | 2,943,206.25 | Malco Construction | CSR-ABOITIZ FUND 2017 | 2018-12-20 | 2019-02-24 | Completed | Completed and usable. |
Atok | Naguey | Construction of Flood Control Along Sip-sip Naguey Provincial Road, Atok | Flood Control | 2,000,000.00 | 1,996,258.09 | REMNANT Builders | LDRRMF TF - 2018 | 2019-03-04 | 2019-06-12 | Completed | Completed |